Elizаbeth Darlene Dorrell (Dorrell) appeals after the circuit court granted summary judgment to respondent APAC-Carolina, Inc. (APAC). This case was certified from the court of appeals pursuant to Rule 204(b), SCACR. We reverse and remand.
Factual/Procedural Background
Dorrell was injured in a one-car accident on April 16, 1996. Apparently a gust of wind caused Dorrell’s car to veer to the right and drop off the road onto the dirt shoulder, which was eleven to twelvе inches below the road surface. Due to the drop, Dorrell lost control of her car, the car rolled several times, and she was thrown from her car into a ditch twenty-five to thirty feet away. Dorrell suffered permanent injuries and incurred significant medical bills.
The road had been recently repaved pursuant to a contract between the paving company, APAC, and the South Carolina Department of Transpоrtation (SCDOT). On April 22, 1996, six days after the accident, SCDOT issued an inspection report, accepting APAC’s work and returning the highway to SCDOT’s control. In its report, SCDOT stated that it had “accepted the highway back for State maintenance as of November 17, 1995.”
Dorrell eventually settled with SCDOT, leaving APAC as the sole defendant. APAC denied liability and subsequently filеd a motion for summary judgment. In support of its motion, APAC argued that the contract did not authorize APAC to rebuild, repair, or maintain the shoulder area. Instead, the contract required only that the shoulder area, and particularly areas with surrounding vegetation, be left in a “neat and presentable condition.” But because vegetation did not exist in the area where the accident occurred, APAC argued that it compliеd with the contract’s mandate. In addition, APAC described the eleven to twelve inch resulting drop-off as a “patent and obvious defect,” which SCDOT should have noticed upon inspecting the completed work. Finally, APAC argued that once SCDOT accepted the resurfacing work, APAC was no longer in control of the roadway and therefore no longer liable for injuries caused by the drop-off.
In response to APAC’s motion for summary judgmеnt, Dorrell filed the affidavit of her expert, Peter S. Parsonson, Ph.D, P.E. (Parsonson), who holds a doctorate in engineering and is a licensed professional engineer. In his affidavit, Parsonson directly contravened APAC’s interpretation of the contract terms and opined that APAC was responsible for the
Two months before trial, APAC filed a second summary judgment motion, reiterating the arguments in its initial motion and including two additional pieces of evidence: the deposition testimony of expert Parsonson and SCDOT’s responses to APAC’s requests for admission. Based on this new evidence, the trial judge — who was not the same judge who heard APAC’s initial motion — granted summary judgment to APAC, finding that (1) rebuilding, repairing, or maintaining the highway shoulders was not within the scope of APAC’s responsibility under the contract; (2) APAC’s work had been completed and accepted as of November 17, 1995; and therefore (3) SCDOT was solely responsible for the roadway and shoulders at the time of the accident. Additionally, the trial judge found that “APAC did not breach any duty to the plaintiffs which proximately caused the accident.”
Dorrell appeals the granting of summary judgment, asking this Court to consider the follоwing issues:
I. Did the contract between SCDOT and APAC limit APAC’s liability for negligent injury to third parties?
II. Was the defense of completion and acceptance a valid legal basis for granting summary judgment?
III. Was it an abuse of discretion for the trial judge to hear APAC’s renewed motion for summary judgment and use SCDOT’s admissions against APAC?
Law/Analysis
In reviewing a grant of summary judgment, this Court must find summary judgment proper when there is no genuine issue as to any material fact and the moving party is entitled to judgmеnt as a matter of law. Rule 56(c), SCRCP;
Osborne
I. APAC’s Liability to Third Parties
Dorrell argues that the APAC-SCDOT contract does not limit APAC’s liability for negligent injury to third parties. We agree.
A tortfeasor may be liable for injury to a third party arising out of the tortfeasor’s contractual relationship with another, despite the absence of privity between the tortfeasor and the third party.
Barker v. Sauls,
In a negligence action, a plaintiff must show that the (1) defendant owed a duty of care to the plaintiff, (2) defendant breached the duty by a negligent act or omission, (3) defendant’s breach was the actual and proximate cause of the plaintiffs injury, and (4) plaintiff suffered an injury or damages.
Steinke v. South Carolina Dep’t of Labor, Licensing and Reg.,
In the present case, we hold that APAC owed a duty of care tо the plaintiff, Dorrell, based on (1) the contractual relationship between APAC and SCDOT and (2) a common law duty of care.
APAC’s broad duty to the traveling public is established in at least two separate provisions of the contract. First, the
The contractor shаll provide all safeguards, safety devices and protective equipment and take any other needed actions as it determines ... to be reasonably necessary to protect the life and health of employees on the job and the safety of the public....
Second, the Red Book, 2 which is part of the contract, includes the following mandate:
107.09 Public Convenience and Safety. The Contractor shall at all times conduct work in suсh a manner as to provide for and insure the safety and convenience of the traveling public....
We also note that under the contract, the work was to “be done in accordance with the Specifications and in a good and workmanlike manner.” Therefore, based on the plain language of the contract, APAC had a duty to provide for the safety of the traveling public and to perform the work in a “wоrkmanlike manner.” This duty arises out of APAC’s contractual relationship with SCDOT, and the absence of privity between APAC and motorists such as Dorrell does not eliminate this duty.
In addition to its duties under the contract, APAC owed a common law duty to exercise due care, which existed independently of the contract with SCDOT.
See Kennedy v. Columbia Lumber and Mfg. Co.,
Moreover, at oral argument before this Court, APAC’s counsel explained that, in the area where the accident occurred, the road surface was already nine inches above the shoulder. Knowing this, APAC proceeded to lay the asphalt, adding another three inches, and increasing the drop to approximately twelvе inches. These facts alone create a jury question as to whether APAC breached its duty of care.
Accordingly, we hold that the APAC-SCDOT contract did not limit APAC’s liability for negligent injury to third parties. Like all motorists that traveled the stretch of highway recently repaved by APAC, Dorrell was a foreseeable plaintiff, and APAC’s duties to Dorrell stemmed from both the APAC-SCDOT contract and the common law.
II. Completion and Acceptance
Dorrell argues that the completion and' aсceptance defense was not a valid legal basis for granting summary judgment. We agree.
Historically, this Court has found that a contractor is not liable to third parties who have been injured as a result of negligent construction after the work has been completed and accepted by the other party to the contract or the owner.
Clyde v. Sumerel,
But as early as 1968, the completion and acceptance defense began to fall out of favor in South Carolina. In
Rogers v. Scyphers,
this Court refused to allow a building contractor to use the defense to avoid liability for an injury caused when the plaintiff fell on a negligently constructed stairway.
the entire weight of modem authority is to the effect that building contractors ... are liable for injuries to, or the death of, third persons occurring after the completion of the work and acceptance by the owner, where the work is reasonably certain to endanger third persons if negligently prepared or constructed.
Later, in 1975, this Court affirmed judgment for a person injured from falling into a six-fоot-deep hole left by a contractor for the telephone company, who had removed a telephone pole earlier that day.
Smith v. Fitton and Pittman, Inc.,
After affirming judgment for the injured plaintiff, the Court addressed the issue of whether the contractor could be relieved of liability based on the theory that the work had been completed and accepted. The Court explained that “[t]o the extent that this doctrine has not been eroded by
Rogers,
it is still viable.”
Id.
at 134,
Although
Smith
suggested that the completion and acceptance dоctrine, though eroded, remained viable, South Carolina courts have continued to limit its application. For example, the South Carolina Court of Appeals has explicitly refused to apply the doctrine in products liability cases, finding that the application of the doctrine “would undermine the whole concept of products liability.”
Stanley v. Montague Co., Inc.,
South Carolina has not been alone in disfavoring the completion and acceptance doctrine.
As late as the 1950s, the majority of jurisdictions adhered to the “completed and accepted rule.” Since then, the “completed and accepted rule” has been severely criticized and repudiated in most states and is now the minority rule while the “modern rule” has become the majority rule.
Emmanuel S. Tipon,
Modem Status of Rules Regarding Tort Liability of Building or Construction Contractor for Injury or Damage to Third Person Occurring After Completion and Acceptance of Work; “Foreseeability” or “Modem” Rule,
A building or construction contractor is liable for injury or damage to a third person even after completion of the work and its acсeptance by the owner where it was reasonably foreseeable that a third person would be injured by such work on account of the contractor’s negligence or failure to disclose a dangerous condition known to such contractor.
Id.
at 436. The rule has been applied in multiple contexts, including cases involving the construction of streets and highways.
Id.
at 534-35;
see also Louk v. Isuzu Motors, Inc.,
The modern view, rejecting the completion and acceptance doctrine, is reflected in the Restatement (Second) of Torts as well:
One who on behalf of the possessor of land erects a structure or creates any other condition thereon is subject to liability to others upon or outside of the land for physical harm caused to them by the dangerous character of the structure or condition after his work has been accepted by the possessor, under the same rules as those determining the liability of one who as manufacturer or independent contractor makes a chattel for the use of others.
Restatement (Second) of Torts, § 385 (1965).
South Carolina cases that have considеred and rejected the application of the completion and acceptance doctrine have incorporated foreseeability of harm in the analysis. For example, in
Smith v. Fitton,
the Court explained that given the location of the six-foot-deep hole left by the contractor who removed the telephone pole, “it was certainly inferable that this area would be traversed by invitеes as well as the owner.”
We join the majority of jurisdictions in deciding that a contractor’s duty of care is not extinguished upon the completion and acceptance of the contractor’s work. Liability should be governed by the same principles that govern ordinary negligence actions, and we see no reason why paving contractors should be treated differеntly from building contractors and product manufacturers.
Therefore, in light of
Rogers
and its progeny, the completion and acceptance defense was an improper legal basis upon
III. Abuse of Discretion
Dorrell argues that the trial judge abused his discretion by (1) hearing APAC’s renewed motion for summary judgment and (2) using SCDOT’s admissions against APAC. We disagree.
The trial judge had the discretionary authority to hear APAC’s renewed motion for summary judgment. That a different trial judge previously denied the motion did not preclude APAC from renewing its motion once new evidence came to light.
See Ballenger v. Bowen,
As to SCDOT’s admissions, the trial judge had the discretion to consider the impact of these admissions just as he would any other evidence. Moreover, the trial judge had the discretion to allow such evidence to be admitted outside of the scheduling order. Accordingly, the trial judge did not abuse his discretion.
Conclusion
Based on the foregoing analysis, we reverse the order granting summary judgment and remand this case for a jury trial in accordance with this opinion.
Notes
. A third defendant, APAC-Geоrgia, Inc., was dismissed by stipulation.
. "Red Book” is the common name for the "South Carolina State Highway Department Standard Specifications for Highway Construction,” which is typically incorporated into highway construction contracts. The 1986 edition of the Red Book was part of the contract in this case.
. In so holding, the Court "assumed that the defect in the stairway was a latent, concealed one, unknown to plaintiff or her husband prior to plaintiff’s injury....” Id.
. We note that this A.L.R. section supersedes the section relied upon by the Court in Clyde v. Sumerel and Nichols v. Craven.
