Donald H. Rumsfeld, Secretary of Defense v. Applied Companies, Inc.Donald H. Rumsfeld, Secretary of Defense v. Applied Companies, Inc.
Lead Opinion
Opinion for the Court filed by Circuit Judge SCHALL. Opinion concurring-in-part and dissenting-in-part filed by Circuit Judge DYK.
ON PETITION FOR PANEL REHEARING.
ORDER
Applied Companies, Inc. (“Applied”) has petitioned for panel rehearing of the court’s December 10, 2002 decision. Rumsfeld v. Applied Companies, Inc.,
This suit arises out of a requirements contract between the Defense Logistics Agency (“DLA”), a component of the Department of Defense, and Applied. Under the contract, during the specified period, DLA was to purchase from Applied all of its requirements for two types of refrigerant storage cylinders. After DLA terminated the contract for the convenience of the government, Applied submitted termination settlement and breach of contract claims to the contracting officer. Among other things, Applied alleged that DLA
Ruling on cross-motions for summary judgment, the Board concluded that DLA had breached the contract by negligently fading to inform Applied that the estimates in the RFP were inaccurate. In re Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-1 B.C.A. (CCH) ¶31,-325, at 154,729,
In its petition for rehearing, Applied argues first that our decision contains a factual error. Specifically, Applied asserts that we incorrectly state that DLA purchased a total of approximately 11,500 cylinders under the contract. According to Applied, while DLA did order that number of cylinders, the contract was terminated before any deliveries were made. Applied’s second point is that our conclusion that Applied is not entitled to recover its anticipated profits is incorrect as a matter of law. In its response to the petition, the government states that “[t]he record below does not reflect — either way — whether, in fact, Applied delivered any items pursuant to the contract.” As far as Applied’s second point is concerned, the government urges that our decision is free of legal error.
Having considered Applied’s petition and the government’s response, we conclude that, to the extent our decision states in definitive terms that there were deliveries under the contract, the decision is factually incorrect. Accordingly,
IT IS ORDERED THAT:
(1) The Petition for Rehearing is granted for the limited purpose of correcting factual misstatements in the court’s decision issued on December 10, 2002. That decision is hereby withdrawn and the decision attached to this Order is substituted in its place.
(2) In all other respects, the Petition for Rehearing is denied.
OPINION
This suit arises from a requirements contract between the Defense Logistics Agency (“DLA”), a component of the Department of Defense, and Applied Companies, Inc. (“Applied”). Under the contract, among other things, DLA was to purchase from Applied all of its requirements for two types of refrigerant storage cylinders during the period from June of 1994 through June of 1995, with an option year. In its request for proposals (“RFP”), DLA estimated its annual requirements for the two types of cylinders at 62,945 and 56,550 units, respectively. Prior to contract award, DLA determined that the estimates in the RFP were greatly overstated. However, this information was not communicated to any of the offerors, including
Following the denial of its termination for convenience settlement proposal and a claim for breach of contract, Applied appealed to the Armed Services Board of Contract Appeals (“Board”) under the provisions of the Contract Disputes Act, 41 U.S.C. §§ 601-613 (“CDA”). Ruling on cross-motions for summary judgment, the Board concluded that DLA had breached the requirements contract by negligently failing to inform Applied that the estimates of its cylinder requirements in the RFP were inaccurate. Determination of the amount of damages was reserved for further proceedings. In re Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-1 B.C.A. (CCH) ¶ 31,325,
BACKGROUND
I.
The pertinent facts, which are not in dispute, are set forth in Applied I. They are as follows:
The requirements contract stemmed from a procurement for cylinders to store R-12 and R-114 refrigerants, which are classified as “Class I Ozone Depleting Substances,” or “ODSs.” Applied I, 01-1 B.C.A. at 154,730. DLA, which was charged with building and maintaining a stockpile of ODSs for the Department of Defense, assessed the existing inventories of ODSs, the amount of ODSs likely to be used and recycled, and the amount of ODSs needed to ensure availability for mission critical uses. In June of 1993, based on its assessment, DLA developed estimates of the amount of R-12 and R-114 refrigerants that it needed to acquire and, by extension, the number of cylinders that would be required to store those refrigerants. Id. On July 14, 1993, DLA issued the RFP for the requirements contract. DLA estimated in the RFP that 62,945 cylinders would be needed for the storage of R-12 refrigerants and that 56,-550 cylinders would be needed for the storage of R-114 refrigerants, for a total of approximately 120,000 cylinders during the one year term of the contract.
In January of 1994, after initiating a pre-award survey, DLA determined that the reserve requirements for R-12 and R-114 refrigerants were considerably lower than previously believed. Id. at 154,731. As a result, DLA established that the number of R-12 and R-114 storage cylinders that would be needed during the upcoming year were 2,555 and 1,037, respectively. Id.
On June 20, 1994, DLA awarded the requirements contract to Applied, accepting its bid of $52.60 per cylinder. Id. In
In August of 1994, DLA informed Applied — for the first time — that it had “discovered that a significant mistake was made in calculating the estimates.” Id. In place of the erroneous estimates contained in both the RFP and the contract, DLA provided new estimates of the minimum and maximum quantities of R-12 and R-114 refrigerant cylinders actually purchased that it would require. Id. DLA eventually ordered a total of approximately 11,950 units of R-12 and R-114 cylinders, approximately one-tenth of the total quantity originally estimated. Id.
DLA sought to modify the contract to reflect the new estimates. Applied responded by submitting a revised price of $126.98 per cylinder and requesting payment for $615,945 in “under absorbed indirect costs.” Id. DLA replied by proposing to pay $79 per unit for the reduced quantity of cylinders. Applied did not accept this proposal, and on February 6, 1995, DLA terminated the contract for convenience. Id. at 154,732. It does not appear from the record before us that Applied delivered any cylinders to DLA.
Applied submitted a termination for convenience settlement proposal in the amount of $1,791,499.00, to compensate it for the shortfall in the cylinders ordered by DLA and for the overhead it allegedly absorbed in the course of preparing for and performing its obligations under the contract. Id. On February 26, 1997, by unilateral determination, the termination contracting officer denied payment for under-absorbed overhead costs and unilaterally settled Applied’s termination claim for $295,253.00. Id. This sum covered Applied’s costs of terminating its work in progress and $31,718.00 for profit relating to work in progress. Since Applied already had received partial payments under the contract totaling $295,253.00, the termination contracting officer determined that Applied was not entitled to any payment by way of termination settlement. Id.
Applied subsequently submitted to the contracting officer a claim for breach of contract. Applied alleged that it had relied on DLA’s faulty estimates in preparing and submitting its bid and had entered into agreements with subcontractors and suppliers accordingly. Id. at 154,733. Based on the estimates contained in the RFP and contract, Applied asserted, it had expected to generate a profit of $8.85 per cylinder on approximately 119,495 cylinders, for a total profit of $1,057,530.80. Id. According to Applied, DLA’s negligence in the preparation of the estimates constituted a breach of contract that entitled Applied “to recover damages in the amount of its anticipated profit.”
On June 12, 1998, the contracting officer issued a final decision denying Applied’s breach claim. Id. Though the contracting officer concluded that DLA had failed to exercise due care in the preparation of its estimates, she viewed that negligence as giving rise to a constructive change, rather than a breach, of the contract between DLA and Applied. Accordingly, she ruled that, in terms of relief, Applied was limited to an equitable adjustment under the Changes Clause of the contract, see FAR 52.243 — 1(b), 48 C.F.R. § 52.243-l(b), or to the recovery of the costs it had incurred plus a reasonable profit, as contemplated by the Termination for Convenience
II.
Applied appealed the two contracting officers’ decisions to the Board. Ruling on the parties’ cross-motions for summary judgment, the Board addressed the question of whether DLA’s negligent inclusion of inaccurate estimates in the RFP was a breach of its requirements contract with Applied. Noting the undisputed fact that “the Government knew it would actually need about one-tenth of the quantities in the solicitation,” and relying on the decision of the Court of Claims in Womack v. United States,
DISCUSSION
We review the Board’s decision under the standard set forth in the CDA:
*1334 The decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.
41 U.S.C. § 609(b). Because the parties do not dispute the facts relating to the preparation of the estimates, inclusion of the estimates in the RFP, and the termination of the contract, the sole question before us is whether the Board’s decision is tainted by legal error. We review the Board’s legal conclusions de novo. Rex Sys. v. Cohen,
On appeal, the government does not dispute that DLA’s estimates as to the number of R-12 and R-114 refrigerant cylinders that it would require during the contract term were significantly overstated. Neither does the government dispute that, prior to contract award, DLA was aware that the estimates were incorrect but did not inform Applied of the error until after the contract was awarded. The government asserts, however, that the Board erred as a matter of law (i) in holding that DLA breached its contract with Applied and (ii) in stating that, as far as damages are concerned, Applied is entitled to recover anticipatory profits. We address these contentions in turn.
I.
The government argues that a requirements contract only obligates an agency to purchase from a contractor all its requirements for the items covered by the contract, at the agreed-upon price; it does not obligate the agency to purchase a particular quantity of items. Starting from that premise, the government contends that DLA did not promise to purchase the estimated quantity of approximately 120,000 cylinders and that, consequently, its failure to do so did not breach the contract. In short, under the government’s reasoning, the fact that DLA awarded the contract to Applied knowing the estimates in the RFP were faulty is irrelevant for purposes of determining whether there was a breach of contract. Applied responds that it is the law of this circuit that, by preparing estimates negligently, the government may breach a requirements contract even if it in fact fulfills such needs as it has for contract items from the contractor. The government’s understanding as to the nature of a requirements contract is correct, but we agree with Applied that faulty estimates may form the basis for a claim that a requirements contract has been breached.
A requirements contract “calls for the government to fill all its actual requirements for specified supplies or services during the contract period by purchasing from the awardee, who agrees to provide them at the agreed price.” Medart, Inc. v. Austin,
While the quantity of items that the government will purchase under a requirements contract necessarily is uncertain, it is not irrelevant, as the quantity may impact both a contractor’s capacity to
This case is squarely controlled by the jurisprudence that holds that negligently prepared estimates can give rise to a claim for breach of a requirements contract:
It is not disputed that the Government knew it would actually need about one-tenth of the quantities in the solicitation. It did not exercise reasonable care when that knowledge, acquired well in advance of contract award, was not factored into the contract estimates. The Government was, therefore, negligent, and appellant is entitled to ... damages for breach of the contract.
Applied I, 01-1 B.C.A. at 154,734. In view of the undisputed facts, the Board did not err in holding that DLA breached the requirements contract and that Applied was entitled to recover the damages that re
II.
As noted above, the Board only decided the issue of liability. It did not address quantum. The Board did, however, make statements concerning the recovery to which it believed Applied was entitled by reason of DLA’s breach. In Applied I, the Board stated that Applied was entitled to “compensatory damages” for DLA’s breach, and it observed that “[bjreach damages may include anticipatory profits.” Id. at 154,734. In Applied II, the Board stated that because DLA’s breach was “total,” Applied “is entitled to be made whole, and here that includes anticipatory profits to the extent they can be proved.” 02-1 B.C.A. at 155,220. The Board’s statements regarding quantum suggest that it is appropriate for us to provide guidance regarding the proper measure of Applied’s recovery. See Fla. E. Coast Ry. Co. v. United States,
The parties’ respective positions on the damages issue are as follows: The government argues that when, under a requirements contract, an agency orders all the contract items it requires from a contractor, the contractor may not recover anticipatory profits to compensate it for the loss of sales that never occurred and to which it never was entitled under the contract. According to the government, a contractor’s recovery for negligently prepared estimates is limited to reliance damages and a price adjustment. Applied submits that it is entitled to a recovery of compensatory damages that includes anticipatory profits. Applied contends that the proper measure of damages to compensate for DLA’s breach is the profit it would have made on the entire quantity of cylinders that DLA negligently estimated it would require. For the reasons set forth below, we agree with the government that Applied is not entitled to anticipatory profits on the estimated quantity of cylinders.
As a general rule, when there has been a breach of contract, the non-breaching party is entitled to an award of damages that will place it “in as good a position as [it] would have been in had the breaching party fully performed.” Wells Fargo Bank, N.A v. United States,
Because the purpose of a damages award is to put the non-breaching party “in as good a position as [it] would have been in had the breaching party fully performed,” Wells Fargo Bank,
In Locke v. United States,
In opposing Locke’s breach claim, the government advanced essentially two arguments. First, it contended that since Locke’s company had entered into a requirements contract, which did not guarantee that any minimum quantity of services would be ordered, Locke could not recover lost profits for providing services to which his company had no entitlement under the contract. Second, the government urged, it only agreed to list Locke’s company, along with other typewriter-repair contractors. Because departments were free to choose any of the listed companies to perform the services at issue, the government’s performance of the contract by continuing to list Locke’s company did not guarantee the company any actual sales. The government contended that, under these circumstances, any award of lost profits was speculative and inappropriate. Id. The Court of Claims rejected the government’s contentions. As for the first argument, the court stated:
We agree that nothing in the contract would have prevented the Government from enlarging its own repair facilities to fill completely its needs. This would have left nothing to be awarded under the Federal Supply Schedule contracts. But the facts as alleged show that the Government did have some service requirements beyond its own capacity. Presumably, these requirements were awarded to contractors in the schedule. Plaintiffs chance of obtaining some of these awards, by being in the schedule and competing with the other contractors, had value in a business sense. The Government by its breach deprived plaintiff of this value.
Id. at 524 (emphasis in original).
In rejecting the government’s second argument — that an award of anticipatory profits would be speculative' — the court pointed out that it appeared that Locke “did have a chance of obtaining at least one-fourth of the total typewriter repair business let by the Government.” Id. at 525. The court therefore referred the case to the trial commissioner for further proceedings, directing the trial commissioner to determine: (1) the total amount of typewriter-repair business that was let by the government and for which Locke would have been eligible but for the government’s breach; (2) whether any material facts would have tended to prevent Locke from receiving its proportionate share of the business that was available; (3) the average unit cost normally incurred in performing the kind of repair work involved under the contract; and (4) the expenses
In Tomcello v. United States,
Finally, in Ace-Federal Reporters, Inc. v. Barram,
Recognizing that the contracts at issue were not typical requirement contracts and that they did not guarantee any of the individual contractors business, because the agencies were free to choose amongst
The combined teaching of Locke, Tomcello, and Ace-Federal is that the government breaches a requirements contract when it has requirements for contract items or services, but diverts business from the contractor and does not use the contractor to satisfy those requirements. In that case, the contractor is entitled to recover damages in the form of lost profits, provided it is able to meet the requirements for lost profits recovery noted in California Federal Bank. The critical point is that the government’s breach of its obligation “to fill all its actual requirements ... by purchasing from the awardee,” Medart,
This case, however, does not involve the kind of breach that occurred in Locke, Tomcello, and Ace-Federal. DLA did not purchase from third parties the refrigerant cylinders that it was obligated, under the contract, to purchase from Applied. Thus, unlike the government in those cases, it did not divert from a requirements contractor business that existed. To the contrary, it did order from Applied all of its actual requirements for refrigerant cylinders, although those requirements were far less than what had been estimated in the RFP. Eventually, the contract was terminated for the convenience of the government after Applied and DLA were unable to agree on an adjusted price for the cylinders. In short, the government did not commit the breach that occurred in Locke, Tomcello, and Ace-Federal; — diverting business that existed away from the contractor.
The government’s breach in this case was the inclusion of negligently prepared estimates in the RFP. For that breach, Applied is not entitled to recover the profits it would have made had DLA in fact had requirements to the extent of approximately 120,000 refrigerant cylinders. Allowing Applied to recover lost profits on the 120,000 estimated cylinders would effectively convert the contract at issue from one to satisfy all of DLA’s requirements to one in which DLA guaranteed Applied a certain level of business. Contract estimates are “not guarantees or warranties of quantity,” however. Shader Contractors,
Finally, awarding Applied damages in the form of lost profits would allow Applied to profit from DLA’s breach. If DLA had furnished a reasonable estimate of its cylinder needs for the term of the contract, one of two things would have occurred: either Applied would have submitted a bid and been awarded the contract, in which case it perhaps would have earned a profit on the number of cylinders it sold; or Applied would have declined to bid on the contract, in which case it would have earned no profit. To the extent that it is allowed to recover a profit based upon the 120,000 units of cylinders included in DLA’s negligently prepared estimates, Applied would find itself in a better pecuniary position than if DLA had never propounded the inflated estimates and breached the contract. As noted above, such a damages award would squarely conflict with the rule that a non-breaching party “should on no account get more than would have accrued if the contract had been performed.” Delta Constr. Int’l,
In our view, Everett Plywood v. United States,
The Court of Claims calculated the damages resulting from the breach. The court pointed out that because of the Forest Service’s inaccurate estimate, Everett Plywood cut less timber than it expected when bidding on the contract. Its per unit cutting costs therefore increased. Accordingly, Everett Plywood “suffered damages ... as a reasonably foreseeable result of defendant’s breach of warranty, by failing to realize the advantages of the lower average rates which would have resulted” from cutting a larger volume of timber. Id. at 433. The court therefore calculated “the average rate which plaintiff would have paid ... had the contract volume ... been realized.” Id. Then, to compute the damages to which Everett Plywood was entitled, the court applied the difference between that rate, which Everett Plywood would have paid had the government’s estimates been accurate, and the contract rate, for the volume actually cut, “to arrive at the excess payment ... resulting from plaintiffs failure to realize the lower average rate contemplated.” Id. In other words, Everett Plywood was entitled to
Similarly, in Crown Laundry & Dry Cleaners, Inc. v. United States,
It does not appear from the record before us that Applied delivered any cylinders before DLA terminated the contract for the convenience of the government. If any cylinders were delivered, Applied ■ should have the opportunity to establish that it is entitled to an equitable adjustment in the price of those cylinders because it relied on DLA’s negligent estimates and, as a result, suffered damages. We note that, in denying Applied’s breach claim, DLA’s contracting officer referenced such an approach. The contracting officer noted that “[a]n equitable adjustment compensates for changes by paying a contractor its increased costs resulting from the change, plus an allowance for profit on that cost.” See United States v. Callahan Walker Constr. Co.,
If, as appears to be the case, no cylinders were delivered, Applied is limited to recourse under the Termination for Convenience of the Government Clause of the contract. As noted above, Applied’s termination settlement claim and breach of contract claim sought the same anticipatory profits. As we have explained, however, Applied is not entitled to recover such profits. Accordingly, any further proceedings before the Board will be limited to disposing of any other outstanding issues in connection with Applied’s termination settlement claim.
CONCLUSION
The decision of the Board holding that DLA breached its requirements contract with Applied is affirmed.
COSTS
No costs.
AFFIRMED.
Notes
. The RFP and contract involved other sizes and models of cylinders that are not at issue in this dispute. In the interest of clarity, we hereafter refer to the two types of cylinders at issue as the "cylinders” covered by the contract.
. The Board denied Applied’s claim for anticipatory profits for the option year that DLA did not exercise. The Board also denied the government's motion for summary judgment dismissing Applied's appeal of DLA's unilateral determination of the termination for convenience settlement. Applied I, 01-1 B.C.A. at 154,734. Since the termination settlement claim and the breach of contract claim sought the same anticipatory profits, the Board sustained both appeals "with the understanding that one of the appeals will be dismissed during the quantum phase after an agreement is reached or a determination is made as to the date when interest begins.” Id. at 154,-735.
. We have exclusive jurisdiction "of an appeal from a final decision of an agency board of contract appeals pursuant to section 8(g)(1) of the Contract Disputes Act of 1978.” 28 U.S.C. § 1295(a)(10) (emphasis added). The CDA provides that all claims must first be submitted to the contracting officer for a decision. See 41 U.S.C. § 605(a); Dewey Elecs. Corp. v. United States,
In this case, Applied appealed two contracting officers' decisions to the Board. Applied I, 01-1 B.C.A. at 154,733. In the first decision, the termination contracting officer denied Applied entitlement to under-absorbed overhead costs. In the second decision, the contracting officer denied Applied's claim for breach of contract. For its part, the Board only decided entitlement. Id. at 154,734. Accordingly, since the contracting officer did not decide quantum, but decided only entitlement, the Board's decision on entitlement is final and appealable to this court. See Dewey,
. As noted, the Board found that DLA’s estimates were negligently prepared. The Board did not find bad faith on the part of DLA. A finding of bad faith is not a prerequisite to a claim for breach of contract based upon faulty estimates. As the Court of Claims explained in Womack, ‘‘[a]n inadvertent misrepresentation stemming from negligence is fully as damaging as a deliberate one to the party who relies on it to his detriment.”
. The case on which the Board relied for the proposition that Applied's breach damages may include anticipatory profits, Carchia,
. In Cactus Press, the Board rejected the contractor’s claim because it was untimely. In HKH Capitol Hotel Corp., the contractor's claim was barred because the contractor did not seek clarification of a patent ambiguity in the contract relating to the estimate. 98-1 B.C.A. ¶ 29,548 at 146,472
Concurrence Opinion
concurring in part and dissenting in part.
In the present contract the government undertook two relevant obligations: (1) to purchase its actual requirements from the plaintiff and (2) to accurately estimate its requirements. There was no breach of the first obligation, but the majority holds that the second obligation was breached because the government, either in bad faith or negligently, provided an incorrect estimate. I am in full agreement with the majority so far. Having found that the second obligation was breached, however, the majority unaccountably denies the plaintiffs claim for lost profits for the admitted breach. The measure of damages the majority uses is unsupported by our precedent and contrary to the general law of contracts. Moreover, it leaves the contractor completely uncompensated for the breach and provides almost no incentive for the government to avoid such breaches in the future. I respectfully dissent.
The majority cites no case in which there was a bad faith or negligent misrepresentation in a requirements contract but lost profits were denied. In Everett Plywood & Door Corp. v. United States,
In Everett Plywood the plaintiff contracted with the Forest Service to purchase timber on a parcel of government land for a price that would decrease over time, so that the plaintiff would pay less per unit for the timber the more timber it cut and purchased.
In none of the other cited cases involving negligent misrepresentation did the contractor seek lost profits. In Crown Laundry, the contractor sought only equitable adjustment of the contract, and the parties stipulated the actual dollar amount of damages at the outset were the contractor to prevail.
Without a controlling precedent, this court “applies] ordinary principles of contract construction and breach.” United States v. Winstar Corp.,
As the majority recognizes, the rule in this area is that lost profits are available to the non-breaching party, assuming foreseeability. As we have said,
*1344 “One way the law makes the non-breaching party whole is to give him the benefits he expected to receive had the breach not occurred.” Glendale Federal Bank FSB v. United States,239 F.3d 1374 , 1380 (Fed.Cir.2001) (citing Restatement (Second) of Contracts § 344(a)(1981)). A party’s expectation interest is the “interest in having the benefit of his bargain by being put in as good a position as he would have been in had the contract been performed.” Restatement (Second) of Contracts § 344(a)(1981). Expectation damages are recoverable provided they are actually foreseen or reasonably foreseeable, are caused by the breach of the promi-sor, and are proved with reasonable certainty.
Bluebonnet Sav. Bank, F.S.B. v. United States,
To determine how to calculate the gains prevented by Defense Logistics Agency’s (“DLA”) breach, we should look to breach of warranty cases. If DLA had warranted to Applied Companies, Inc. (“Applied”) that the requirements contract would provide 120,000 cylinders’ worth of work, damages would be awarded to compensate the contractor for the benefit of the expected bargain, not for the value of the contract as it was without the misrepresentation. For example, the Uniform Commercial Code provides, “The measure of damages for breach of warranty is the difference ... between the value of the goods accepted and the value they would have had if they had been as warranted.” UCC § 2-714(2) (1989). This is in keeping with the rule that “[o]rdinarily, the damages recoverable for a breach of contract are measured on the basis of the value of the promised performance.” Corbin, supra, § 1030 (emphasis added).
To be sure, in this case there was, in effect, only a warranty that the requirements were properly estimated; the quantity ordered could have been higher or lower. But such uncertainty, contrary to the majority’s assertion, does not bar recovery. Although we have not specifically addressed the lost profits issue, we have repeatedly recognized that when the government allows bidding on either requirements or indefinite quantities contracts, it is reasonable and foreseeable for contractors to rely on government estimates. Medart, Inc. v. Austin,
The majority holds that an award of lost profits would overcompensate Applied because, had the government disclosed its actual requirements, Applied would have either “submitted a bid” on the contract as it was or “declined to bid on the contract and thus made no profit at all.” Ante at 1339. In short, the majority contends, it would have been impossible for Applied to recover the profits on this contract, because even absent the breach, Applied “would not have expected to sell, and it would not have sold, 120,000 cylinders.” Ante at 1340. But that characterization removes the misrepresentation from the measure of damages, as if it had never happened. The famous Bristol Seed case, treated by Corbin, provides an illustration of the majority’s approach. Corbin, supra, § 1026 (describing White v. Miller,
Here the contractor assumed the risk that the government’s requirements would actually be less than the estimate; the contractor did not assume the risk that the government’s requirements estimate would be deliberately or negligently misstated. The majority’s measure of damages thus effectively erases the breach. Far from “converting] the contract ... to one in which DLA guaranteed Applied a certain level of business,” as the majority asserts, ante at 1339, awarding lost profits merely reflects the general measure of damages.
The consequence of today’s decision is that the government may misrepresent its requirements with impunity so long as the contractor suffers no increase in costs. That seems to me to be bad policy as well as bad law. I respectfully dissent.
. Equally inapplicable, so far as computation of damages is concerned, are the diversion cases, when lost profits recovery is allowed because the government has improperly diverted orders to other sellers. Ante at 1336-1339 (discussing Ace-Federal Reporters, Inc. v. Barram,