95 Ct. Cl. 140 | Ct. Cl. | 1941
delivered the opinion of the court:
Plaintiff in January 1934 made two contracts, one for six and the other for ten Dolphin amphibian airplanes to be
Plaintiff’s first contention is that it was entitled to the full contract price, in spite of the fact that the defendant did not advertise for bids. On that basis plaintiff would recover $175,849.57. We think that the fact that plaintiff fully performed the contracts and that the defendant paid all of the agreed price on one of them, and a large part of it on the other, does not prevent the defendant from asserting the statutory requirement. Cf. Wisconsin Central Railroad Co. v. United States, 164 U. S. 190.
Plaintiff contends, in the alternative, that if it may not recover the contract price as such, it is entitled to recover its costs incurred in the manufacture of the airplanes, plus a ten percent profit. The defendant concedes that principle. But the parties disagree as to what those costs were. The Comptroller General’s audit allowed plaintiff the actual
Only fifty-nine planes of the Dolphin model were manufactured by: plaintiff. In¡ developing a new model, the first unit is built almost entirely by hand, and at great cost. Then tools, jigs and dies for multiple production of parts are made, and workmen are trained. Not until some three shop orders or groups of planes are manufactured do the costs level off to what becomes normal for regular production. On this model, the cost of building the one plane on the first shop order was $94,199.66, the sale price was $19,981.79; on the next shop order, the corresponding average figures for each plane were $49,522.48 and $24,016.94. The immediate cost of the planes built for the defendant was $26,725.50 per plane, and the contract price was $46,519.44 per plane.
Plaintiff contends that the development cost of the model is the amount by which the costs of the early built units, before costs leveled off to normal, exceeded the normal costs. It says that the defendant should bear its proportionate share of that development cost, sixteen fifty-ninths, because it got sixteen of the fifty-nine planes of this model which plaintiff manufactured. Defendant does not deny that development costs should properly be included, but asserts that plaintiff has not shown what they were with sufficient accuracy to enable the court to fix their amount.
It is true that plaintiff, at the time it manufactured the planes in question had no systematic method of allocating certain costs and calling them, on the books, development costs. Its need for such figures in the present case results from the fault of agents of the government in not advertising for bids as the statute required. Plaintiff should not be penalized for not setting up a system of bookkeeping to meet that contingency. We should not, therefore, dismiss plaintiff’s claim because of indefiniteness of proof unless the proof is really so indefinite as to make an intelligent judgment impossible. We think it is not so here.
We think this method of computation is acceptable, with one minor exception,
During the course of shop order 340, which carried the defendant’s contracts, the defendant requested certain changes in the tail structure, or empennage, of the Dolphin, to facilitate landing in rough water. Shop order 380, for nine commercial planes for another purchaser, was progressing through plaintiff’s plant concurrently with shop order 340, and as the first plane in shop order 380 was in a more advanced stage of construction than any of the planes on shop order 340, the redesigning and experimental work on the empennage was largely carried out on it. The development cost was carried on that shop order and none of it was allocated to shop order 340. Plaintiff proposes to allocate that cost by adding the total empennage costs on the two shop orders and dividing by the number of planes so as to make each plane in the two shop orders bear an equal amount of that cost. Since all the planes under the two orders were substantially similar, we think that method of computation is permissible, under the circumstances of this case. The empennage costs on both shop orders totalled $294,189.89. Allocating this amount proportionately to the number of planes in each group increases the cost of shop order 340 by $27,782.50.
We conclude, therefore, that plaintiff should have been paid development costs in the amounts of $54,683.46 and $27,782.50 in addition to the direct costs. It should have been paid a total of $665,029.72 (costs plus 10%). It was paid $654,630.92 on these contracts and the defendant is withholding from it on other contracts the sum of $86,-169.03. It may therefore recover $96,567.83.
It is so ordered.
United States Code, tit. 41, see. 5.
Our computation of the adjusted overhead is $2,205.86:
($2,409.92 — 2, 409.92) instead of $2,193.60.