The issue in this case is whether ORS 279.029(1), which requires that a “public contracting agency shall award [a] contract to the lowest responsible bidder,” applies to a public contracting agency’s award of a concession contract of the kind involved in this case. We hold that it does not.
Plaintiff, Double Eagle Golf, Inc., brought this action in the circuit court against the City of Portland (City)
1
under ORS 279.067,
2
claiming that the City had violated ORS 279.029 when it accepted another company’s bid to operate the concessions at a municipal golf course.
3
Both plaintiff and the City moved for partial summary judgment. The circuit court granted partial summary judgment for the City and dismissed plaintiff’s complaint with prejudice. Plaintiff appealed, and the Court of Appeals affirmed.
Double Eagle Golf, Inc. v. City of Portland,
Because the trial court granted partial summary judgment for the City, we must decide whether there are any genuine issues of material fact and whether the moving party (the City) is entitled to judgment as a matter of law.
See Seeborg v. General Motors Corporation,
In 1988, the Portland City Council amended the Portland City Code (PCC) Section 5.32.070 to establish a *607 procedure for awarding concession contracts at its municipal golf courses. In enacting that amendment, the City made the following findings:
“1. The Bureau of Parks has entered park concession agreements through a process in which the Purchasing Agent has solicited bids in the normal manner with the award going to the highest responsible bidder as outline[d] in Section 5.32.070 of the City Code.
“2. The Bureau of Parks recognizes the need to attract golf concessionaires who have the ability to maximize revenues to the City while at the same time being service oriented, with a proven reputation for dealing with the public in a way which reflects favorably on the Bureau.
“3. Based on the importance of both the financial and service aspects of golf course operation, the code should be amended to allow a selection process for golf concessions contracts which gives equal weight to financial return for the City and to the proven service ability of the proposer.” Portland City Ordinance No. 161118 (amending PCC § 5.32.070) (emphasis added).
Based on those findings, the Portland City Council amended the PCC to establish the following procedures for awarding concession contracts at public golf courses: A selection advisory committee would review contract proposals and recommend “the most advantageous proposal” to the superintendent of parks; the superintendent, in turn, would recommend that proposal to the commissioner in charge; after receiving a recommendation from the superintendent, the commissioner would grant a contract to the “highest responsible bidder.PCC § 5.32.070 (emphasis added).
In August 1992, the City issued a request for proposals to operate concessions at the City’s Heron Lakes Golf Course. In the request for proposals, the City notified prospective bidders that the “goals of this contract will be to maximize the revenue potential of the Heron Lakes Golf Course, while at the same time maximizing the potential of the Heron Lakes Golf Course as a service to the public.” (Emphasis added.) In September 1992, plaintiff submitted a bid to operate the concessions at Heron Lakes. Eventually, the City awarded that contract to another bidder, *608 Byron Wood Enterprises, Inc. (Wood), whose bid guaranteed less revenue to the City than did plaintiff’s bid. Plaintiff then brought this action against the City.
In its complaint, plaintiff alleged that the “[City’s] actions in authorizing a contract with Wood are in violation of ORS 279.029 in that Wood was not the lowest responsible bidder, and Plaintiff was.” The city moved for partial summary judgment, arguing that ORS 279.029(1) did not apply to the award of a golf concession contract, and that motion was granted. Plaintiff appealed.
The Court of Appeals affirmed the judgment of the trial court, holding that, under ORS 279.051, golf concession contracts are not public contracts, but rather are contracts for personal services to which ORS 279.029(1) did not apply.
Double Eagle,
The issue on review is whether ORS 279.029(1) applies to the award by the City
4
of a concession contract of the kind involved in this case. To resolve that issue, we begin with an analysis of the text and context of ORS 279.029(1).
PGE v. Bureau of Labor and Industries,
*609 The request for proposals in this case illustrates the foregoing proposition. Section 4 of the request for proposals, entitled “Contract Objectives,” provided that one of “the goals of this contract will be to maximize the revenue potential of the Heron Lakes Golf Course.” (Emphasis added.) To that end, the request for proposals requested that bidders include in their proposals, among other things, a guaranteed minimum annual payment to the City for revenue from the golf pro shop and restaurant businesses. As the request for proposals clearly demonstrates, the purpose of the golf concession contract was to raise the most possible revenue for the City from a responsible bidder. Plaintiff’s complaint supports that conclusion. Plaintiff’s complaint alleges that, notwithstanding plaintiff’s claim that ORS 279.029(1) requires that a “public contracting agency award the contract to the lowest responsible bidder” plaintiff should have been awarded the golf concession contract at issue here, because plaintiff’s bid guaranteed the City more annual income than did the successful bid. 5
Rules of statutory construction that bear directly on how to read the text of a statute support the conclusion that ORS 279.029(1) does not apply to the award of a concession contract.
See PGE,
It may be that, as a matter of policy, public contracting agencies should award concession contracts to the “highest responsible bidder,” the responsible bidder who would provide the agency with the most revenue from operating the concession. By doing so, the agency would ensure that the taxpayers would receive the highest monetary return in exchange for giving contractors the right to operate concessions in publicly-owned areas. We are not free, however, to insert in ORS 279.029(1) what the legislature has omitted. ORS 279.029(1) does not provide that public contracting agencies must award concession contracts to the highest responsible bidder. In summary, ORS 279.029(1) does not regulate the procedure for awarding concession contracts of the kind involved in this case by public contracting agencies. 6
Because there are no facts in dispute and because we conclude that ORS 279.029(1) does not, as a matter of law, apply to the award of a concession contract by a public contracting agency, we hold that the trial court did not err *611 when it granted partial summary judgment to the City. Accordingly, we affirm the decision of the Court of Appeals and the judgment of the circuit court, but for different reasons.
The decision of the Court of Appeals and the judgment of the circuit court are affirmed.
Notes
Plaintiff’s complaint also named as defendants various agencies of the City, including the Bureau of Purchases and Stores, the Bureau of Parks and Recreation, and Charles Jordan, the director of the latter agency.
ORS 279.067(1) provides in part:
“Any bidder adversely affected * * * may commence a suit in the circuit court for the county in which are located the principal offices of the public contracting agency, for the purpose of requiring compliance with, or prevention of violations of ORS 279.011 to 279.063, or to determine the applicability of ORS 279.011 to 279.063 to matters or decisions of the agency.”
Plaintiff also brought a claim under 42 USC § 1983. Plaintiff does not raise any issue on review regarding that claim.
The City is a public contracting agency under ORS 279.011(6).
Plaintiffs complaint alleges that its bid “guaranteed the City at least $84,000 per year income from services outside of greens fees and other facility generated income,” while the successful bidder only “guaranteed the City $40,000 for Years One and Two and $43,000 for Years Three to Five.”
In
Lasday v. Allegheny County,
499 Pa 434,
“As the Legislature’s use of the phrase ‘lowest responsible bidder’ makes clear, section 2001(a) is addressed to those situations where, unlike here, the County is spending public funds and thus should be attempting to secure for the taxpayers the least costly contract. Here, as lessor, the County is not spending money, but receiving it. The ‘lowest responsible bidder’ requirement is thus manifestly inapposite to this case, and if applied, would lead to the absurd result requiring the County to award its concession contracts to the concessionaire who promised to pay the County the least rent and the smallest concession fee.” Id.