Plaintiffs brought suit for declaratory relief, and particularly for a judgment to the effect that, by governmental regulations, they were frustrated and prevented from complying with the terms of a contract to convey to defendants certain real property, and therefore entitled, as a matter of law, to rescind such contract. The trial court rendered judgment in favor of defendants. Plaintiffs appeal.
Having purchased land upon which they proposed to construct a new home, plaintiffs decided to sell their old home, and on February 15, 1946, entered into a contract to sell it and the land upon which it stands, to defendants for the sum of $13,000. The contract was executed on the standard deposit receipt form of one of the title companies. It provided that the sum of $1,000 had been paid as a deposit and that the balance of the purchase price was to be paid as specified in the attached “addenda.” There were the usual provisions that in the event of the failure of the purchaser to pay the balance as provided the seller could retain the deposit as liquidated damages; if the seller could not deliver title in 90 days the purchaser could demand his deposit back and be relieved from all obligation under the contract; and “Time is the essence of this contract.” The addenda states: “Seller is about to commence erection of a new home and agrees that when said new home has reached a state of erection that will enable him to move into same, he will convey, vacate and deliver to purchase— the above described property free and clear of all incumbrances. ... It is anticipated that said new home will be ready for occupancy not later than July 1, 1946, but because of unforeseen building difficulties that may arise seller does not desire to fix this date exactly, accordingly seller agrees to give purchaser notice in writing 30 days in advance of the exact date that seller will vacate said described property and deliver same to purchaser. Within 30 days after receipt of such written notice purchaser agrees to pay the balance of $12,000.00.”
On May 22, 1946, the President approved the Veterans’ Emergency Housing Act of 1946 (ch. 268, Public Law 388,
Immediately after signing the contract plaintiffs engaged an architect to draw plans for their new home. The court found that plaintiffs were unable to obtain the necessary building priorities and were temporarily unable to commence the erection of the home contemplated by them because of the government regulations. It also found that “the alleged hardship of plaintiffs was foreseeable but that said plaintiffs assumed the risk and that plaintiffs did or should have contemplated a state of war and the risks arising from it; that counter-performance by defendants is possible; . . . it is untrue that plaintiffs were prevented or completely frustrated in their efforts to comply with the terms of said contract; it is untrue that by reason of said alleged frustration, said contract cannot be complied with, and the court specifically finds that counter-performance was and is possible; it is untrue that plaintiffs are entitled to have the said contract rescinded and cancelled.” Defendants have excused the delay and are insisting on the performance of the contract.
Plaintiffs contend that time being made the essence of the contract, and they being prevented by government regulations from building their new home which they claim was the sole object of their making the contract, they were frustrated and entitled to rescind.
The doctrine of commercial frustration is defined in Willis-ton on Contracts, volume 6, revised edition, page 5419, as follows: “Performance remains entirely possible, but the whole value of the performance to one of the parties at least, and the basic reason recognized as such by
both
parties, for entering into the contract has been destroyed by a supervening and unforeseen event. This does not. operate
That the basic reason for entering into the contract, which it is claimed has been destroyed by the supervening event, must be recognized by
both
parties is emphasized in the case of
Brown
v.
Oshiro,
In
Lloyd
v.
Murphy,
“The question in cases involving frustration is whether the equities of the case, considered in the light of sound public policy, require placing the risk of a disruption or complete destruction of the contract equilibrium on defendant or plaintiff under the circumstances of a given ease [citing cases], and the answer depends on whether an unanticipated circumstance, the risk of which should not be fairly thrown on the promisor, has made performance vitally different from what was reasonably to be expected (6 Williston, op. cit. supra, § 1963, p. 5511; Restatement, Contracts, § 454). The purpose of a contract is to place the risks of performance upon the promisor, and the relation of the parties, terms of the contract, and circumstances surrounding its formation must be examined to determine whether it can be fairly inferred that the risk of the event that has supervened to caused the alleged frustration was not reasonably foreseeable. If it was foreseeable there should have been provision for it in the contract, and the absence of such a provision gives rise to the inference that the risk was assumed.
“. . . It is settled that if parties have contracted with reference to a state of war or have contemplated the risks arising from it, they may not invoke the doctrine of frustration to escape their obligations. [Citing cases.]” (Pp. 53, 54, 55.)
Applying the foregoing rules to the facts of this casé, it appears that the desired object or effect and purpose of the contract recognized by both parties was the purchase and sale of the old home. The construction of a new home was not the object, effect, or purpose of the contract, but had to do only with the time when the conveyance and delivery of the property sold would take place. It was merely an event by which consummation of the sale was to be timed. Delay in the construction of the new home was not a frustration of the desire to be attained. Both parties anticipated a delay and contracted in contemplation of it, although the precise cause of possible delay they had in mind was the shortage of labor and building materials rather than a governmental decree. Plaintiffs contend that the trial court should have taken judicial notice of the fact that “the shooting war was over, and our armed forces were being returned and discharged” and, therefore, there was no longer a war risk at the time of making the contract. However, assuming that the court should have taken notice of these facts, plaintiffs’ conclusions therefrom are erroneous. As a result of the acute shortages actually contemplated by the parties, government intervention for the protection and welfare of returning veterans became necessary and we cannot, under these circumstances, say that the possibility of such regulation was not reasonably foreseeable.
In
Levy
v.
Caledonian Insurance Co.,
in
Johnson
v.
Atkins,
The case of
20th Century Lites, Inc.
v.
Goodman,
The contract provided “Time is of the essence.” But that clause must be read and construed in conjunction with the addenda, which states that “unforeseen building difficulties . . . may arise” and therefore the seller did not desire to fix the date of delivery definitely. Plaintiffs contend that as they could not get priorities to obtain materials to start the building, there were no “building difficulties,” as this expression could only apply after building was actually commenced. That is certainly a strained construction of the language used. Delay in obtaining labor or materials whether the building has commenced or not is commonly considered ‘ ‘ building difficulties ’ ’; and in war times and periods following, delay in obtaining materials due to governmental regulations as well as otherwise may be reasonably expected. Mrs. Dorn testified that she anticipated a shortage of both labor and building materials.
The federal regulations upon which plaintiffs base their contentions, did not apply in any way to the house which they contracted to sell. They applied only to the house
Moreover, plaintiffs have in no way shown that they have been harmed by the delay. Plaintiff C. D. Dorn testified: “We are entire [ly] frustrated from ever endeavoring to fulfill that contract.” (Emphasis added.) This was his conclusion, but there is no evidence upon which to base it, nor to show any reason why they should not go on and fulfill the contract. The promisor who claims a frustration must show that he is harmed thereby. (Restatement of the Law of Contracts, § 288; Johnson v. Atkins, supra, p. 434.) In their closing brief plaintiffs say: “It does not seem reasonable, fair nor just, that a party should be held to a contract of this kind for a long and indefinite length of time. Time and changing conditions affecting performance change.” Yet they introduced no evidence whatever to show in what manner they have been harmed by the delay. As to the claimed hardship of having to move into the street, defendants have stated that they are willing to wait a reasonable time for plaintiffs to do what they originally contemplated—build themselves a new home.
In their reply brief plaintiffs quote
F. P. Cutting Co.
v.
Peterson,
The case does not come within the provisions of Civil Code section 1511 which provides that performance of an obligation is excused “When such performance ... is prevented ... by the operation of law.” The purchase and sale of the old home was in no wise prevented by operation of law. The time of conveying and delivering was merely delayed. In
United States Trading Corp.
v.
Newmark G. Co.,
The judgment appealed from is affirmed.
Peters, P. J., and Ward, J., concurred.
