*1 construction, it difficult to tory why is see apply equally does not construction Lilly non-priority context. line
Perhaps the entire of cases stem- perhaps
ming Ruschig wrong, point ques-
we should at some address that position
tion I take no on that en banc. juncture.
issue at this I think is worth out, however,
pointing ques- real by Judge
tion statutory raised Rader’s
analysis Lilly is not whether was an un- departure from Ruschig
warranted cases,
line of but whether entire line based on a fundamentally cases is §
flawed construction of 35 U.S.C. 1.
paragraph RUMSFELD, Secretary H.
Donald Defense, Appellant, COMPANIES,
APPLIED
INC., Appellee.
No. 01-1630.
United States Court of Appeals,
Federal Circuit.
DECIDED: April 2003. *2 Donovan, Jones, B. & of
Peter Jones Beach, CA, peti- Newport filed combined panel rehearing rehearing and en tion for Appellee. banc for the Stinson, Attorney, B. Trial Com- David Branch, Division, Civil Litigation mercial Justice, DC, Washington, Department of petition for the response filed a to the response him the were appellant. With McCallum, Jr., Attor- Robert D. Assistant Cohen, Director; General; David ney M. Di- Bynum, Deborah A. Assistant and response was counsel on the rector. Of Attorney, Trial Defense Tracy, Donald Center, Richmond, Logis- Defense Supply Richmond, Virginia. Agency, tics SCHALL, DYK, PROST, Before Judges. Circuit by Opinion filed Circuit for Court Opinion concurring-in- Judge SCHALL. filed Circuit part dissenting-in-part DYK. Judge PANEL ON PETITION FOR REHEARING.
ORDER
(“Applied”)
Inc.
has
Applied Companies,
panel
rehearing of
petitioned
10, 2002 decision.
December
court’s
Inc., 318
Companies,
Rumsfeld
(Fed.Cir.2002) (“Applied”).
F.3d 1317
out of a
This suit arises
Logistics
the Defense
between
(“DLA”),
the De-
component
Agency
Defense,
Applied. Under
partment of
specified period,
during the
Applied all of
purchase from
DLA was to
refriger-
types
two
DLA termi-
cylinders. After
storage
ant
the convenience
contract for
nated the
termi-
Applied submitted
government,
of contract
and breach
nation settlement
Among
officer.
contracting
claims to
alleged that
things,
other
had breached the contract
providing, in
response
of law. In
petition,
(“RFP”)
the request
proposals
fur-
government states that “[t]he record below
bidders,
prospective
nished to
faulty esti- does not reflect —either way whether, in
—
mates of the
number
it would fact, Applied delivered any
pursuant
items
*3
require during the
period
contract
and to the contract.” As far as Applied’s sec-
failing
then
to inform
when it
bidders
de-
point
concerned,
ond
is
termined the estimates were inaccurate.
urges that our decision is free of legal
Following the contracting officer’s denial
error.
of its claim for
profits,
appeal-
Having
Applied’s
considered
petition
ed to the Armed Services Board of Con-
and the
response, we con-
(“Board”)
Appeals
tract
provi-
under the
that,
clude
to the extent our decision states
sions of
Disputes Act,
the Contract
in definitive terms that there were deliver-
§§
U.S.C.
601-613. Id. at 1319.
contract,
ies under the
the decision is fac-
Ruling on cross-motions
summary
tually incorrect. Accordingly,
judgment, the Board concluded that DLA
IT IS ORDERED THAT:
had breached the
contract
negligently
(1)
fading
to inform
that the
estimates
Petition for Rehearing
grant-
is
in the RFP were inaccurate.
In
Ap
re
ed for
purpose
the limited
of correcting
Cos., Inc.,
plied
50,749, 50,
ASBCA Nos.
factual misstatements in the court’s deci-
51,662,
(CCH)
01-1
¶31,-
B.C.A.
sion issued on December
2002. That
154,729,
(Feb.
at
In petition for rehearing, Applied two types of refrigerant storage cylinders argues first that our decision contains a during the period from factual error. June Specifically, Applied asserts through June of incorrectly option we year. state pur- DLA request proposals (“RFP”), chased a 11,500 total of DLA approximately cyl- inders estimated its annual the contract. According to Applied, types two 62,945 while DLA of did order number cylinders, units, respectively. contract was terminated Prior to contract any award, before deliveries were DLA Ap- made. determined that the estimates plied’s point second is that our conclusion the RFP were greatly overstated. that Applied not However, entitled to recover its this information not commu- anticipated profits is as a incorrect matter offerors, nicated to any of the including Applied. Applied stances,” was awarded the con- I, or “ODSs.” Applied tract, ordering only approximate- but after 154,730. DLA, B.C.A. at which was ly quantity 10% cylin- estimated charged with building and maintaining a ders, DLA terminated the stockpile of Department ODSs for the 6,1995. February convenience on Defense, assessed the existing inventories ODSs, the amount of likely ODSs to be Following the denial of its termination recycled, used and and the amount of for convenience proposal settlement and a ODSs needed to ensure availability for claim for Applied ap breach of mission critical uses. In June of pealed to the Armed Services Board of assessment, based on its (“Board”) developed Appeals Contract pro under the estimates amount of R-12 and R- Act, visions of the Disputes Contract *4 114 refrigerants that (“CDA”). §§ it needed acquire U.S.C. to Ruling on and, by extension, cross-motions for the number of summary judgment, cylinders be required Board would concluded that DLA had store those re- breached frigerants. requirements 14, Id. July 1993, On DLA negligently failing to issued Applied inform that the the RFP for requirements estimates of cylinder requirements in RFP tract. DLA in estimated the RFP that 62,945 were inaccurate. Determination of the cylinders would be needed for the amount of was reserved fur for storage R-12 refrigerants 56,- and that Cos., ther proceedings. In re Applied cylinders would be needed for the Inc., 50,749, 50,896, 51, ASBCA Nos. and storage of R-114 refrigerants, for a total ¶ (CCH) 31,325, 01-1 B.C.A. 2001 WL 120,000 of approximately cylinders during (Feb. 2001) I”). (‘‘Applied year the one term of the contract.1 Id. DLA’s subsequent motion for reconsidera The RFP stated that the variation in actu- Cos., Inc., tion was In re Applied denied. quantity purchased al “plus be 03% 50,749, 50,896, ASBCA 51,662, Nos. and minus 03%.” The quantities estimated ¶ (CCH) 31,430, 01-2 B.C.A. 2001 WL were the same for option year. Id. On 2001) (May 21, II’’). (‘Applied The 11, 1993, or about August Applied, among Secretary of (“government”) Defense now others, responded to the Applied RFP. appeals the Board’s decision. Because the responsive was the lowest offeror. Board did not err in holding that had DLA In January of after initiating a breached its contract with Applied, af we pre-award survey, DLA determined firm. the reserve R-12 for and R- 114 refrigerants were considerably lower BACKGROUND than previously 154,731. believed. Id. at I. result, As a DLA established that facts, number of R-12 pertinent storage and R-114 cylin- which are not in ders dispute, that would be during up- are forth in needed Applied set They I. coming 1,037, are as follows: year were respec- tively. Id. The requirements stemmed procurement from a cylinders to store On June DLA awarded the R-12 refrigerants, R-114 which are contract to Applied, accept- classified as I “Class Ozone Depleting Sub- ing per its bid of cylinder. Id. In $52.60 1. The RFP and contract involved sizes types cylinders other refer to the two hereafter and models of that are "cylinders” at issue not issue covered the con- dispute. in this clarity, In the interest of we tract. award, repeated determination, DLA the notice unilateral the termination in the RFP. Under the contracting payment estimates contained officer un- denied contract, 20, 1994, period June der-absorbed overhead costs and unilater- 14, 1995, obligated DLA was to “or- ally Applied’s June settled termination claim for [cylinders] $295,253.00. der from contractor all the Ap- Id. This sum covered required purchased by that are to be plied’s terminating costs its work provided The contract also Government.” $31,718.00 progress relating [cylinders] specified that the “quantities in progress. to work Since al- the schedule are estimates and are ready partial payments had received purchased by not this contract.” The con- $295,253.00, totaling the contract the ter- incorporated tract various clauses from the contracting mination officer determined (“FAR”). Acquisition Regulations Federal any not pay- entitled by way ment of termination settlement. August Ap- DLA informed Id. plied time—that it the first had “dis- —for that a significant covered mistake was Applied subsequently submitted calculating made in the estimates.” Id. In contracting officer a claim for breach of place of the erroneous estimates contained Applied alleged that it had re- RFP both the and the faulty lied on DLA’s in prepar- estimates *5 provided new estimates of the minimum ing and submitting its bid and had entered quantities and maximum of R-12 R- and agreements into with subcontractors and 114 refrigerant cylinders actually pur- suppliers 154,733. accordingly. Id. at that it require. chased Id. DLA Based on the estimates contained in the eventually ordered a total approximately contract, asserted, RFP Applied and it had 11,950 units of R-12 R-114 cylinders, and expected generate to a profit per of $8.85 approximately quan- one-tenth of the total cylinder on approximately cylin- tity originally estimated. Id. ders, $1,057,530.80. for a total Id. According Applied, to negligence DLA’s in
DLA sought modify to the contract to preparation of the estimates constitut- reflect the new Applied estimates. re- ed a breach of Ap- contract that entitled sponded by submitting price a revised plied damages “to recover in the amount of per cylinder pay- and requesting $126.98 anticipated profit.” $615,945 ment “under absorbed indi- DLA replied by rect costs.” Id. proposing 12, 1998, On June the contracting officer pay per to unit for the quanti- reduced $79 issued a final denying Applied’s decision ty cylinders. Applied accept did not breach claim. Id. Though contracting 6, this proposal, and on February officer concluded that DLA had failed to DLA terminated the contract for conve- exercise due care in preparation of its 154,732. nience. Id. at It appear does not estimates, she negligence viewed that as from the record before us Applied giving to a change, rise constructive rather any cylinders delivered to DLA. breach, than a of the contract between Applied. Applied Accordingly, she ruled submitted termination for con- relief, Applied terms of proposal venience settlement was limited in the $1,791,499.00, an equitable adjustment amount of compensate it Changes for the shortfall in ordered Clause see FAR 1(b), 52.243-l(b), § DLA and for the overhead it 48 C.F.R. allegedly or to 52.243— absorbed in the preparing course of costs had incurred performing obligations plus profit, under the reasonable contemplated as 26, 1997, February Id. On by the Termination for Convenience Clause, 2(f)(2), see FAR 48 C.F.R. constituted a breach of the contract that 52.249— 2(f). § contracting The officer entitled Applied to compensatory damages: 52.249— stated that whatever costs could “The Government was ... negligent, and have established under a theory appellant of con- entitled damages change partial structive termination for breach I, of the contract.” Applied would have been paid part 154,734. convenience B.C.A. at The Board therefore of the termination settlement. granted Applied’s motion for summary judgment. Finally, while it noted that its
II.
decision only addressed the issue of Ap-
plied’s entitlement,
Applied appealed the
the Board
contracting
two
of-
observed
“[bjreach
ficers’ decisions
may
to the Board. Ruling on
include antici-
patory
parties’
profits.”
Id.
summary
(citing
cross-motions for
Carchia v.
United
judgment, the
Board addressed
Ct.Cl.
ques-
(1973)).2
tion of
May
DLA’s
On
negligent
whether
inclusion
Board
inaccurate estimates
the RFP
denied
was a
motion for
II,
reconsideration.
of its
contract with
01-2 B.C.A.
¶ 31,430.
Applied.
Noting
undisputed
timely
appealed
fact that
the Board’s
jurisdiction
“the Government
decision. We
knew it would
have
actually
pursuant
1295(a)(10).3
§
need
to 28
about one-tenth of the
U.S.C.
quantities in
solicitation,”
relying
on the deci-
DISCUSSION
sion of
Court of
Claims in
Womack
almost unbridled flexibility with respect to I, Applied 01-1 154,734. B.C.A. at In view the number of purchases. units it There- of the undisputed facts, the Board did not fore, implied there is an obligation upon err holding that DLA breached the re- government good to “act in faith quirements Applied and that use reasonable in computing care its esti- entitled to recover the damages that re1 Medart, mated needs.” 967 F.2d at suited 581. from the breach.4 Failure to meet obligation constitutes II. a breach of the resulting contract. Id. We above, As noted Board decided have stated “[w]here contractor can of liability. issue It did not address by preponderant show evidence esti- quantum. did, however, The Board make mates were ‘inadequately negligently or concerning statements the recovery to prepared, faith, not in good grossly or which it believed Applied was entitled unreasonably inadequate at the time the reason I, of DLA’s breach. made[,]’ estimate was Board stated that was entitled to could be liable appropriate “compensatory damages” for DLA’s resulting.” Id. (quoting Clearwater Forest breach, “[bjreach and it observed that Indus., Inc. v. United damages may anticipatory profits.” include (1981)). According- 154,734. II, Id. at In Applied the Board ly, to the extent that a esti- stated that because DLA’s breach was “to- mate is inadequately or negligently pre- tal,” Applied whole, “is entitled to be made pared, its inclusion without in a correction and here that includes anticipatory solicitation or contract constitutes a mis- they to the extent proved.” can be representation that, whether deliberate or 155,220. B.C.A. at The Board’s state- unintentional, amounts to a breach of con- ments regarding quantum suggest that it Womack, tract. F.2d at 800. *8 is appropriate for provide guidance us to This case squarely is controlled regarding proper Applied’s measure of jurisprudence that holds that negli recovery. See Fla. E. Ry. v. Coast Co. gently prepared States, can give estimates rise to United 647, 228 Ct.Cl. 660 F.2d noted, 4. As Womack, the Board plained found that DLA’s esti- misrep- ‘‘[a]n inadvertent negligently prepared. mates were Board The stemming negligence fully resentation is did not find part bad faith on the of DLA. A damaging as as a party deliberate one to the finding prerequisite of bad faith is not a to a who it relies on to his detriment.” 389 F.2d claim for upon breach of contract based at 800. faulty estimates. As the Court of Claims ex- 1336 (1981)
474,
put
position by
in a
(Though
judge
the trial
had
entitled to be
better
475
if
liability
recovery
[breaching party]
the issue of
and the
than
ruled
fully performed
was reserved
had
the contract.” Miller
quantum
determination
Robertson,
260,
243,
the court ad-
proceedings,
for further
v.
266 U.S.
45 S.Ct.
(1924).
thought
“ap- 73,
it
it
quantum
way,
because
Put
dressed
the entire
negligently
require.
estimated it would
purpose
Because the
of a
below,
agree
For the reasons
forth
we
set
award
put
non-breaching party
is to
is not
“in
good
position
a
as
would have
[it]
profits on
anticipatory
entitled to
the esti-
breaching party fully per-
been
had the
quantity
cylinders.
mated
formed,”
Bank,
Fargo
Wells
88 F.3d at
logical starting point
for a dam-
rule,
general
As a
when there has
ages
is an
analysis
understanding of the
been breach of
the non-breach
party’s
breaching
obligations under
ing party is entitled to an award of dam
above,
explained
contract. As
a require-
ages
place
good
posi
that will
it “in as
ments
“calls for the
tion as
would have been in had the
[it]
fill
speci-
all its actual
breaching party fully performed.” Wells
supplies
fied
Bank,
during
services
the con-
Fargo
N.A v. United
(Fed.Cir.1996).
period by
tract
purchasing from the awar-
F.3d
This rule
dee,
agrees
provide
who
them at the
damages, by ensuring
sets the floor for
Medart,
agreed price.”
party
no
at 581.
non-breaching
suffers
*9
pecuniary
Court of Claims and Federal Circuit
loss as
result of the breach.
cases
well,
support
It
ceiling
damages
anticipatory
sets the
for
the award of
party
profits
because the non-breaching
requirements
is “not
for the breach of a
contract all involve situations in which
guarantee
the
the company any actual sales.
government
perform
failed to
this obli-
government
contended
gation because it
had “actual
circumstances,
these
any award of lost
specified supplies
but,
and services”
in profits
speculative
and inappropriate.
another,
way
one
diverted that business
Id. The Court of
rejected
Claims
the gov-
away from
party
the
with whom it had ernment’s contentions. As for the first
contracted.
argument, the court stated:
In Locke v. United
agree
We
that nothing in the contract
(1960),
that Locke would have
(“GSA”)
under the contract.
Services Administration
forming
obligations
its
General
Thus,
Locke,
transcription
reporting
in
the
of Claims
and court
ser-
Id.
Court
for
was entitled to
agencies.
held that
the contractor
for various federal
Each
vices
(i) the amount of
recovery
require-
to the extent of
contract
included the standard
52.216-21(e).
that
typewriter-repair
§
business
existed ments clause found in FAR
(ii)
obtained;
that,
that it would have
its
“[ejxcept
That clause states
as this
ability
satisfy
requirements
the
for the
provides,
contract otherwise
the Govern-
stated
ment shall order from the Contractor all
California
Federal Bank.
specified in
supplies
or services
required
pur-
that are
to be
Schedule
In Tomcello v. United
by
activity
ac-
chased
the Government
(1982),
government
was a
result of the breach and
was the inclusion of negligently prepared
there
some
[was]
basis on which a
estimates in
breach,
the RFP. For that
estimate
reasonable
of the amount of the
Applied is not entitled to recover
prof-
Bank,
[could] be made.” Cal. Fed.
it
its would have made had
DLA fact
tory profits, *12 Snoqualmie in the government’s chase timber located that without lished” profit. Washing- have been a in the State of would National Forest breach there Bank, Applied at award prospectus 1349. ton. In its issued before Fed. Cal. contract, DLA requirement. Had States Forest cannot meet that the United properly preparing tim- duty by estimated the total volume of discharged Service estimates, or cylinder specified approxi- area to be propounding ber that the estimates 73,100 if told offerors Id. at 427. mately it had M board feet. award, before contract were inaccurate to Though Plywood’s agreement Everett sell, expected have would not Applied purchase the timber from the Forest Ser- sold, 120,000 cylin- contract, it would not have a vice was not words, profit Applied In ders. other of volume were material to the estimates in the form of lost attempts to recover inaccurate, The estimates were contract. would not anticipated sales as the total volume of timber Everett but for DLA’s “definitely” have existed able to cut and Plywood was breach. 46,081 contract M board under the was 27,000 feet, approximately fewer M or Applied damages in
Finally, awarding
than the
had
board feet
Forest Service
Ap-
would allow
form of lost
prospectus.
in the
estimated
If
DLA’s breach.
plied
profit
from
furnished a reasonable estimate
had
of Claims calculated the dam-
Court
for the term of the
cylinder
needs
resulting from the breach. The court
ages
have
things
one of two
would
the Forest
pointed out that because of
would have sub-
occurred: either
estimate,
Ply-
inaccurate
Everett
Service’s
a
awarded the
mitted
bid
been
expected
it
wood cut
less timber than
tract,
would have
perhaps
in which case it
bidding
per
when
on the contract.
Its
unit
on
number of
profit
earned a
cutting costs therefore increased. Accord-
sold;
declined to
would have
ingly,
Plywood
damages
Everett
“suffered
contract, in which case it would
bid on the
reasonably
... as a
foreseeable result of
extent that
profit.
earned no
To the
have
by failing
warranty,
defendant’s breach of
upon
based
it is allowed to recover
av-
advantages
to realize the
lower
cylinders included in
units of
which
have resulted”
erage rates
would
estimates, Ap-
negligently prepared
DLA’s
of timber.
cutting
larger
from
volume
pecuniary
plied would find itself
a better
Id. at 433. The court therefore calculated
propound-
DLA had never
position than if
plaintiff
average
“the
rate which
estimates and breached the
ed
inflated
...
paid
have
... had the contract volume
above,
a damages
As
such
noted
Then,
compute
realized.” Id.
been
conflict with the
squarely
award would
Plywood
to which Everett
non-breaching party
rule that a
“should
entitled,
applied
the court
the difference
than would have ac-
get
no account
more
rate,
Plywood
between that
which Everett
performed.”
crued if the contract had been
paid
would have
had the
es-
Int’l,
Delta Constr.
damages.5
claim for lost
for the ad-
plaintiffs
case,
cylin-
If,
no
appears to be
The measure of
mitted breach.
delivered,
is limited to
ders were
by our
majority
unsupported
uses is
the Termination
Conve-
recourse under
contrary
general
law
precedent and
Clause
nience of the Government
Moreover,
it leaves the
above,
of contracts.
Applied’s termi-
noted
contract. As
completely uncompensated for
breach of con-
tractor
claim and
nation settlement
anticipatory
provides
the same
almost no incentive
sought
tract claim
breach and
however,
explained,
profits.
we have
As
to avoid such breaches
recover such
not entitled to
Applied is
respectfully
I
dissent.
in the future.
proceed-
any further
profits. Accordingly,
no
in which
majority
cites
case
limited to
the Board will be
ings before
misrep
or negligent
was a bad faith
there
outstanding issues
disposing
any
other
in a
contract but
resentation
termination
Applied’s
connection
Ply
In Everett
were denied.
claim.
settlement
*14
States,
190
Corp.
wood & Door
United
CONCLUSION
(1969),
80,
“One give him the whole is to the value of the breaching party difference between receive had the expected to they benefits he accepted and the value goods Federal Glendale breach not occurred.” they if had been as warranted.” have had States, 239 F.3d v. United Bank FSB 2-714(2) (1989). in keeping § This is UCC (Fed.Cir.2001) (citing Re- “[o]rdinarily, the dam- with the rule that (Second) of Contracts statement of contract for a breach ages recoverable 344(a)(1981)). expectation party’s A § of the value of on the basis are measured having in “interest interest is the Corbin, su- promised performance.” by being put in as bargain benefit of his added). § pra, (emphasis have as he would been good position sure, was, in Re- To in this case there performed.” been be had the contract (Second) effect, warranty require- Contracts statement 344(a)(1981). damages Expectation § estimated; properly quan- ments were they are actu- provided are recoverable tity higher could have been or ordered reasonably foreseeable, ally contrary to uncertainty, lower. But such foreseen promi- the breach are caused assertion, majority’s does not bar re- sor, with reasonable cer- proved and are specifically not covery. Although we have tainty. issue, the lost we have addressed Bank, v. F.S.B. Bluebonnet Sav. repeatedly recognized gov- that when the (Fed.Cir.2001) bidding require- allows on either ernment added). leading authorities (emphasis contracts, it quantities or indefinite ments that the normal mea- agree on contracts is reasonable and foreseeable for contrac- profits. includes lost As sure of rely tors to estimates. put in the First Restatement Austin, Medart, Inc. Contracts, “compensatory damages will be (Fed.Cir.1992) (“[Presumably contractors amount of the losses given for the net [government’s] proffered esti- rely on the gains prevented, excess of caused and bids, their so the formulating mates possible.” Restatement savings made *16 good act in faith and use government must (1932). (First) § 329 cmt. a of Contracts estimated computing reasonable care Corbin, Arthur Linton Corbin on See also Indus., needs”); Forest Inc. v. Clearwater (Interim 2002) (quot- § Contracts 992 ed. States, 386, 227 Ct.Cl. 650 F.2d United approval); Re- ing First Restatement (1981) (“[A] 233, prospective purchaser 239 (Second) § of 347 statement Contracts reasonably expected should be to base his (1981). operating plans and cost estimates on gains how to calculate the To determine estimates]”); [government Womack v. prevented by Logistics Agency’s Defense 182 Ct.Cl. (“DLA”) breach, we should look to breach (1968) (“Assuming that the bidder 801 If DLA had warranty of cases. warranted rely on reasonably, acts he is entitled to Companies, Applied (“Applied”) Inc. representing Government estimates as pro- that the contract would conclusions.”). In- honest and informed work, worth of cylinders’ vide deed, very purpose quantity the compensate would be awarded to reliance; such other- estimates induce contractor for ex- the benefit wise, said, predecessor court as our pected bargain, not for the value of the “surplusage would be at best or estimate misrepre- contract as it was without the Womack, F.2d at deception at worst.” example, For sentation. Uniform provides, Commercial Code “The measure 801. reasonable,
Where such reliance is “[i]f measure of damages, if as it had never probability reasonable damage can be happened. The case, famous Bristol Seed established, clearly uncertainty as to the by Corbin, treated provides an illustration preclude amount will not recovery.” Ace- of the majority’s Corbin, approach. supra, Barram, Federal Reporters, Inc. v. 226 § 1026 (describing Miller, White v. (Fed.Cir.2000) F.3d (quoting (N.Y.1877)). N.Y. 118 case, In that Locke v. United 283 buyer purchased seed from a seller who (1960)). circumstances warranted that it fit for was human con- which the destroyed all value and sumption. It was in fact mixed seed made under the contract impossi good for animal buyer feed. The was due ble, courts have measured the value damages based on the difference between at right the time of the breach. the value of the seed as warranted and the Corbin, 1030; § supra, E. Allen Farns- value of seed, the actual including lost worth, § Farnsworth on Contracts 12.15 profits. Id. Under the majority’s theory of (2d 1998). too, ed. So at the time the damages, however, buyer could not government made the Ap contract with expected recover profits because there plied, it definite, was worth something would not have any; been the seed was which government’s estimate was high unfit for human consumption. ly probative. Alternatively, recovery could be based on other evidence of the contract Here contractor assumed the risk value—how valued the contract requirements would when it signed, example, or how actually be estimate; less than the other, similarly situated companies valued. contractor did not assume risk that the Farnsworth, contracts. See government’s requirements estimate would § supra, 12.15. Taking into account ex be deliberately or negligently misstated. pected estimate, variations from the The majority’s of damages measure thus Board profits should award lost based on effectively erases the breach. Far from the amount likely purchases given the “converting] the contract to one in estimate. particularly It is inappropriate guaranteed which DLA Applied a certain for the majority to foreclose lost profit business,” level of asserts, majority damages at this stage, before has ante awarding merely even had the opportunity present evi the general reflects measure of damages. dence on the matter. The majority holds that an award of lost consequence of today’s decision is overcompensate Applied be- may misrepresent *17 cause, had the government disclosed requirements with impunity long so as the actual requirements, Applied would have contractor suffers no increase in costs. either “submitted a bid” on the That seems to me policy bad to be as well it was or “declined to bid on the contract as bad law. I respectfully dissent. thus no made at all.” Ante at short, 1339. In the majority contends, it impossible have been for Applied to
recover on this be- breach,
cause even absent
“would not expected sell, have and it sold, 120,000
would not have cylinders.”
Ante at 1340. But that characterization
removes misrepresentation from the
