149 Ky. 347 | Ky. Ct. App. | 1912
Opinion of the Court by
Affirming.
In the summer of 1909, George Lutz, one of the appellants, agreed to hnild for George Young, an appellee here, a house on Young’s lot on the Bardstown road in Jefferson County, at the price of $2,350. When the house had been nearly completed, it was blown down. Photographs in the record evidence its wrecked state and that it entirely lost its identity and character as a building. Lutz did not undertake to rebuild or complete his contract, and the record admits his delinquency. The lumber for the house was furnished by the appellants Doll & Zoeller, the painting was done by appellants Peter, Meyer & Son, the hardware was furnished by appellant Albrecht & Heick Hardware Company, the foundation was constructed by appellant John Pegenhush, and certain • brick were furnished by appellant Southern Brick & Tile Company. All of these filed in the Jefferson County Clerk’s office their statutory mechanics’ or materialmen’s lien statement upon the property, .and either by direct action or by cross-petition sought to assert and enforce their liens in this action. Doll & Zoeller, in addition, sought to recover a personal judgment against Young for the lumber hill of $680.17. By cross-petition, Young sought to recover from Lutz, the contractor, certain amounts advanced to him as the work progressed. The case was prepared before the Master Commissioner. In conformity with his report, a decree was éntered dismissing the claims of Doll & Zoeller, the Albrecht & Heick Hardware Company, Peter Meyer & Son, the Southern Brick & Tile Company, save for a small personal judgment for material bought by Young
1. The facts having so eventuated because of the contractor’s default as that the ground-owner owes the contractor nothing, have these mechanics and material-men liens for work done and material supplied by them? Is their right to a lien direct, or is it through the route and right of the contractor? Can they have a lien when the contractor under whom they performed has none because of his own non-performance?
2. Do the facts in the record sustain Doll & Zoeller’s claim that Young bought the lumber from or agreed to pay them for it, with a consequent right in them to a personal judgment against him?
3. The foundation, the basis of John Fegenbush’s claim, is yet there. Is he entitled to his lien, notwithstanding our answer to question No. 1 is negative?
In the first place, it is- to be remarked that counsel for appellants concede that upon the authority of Louisville F. & M. Co. v. Patterson, Jr., 29 K. L. R., 349, Lutz is not entitled to his pay for the building, whether its wreck was occasioned by his own delinquency or the act of God.
The security afforded to mechanics and material-men by the statutes of the several States of the Union has no recognition in the common law, but rests and must find support in the statute creating the lien security. The language of each particular statute, therefore, must govern its interpretation without much of aid from the judicial declarations of other jurisdictions. The opinion of the learned chancellor below dismissed the lien claims upon the authority of Terrell v. McHenry, 121 Ky., 452. The opinion in that case turns upon the mechanics’ lien statute, as amended by the law of 1896, the law in force at the time of the happening of the facts in the record here. The court remarked that where the contractor failed to carry out his contract, and the owner of the property did not get what he contracted for but in fact got nothing of value, so that he
It is first argued that that opinion was written as upon the statute as it stood before the amendment of 1896, and in the spirit of the old statute which expressly provided that the subcontractors should have no lien if the contractor had none. The opinion expressly quotes and bases itself upon the amended or new statute ; and, therefore, it is idle to say that it is based upon the old.
Then it is argued that the court has departed from, or written counter to, the opinion in several later cases, which it becomes necessary, therefore, to notice:
Hightower v. Bailey, 108 Ky., 198. In this case, where the principal question was the constitutionality of the new statute, it was remarked that under the old law the owner was entirely safe, without notice of the claims of others, to pay his contractor when he pleased, while under the new statute the subcontractors would have their liens, even though the owner should have no notice of them and might “owe the contractor nothing.” Plainly, the court meant by the quoted phrase, a non-indebtedness resulting from some discharge of an indebtedness once having a valid existence; it did not at all mean an indebtedness always existent, a state of fact where there never had been, and never would be, .any
Browinski v. Pickett, 133 Ky., 420. Here the owner was to pay 80 per cent of the contract price to the contractor as the work progressed. When the house was some five-sixths complete and paid for, the contractor abandoned, and the owner completed it. The owner got his house; he received a consideration much larger than the subcontractor’s claim. The court held that the subcontractor, was entitled to his lien. It was simply a case of the owner’s paying the original contractor at his peril.
Thacker v. Bullock Lumber Co., 140 Ky., 463. In this case the facts were in brief that the owner, who had paid the contractor in full for the house, was adjudged to have to pay again to the extent of the lien of a subcontractor. The owner received the house for which he contracted; he paid for it at his peril and did not see that the money which he paid went to discharge the subcontractor’s debt. It has. no bearing upon the question here.
The cases of Schnute Holtman Co. v. Sweeney, 136 Ky., 773, and Canady, Gillum & Key v. Webb, 80 S. W., 172, are not in point further than that they establish that the subcontractor is entitled’ to his lien without respect to whether the owner may have paid the contract- or. In these cases, as well, the owner received that for which he paid.
Watts v. Metcalfe, 23 K. L. R., 2189. This case was decided upon a state of fact accruing before the adoption of the amendment of 1896. In substance, it was held that where the owner had paid the original contractor in part and had used the balance of the sum due him to complete the work, the subcontractor could have no lien. The court remarked that the subcontractor’s rights were dependent upon and could not be greater than the original contractor’s; which remark is seized upon by the appellants here to indicate that under the new law the subcontractor’s rights could be greater than the contractor’s. It is a patent non sequitur.
Henry Vogt Machinery Co. v. Lingenfelser, 99 S. W., 358. In this case, the property into which the material had been put by the one seeking the lien was destroyed by fire; and the court, in discussing the materialman’s rights, observed that the lien could be enforced against
We consider it unnecessary to discuss the other Kentucky authorities. Nor are we concerned by the very excellent discussion in briefs for appellants of the rules and judicial declarations from other jurisdictions; for the reason that, as we have above pointed out, each statute must speak for itself and must afford or deny relief by its own spirit and own terms. The rule of Terrell v. McHenry, upon full consideration, seems satisfactory and entirely sound to us. An analysis of the question under discussion brings us to consider whether in dealing with the original contractor, the owner or the subcontractor must be held to suffer from his delinquency. In other words, the question is as to who assumes the risk of his performing his contract. If the owner does, of course, it is fair that the subcontractor, in morals at least, would be entitled to rely upon the owner’s selection and judgment. If, on the other hand, the risk is that of the subcontractor, it is morally right that he should suffer if he misjudges the character and business capacity of the contractor under whom he engages. In the great majority of cases, the owner and subcontractors never see each other, nor is the owner even acquainted with the identity of the subcontractors. The subcontractors come in contact with the contractor and know that he exercises the shaping -hand which must result in a performance or a non-performance of the contract. It is, therefore, reasonable to assume that when they engagé to supply material or to labor under him, they look to his good faith, his character and his mechanical proficiency in the performance of the contract. They, therefore, take the risk as to him in these respects. The statute, however, does not leave the subcontractors to rely upon the contractor’s financial responsibility alone; but when that contractor has kept the faith and has delivered that which he undertook to deliver to the owner, the subcontractor has, by the express terms of the statute, his
The chancellor’s determination of the second question was purely a determination of fact. There is doubt in the record from the testimony; but upon a careful consideration of it we are inclined to believe the chancellor’s ascertainment of the fact was correct. The testimony for appellants Doll & Zoeller, is significant in one respect as leading to this conclusion. It is testified that Young, the owner, in his conversation with the' lumbermen, said to them that he had desired a bond of Lutz, the original- contractor, for the faithful performance of his contract, but that finding Lutz unwilling to give the bond, the arrangement was made that Young might pay the money direct to the lumbermen. It was not his obligation to pay the money direct to them, nor in any sense his undertaking to do so. On the other hand, it was a privilege accorded to him and to Lutz whereby Lutz was relieved of the necessity of giving the bond, and the owner of the possibility .of having to pay the money twice. The arrangement was an entirely proper and sensible one, but it did not extend so far as to become an obligation.
The third and last question in the record rests upon the claim of the appellant Fegenbush, that as the foundation which he furnished is yet there, he should be entitled to his lien upon it. If anyone were entitled to' a lien, it would not be Fegenbush alone; but the right would extend as well to every mechanic who had done work and every materialman who had put material into the entire building; for the statute does not give each mechanic or each materialman a lien upon that precise part of the building which he has furnished, but gives to each of them a co-ordinate and co-equal lien upon the property improved. The man who built the foundation,
.. For George Lutz, it is claimed that the judgment for $534 against him should be credited by the $250 payment on the foundation, because the foundation is> yet there. Lutz’s opportunity was first to build the ^building as it should have been built; and then failing this when the building blew down, to begin again and u.s,e this foundation; and using this foundation, to carry-out .his contract. Thereby he would have obtained the,; benefit of the foundation. Having undertaken to put up. a completed building, and having so perfomed that only the foundation is there, he cannot recover upon .a quantum meruit; and to allow him credit -for the • foundation would in substance be'an allowance of this -nature^ r ■ The answer given to the first proposition enunciated makes it unnecessary for us to discuss the remaining questions presented by briefs.
The judgment of the trial court is affirmed-