DOVER & COMPANY v. UNITED PACIFIC INSURANCE COMPANY
Docket No. 11632
Court of Appeals of Michigan
February 25, 1972
38 Mich. App. 727
R. B. BURNS, P. J., and LEVIN and T. M. BURNS, JJ.
Appeal from Montmorency, Philip J. Glennie, J. Submitted Division 3 November 3, 1971 at Grand Rapids.
DOVER & CO v UNITED PACIFIC INSURANCE CO OPINION OF THE COURT
- GUARANTY — SURETY — NOTICE OF CLAIM — CONDITIONS PRECEDENT — STATUTES.
Compliance with the statute requiring a subcontractor, who de-sires to recover on a surety bond, to give notice to the appli-cable state agency within 60 days after furnishing the last materials or, performing the last work is a condition precedent to recovery on the bond (
MCLA 570.101 ,570.102 ).
CONCURRENCE BY LEVIN, J.
- STATUTES — NOTICE OF CLAIM — PURPOSE. Notice of claim statutes are not aimed at forestalling litigation altogether by establishing an absolute time limit for the com-mencement of action, but rather mainly seek to provide a governmental authority with early warning so that it can assemble information in support of a defense on the merits while the evidentiary trail is still hot.
- STATUTES — NOTICE OF CLAIM — NONJURISDICTIONAL DEFECT.
The principle in tort cases that failure to comply with a statu-tory requirement concerning notice to a governmental entity is not jurisdictional and that noncompliance should not deprive
a citizen of his day in court except possibly where the gov-ernmental entity can show that it has been prejudiced by noncompliance, should be extended to nontort cases. - GUARANTY — SURETY — NOTICE OF CLAIM — STATUTES — DELAYED NOTICE.
A subcontractor which had earned a substantial sum of money by installing eight overhead doors in the state highway de-partment‘s maintenance garage should not be denied recovery on the principal contractor‘s performance bond even though the subcontractor failed to give notice of the general con-tractor‘s default to the highway department within 60 days, as required by statute, where the surety did not claim that it was prejudiced by the subcontractor‘s delaying in giving notice (
MCLA 570.102 ).
Appeal from Montmorency, Philip J. Glennie, J. Submitted Division 3 November 3, 1971 at Grand Rapids. (Docket No. 11632.) Decided February 25, 1972.
Complaint by Dover & Company against United Pacific Insurance Company to recover on a surety bond. Summary judgment for plaintiff. Defend-ant appeals. Reversed and remanded with instruc-tions.
John T. Garey, for plaintiff.
Cholette, Perkins & Buchanan (by Sherman H. Cone), for defendant.
Before: R. B. BURNS, P. J., and LEVIN and T. M. BURNS, JJ.
R. B. BURNS, P. J. Plaintiff, a subcontractor, agreed to furnish labor and materials to the prin-cipal contractor in completing a construction con-tract with the State Highway Department. In ac-
Plaintiff brought this suit against defendant-surety to recover the unpaid balance on the con-tract between plaintiff and its defaulting principal contractor. One of the controversies at the trial level concerned the effect of plaintiff‘s failure to serve notice upon the State Highway Department within a statutorily-required 60-day period.
“In the case of a subcontractor, he shall within 60 days after furnishing the last material or sup-plies or performing the last work covered by his subcontract, serve a written notice in duplicate upon the board of officers or agents contracting on behalf of the state * * * , that he is a subcontractor for the doing of some part of such work * * * and that he relies upon the security of the bond by this act required to be given by the principal contractor, and the said board of officers or agents shall within 10 days thereafter furnish a copy of such notice to the sureties for the principal contractor.”
Nevertheless plaintiff‘s motion for summary judgment was granted on the following grounds set out by the trial judge:
“Defendant, a paid surety had timely notice of plaintiff‘s claim and * * * defendant would suf-fer no injury or damage if held liable to the plain-tiff because of the fact that the State of Michigan has retained funds under the prime contract with the Trapp Construction Company [the principal con-tractor] which would indemnify the defendant from any injury or loss.” (Emphasis supplied.)
Plaintiff‘s evidence as to timely notice consisted of two letters. A letter dated August 23, 1970 from
The Court in People, for use of Wheeling Corru-gating Co v W L Thon Co, 307 Mich 273, 277 (1943) made compliance with the statutory notice provision “a condition precedent to recovery on the bond“.
Reversed and remanded for entry of judgment in accordance with this opinion.
T. M. BURNS, J., concurred.
LEVIN, J. (concurring). The plaintiff conceded in its answer to the interrogatories put by the defend-ant surety that it had not served notice of claim on the Michigan State Highway Commission as re-quired by 1905 PA 187;
Statutes requiring notice of claim serve a different purpose than statutes of limitations. Statutes of limitations establish an absolute time limit for the commencement of litigation. Statutes requiring notice of claim are not aimed at forestalling litiga-tion altogether, but mainly seek to provide a govern-mental authority with early warning so that it can assemble information in support of a defense on the merits while the evidentiary trail is still hot.
In recent years there has been a clear tendency in the cases to enforce notice of claim statutes less strictly than in former times. It has come to be recognized that it frequently would be excessive to treat noncompliance with a notice requirement as being as irremediable as a failure to commence an action within the time period established in a statute of limitation.
In Stacey v Sankovich, 19 Mich App 688, 697 (1969), we held that the plaintiff had adequately complied with the provision in the Motor Vehicle Accident Claims Act requiring that notice of intent to claim against the accident claims fund be served on the Secretary of State within one year (now six months) of the date that the cause of action accrues,1 and said:
“The notice requirement was not intended to be jurisdictional.”2
In Hussey v Muskegon Heights, 36 Mich App 264 (1971), we held that there had been substantial compliance with a statutory provision requiring as a condition to recovery for injury sustained by reason of a defective highway that notice of injury and defect be served on the governmental agency within 60 days. We said, p 270:
“We are satisfied that as the law now stands, deficiencies in a notice of injury and defect are not of jurisdictional import, and an injured person may not be denied his day in court on that account absent a showing by the governmental agency that it has been thereby prejudiced.”
In Grubaugh v St. Johns, 384 Mich 165 (1970), the Michigan Supreme Court held that the 60-day notice requirement of the general highway statutes3 violated the Due Process Clause when it was sought to apply
This evolving principle, that failure to comply with a notice requirement is not jurisdictional and that such a failure should not deprive a citizen of his day in court except possibly where the governmental agency can show that it has been thereby prejudiced — developed in cases where personal injuries were suffered, and (with the exception of Grubaugh) a timely but incomplete notice was given — should, in my opinion, be extended to nontort cases and to cases, as here, where no notice at all was timely given.
There is no claim on the part of the surety in this case that it was prejudiced by the short delay in the giving of the statutorily-required notice.4 Unless the
I concur rather than dissent because I am bound by the Michigan Supreme Court‘s construction of the statute in People for use of Wheeling Corru-gating Co v W L Thon Co, 307 Mich 273, 275, 277 (1943). In Thon there was a three-month delay in giving the notice. It was “conceded that the surety company was not damaged by failure to give timely notice in accordance with the statutory provisions“. The Supreme Court, nevertheless, declared that the statutory language “is mandatory, and, in our opinion, creates a condition precedent to recovery on the bond“.
Although there is some indication in People for use of Chasteen v Michigan Surety Co, 360 Mich 546 (1960), that the Supreme Court will apply this notice requirement with some flexibility, its most recent pronouncement on the subject reaffirms its adherence to its earlier construction of the statute. See People ex rel F Yeager Bridge & Culvert Co v Cooke Contracting Co, 372 Mich 563 (1964).
We are still in the early stages of the current development of notice of claim law. It is not clear how far the Supreme Court is willing to go in departing from former precedent. I, therefore, conclude that I could not properly declare that I
The law has a tendency to grow in separate pigeonholes, often without recognition that from a functional point of view there is no justification for differentiation in treatment. There is no sound reason why a deficiency in a notice of claim under a tort claims act should be treated differently than a deficiency in a notice of claim under a public con-tractor‘s act. In this connection, it is noteworthy that the issue of whether the surety or governmental agency was prejudiced by such a deficiency will ordinarily be more susceptible of proof in public contractor cases than in tort cases.
Now that the Legislature has eliminated altogether any requirement of notice of claim by subcontractors under public construction, alteration, or repair contracts except construction and maintenance con-tracts of the State Highway Commission6 — thereby evincing, at the very least, legislative recognition that such notices serve a less important purpose than they once did — it would be appropriate, and espe-
