276 Mass. 242 | Mass. | 1931
The plaintiff brought this bill against the Duncan Construction Company, the city of Medford, and the New Amsterdam Casualty Company, hereinafter referred to, respectively, as the contractor, the city, and the surety, alleging that the contractor entered into a contract with the city for the construction of a school building and defaulted in performance of the contract. The plain
G. L. c. 149, § 29, required the officers contracting in behalf of the city to obtain security by bond or otherwise for the payment by the contractor and subcontractors for labor performed or furnished and materials used in the construction of the building. One of the contract documents referred to in the contract contained a provision that the contractor
By the contract the right was reserved in the city to retain from the monthly payments to the contractor a percentage of the value of labor and materials incorporated in the work and of materials stored at the site during the preceding month. Final payment was to become due sixty-three days after substantial completion of the work provided it be completed and the contract fully performed. The city having obtained security by bond was not required to furnish other
The bond was given to afford protection to laborers and materialmen as well as to the owner. Equitable Surety Co. v. McMillen, 234 U. S. 448, 454. In Hunter v. Boston, 218 Mass. 535, the bond purported to be security only for the faithful furnishing of material and doing of the work required of the contractor by the contract, while the contract provided that the payments were to be retained to settle claims for materials or labor furnished where claims have been filed with the city by subcontractors.
In Otis Elevator Co. v. Long, 238 Mass. 257, there was a finding by the master that both the money retained by the city and the bond were security, but in the case at bar there is no such finding as to the money retained by the city. The provisions for the retention of money by the city to which reference has been made must be held upon this record to be for the city’s own protection and not to provide security for labor and materials furnished, and the conclusion of the trial judge that the bond was the sole security under G. L. c. 149, § 29, for payment for labor furnished and materials used in the construction of the building was right.
It is contended by the surety that, because of two clauses numbered 9 and 18 in the printed parts of several of the contracts between the contractor and subcontractors who had filed claims, these claimants have waived their equitable liens or, if not, that their claims were prematurely filed. Clause number 9 in substance provided that these contractors waived and released all lien or right of lien then existing or that might thereafter arise for work or labor performed or material furnished under this contract, under any lien laws upon the building, the land upon which the same is situated, and upon any money or moneys due or to become due from any person or persons to the contractor,
The judge ruled that the waiver expressed in this clause applied only to such lien, if any, as the subcontractor might thereafter have upon any money or moneys due or to become due from the city to the principal contractor. If it be assumed that this clause has a proper place in a contract for the construction of a public building to which the lien laws do not apply, it cannot affect the rights of the subcontractors upon the facts in this case because the waiver by its terms is expressly confined to the money that is due or to become due to the contractor from the city.
Clause 18 provided for the retention by the contractor from the monthly payments of twenty per cent of the value of all work done and material furnished until the time for final payment, which is stated in that clause to be within sixty-one days after the acceptance of the building. The surety contends that because of this clause certain claims were prematurely filed and should be reduced twenty per cent of their face value. Under the statute claims must be filed within sixty days after the claimant ceases to perform labor or to furnish labor or materials. If the construction for which the surety contends were adopted it would be impossible for a claimant whose contract contains clause 18 to obtain the benefit of the security, at least as to a part of his claim, notwithstanding the fact that the contractor had broken his part of the agreement by abandoning the work and refusing to complete the building. The surety cannot successfully contend that this provision continued to be binding on a subcontractor after the contractor abandoned the contract.
All claims presented, with the exception of a part of the claim of W. W. Hall and Sons, were based upon contracts made directly with the contractor. The claim of this intervenor was based in part, upon a contract made with a subcontractor. For reasons already stated the contention of the surety that the bond does not secure a claim based upon a contract with a subcontractor is not tenable.
It appears from the master’s supplemental report that the claim of the Richmond Fireproof Door Company was mailed on the twenty-seventh day of September, 1927, and received and filed by the clerk of the city on September 28. By its contract this claimant was to furnish and work on kalamin and tinclad doors and standard fire door hardware for an undivided lump sum. The work on the doors was finished July 29, 1927, but on July 30 one of its workmen inspected them, oiled the hinges and eased the working of the doors so that they would close and open accurately and without difficulty. This work was found to be reasonably necessary in order to make a good job and was done in good faith. In these circumstances the claim must be held to have been filed in time. Thurston v. Blunt, 216 Mass. 264. See v. Kolodny, 227 Mass. 446. Winer v. Rosen, 231 Mass. 418.
The Building Finishing company assigned its claim to Commercial Finance and Discount Company on June 21, 1927, and afterwards was adjudged a bankrupt. The claimant furnished and delivered material which was wrought into the building, up to August 18, 1927. Its statement of claim was filed with the city clerk September 8, 1927. The only contention of the surety concerning this matter is that the assignor filed the statement of claim without referring to the assignment. There is nothing in the record to indicate that the rights of the surety have been in any way prejudiced by the fact that proof was in the name of the assignor, and no error appears in the part of the decree ordering the amount due on this claim to be paid to the assignee of the claimant. An assignee may by statute sue in his own name but he may also sue in the name of the assignor. G. L. c. 231,
Edward J. McHugh and Son used cinders as filling in the granolithic walks and under the loam of the lawn of the school. The surety contends that, while the plans indicate granolithic walks and also show that the lawn should be seeded, there is nothing to indicate that cinders were to be used under the lawn, and that the claim should be disallowed because it was an extra for which no provision was made and because the item was not certified by the architect. The master’s report does not indicate whether it was so certified. We cannot say that there was error of law in allowing the claim. Inasmuch as the only issue concerning this claim as stated by the master is the question of law whether the material so used can be the subject of lien under the statute, it is apparent that so far as the claimant’s rights depend upon questions of fact they have been decided in its favor. The cinders as used could be found to be reasonably necessary for the proper construction of the school, and upon such a finding the cost thereof would be provable against the statutory security, not as an extra but as a part of the principal contract. Reid v. Berry, 178 Mass. 260. Friedman v. County of Hampden, 204 Mass. 494, 511.
The International Casement Company had the subcontract for furnishing and installing casement windows. Its statement was filed with the city clerk on September 16, 1927, and the work so far as it was possible was completed on May 27, 1927, but because of the prosecution of the construction by other workmen additional work was required to put the casements in a satisfactory condition. Stone ornaments had been placed outside the windows which thereafter could not be fully opened without coming in contact with the ornaments. The windows had also been affected by the plastering, and the pivots, nails and other hardware had become distorted. This claimant was requested to correct these defects and, accordingly, on September 15 its workmen replaced the screws and hardware,
Upon being notified of the contractor’s default which occurred on August 17, 1927, representatives of the city and of the surety held a conference and the surety signed and delivered to the city the following letter: “It is under-stood that any action the City or the Schoolhouse Building Commission, or any other proper municipal authority may take in completing the work of constructing the Milton F. Roberts Junior High School through the use of the organization of the Duncan Construction Co.- or any part thereof or otherwise, shall be entirely without prejudice to any rights which said commission or the city may have against any one, and also without prejudice to any rights which the Duncan Construction Co., as principal, and the New Amsterdam Casualty Co., as surety, may have against the City of Medford or any one. The New Amsterdam Casualty Co., as surety, hereby waives any further notice to it requesting it to complete the work on said school and assents to the use of the organization, in whole or in part, of the Duncan Construction Co., which shall be without prejudice, as stated above.”
At a regular meeting of the schoolhouse building com
The trial judge in his order for interlocutory and final decrees found and ruled upon the facts found by the master and the inferences of fact to be drawn therefrom that, whatever other rights the city may have had upon the contractor’s abandonment of the work, the city elected to proceed as upon a termination of the contractor’s employment, in the manner provided by the contract, by taking possession of the work and materials then upon the premises, by employing the superintendent and other employees of the contractor to finish the work, and by providing the material therefor. By the final decree it was determined that the unpaid balance of the amount to be paid under the contract exceeded the expense incurred by the city in finishing the work and all damages suffered by the city because of deviation from the specifications, defective work, delay in completion and failure to furnish guaranty bonds and insurance, by the sum of $33,335.34, and that at the time the cross bill of the surety was filed this sum was owed to the contractor by the city in respect of the contract, and the surety by virtue of the assignment to it by the contractor is entitled to that sum with interest from June 11,1928.
The question whether the city completed the contract for the benefit of the contractor must be decided by us on the documentary evidence and findings of fact by the master, uninfluenced by the decision of the trial judge. Brockton Olympia Realty Co. v. Lee, 266 Mass. 550, 562. Upon the abandonment of the contract the contractor lost all right to recover from the owner any sums which otherwise might have been due it under the contract. Smedley v. Walden, 246 Mass. 393, 400. In this situation an intention to complete the contract for the benefit of the contractor would not be inferred unless made clearly to appear. Bernz v. Marcus Sayre Co. 52 N. J. Eq. 275. The provision as to termination is applicable only in case the owner terminates the employ-, ment upon the conditions and in the manner specified in the
The conclusion that the judge erred in finding and ruling that the contract was completed by the city for the benefit of the contractor makes necessary .certain changes in the decree as follows: The paragraphs numbered 8, 9, 10 and 11 of the decree are struck out. Paragraph 12 is struck out and a paragraph is to be substituted therefor and numbered 8 ordering the intervening petition of the Manufacturers National Bank dismissed, without making reference to any amendment of the bill by the surety. The paragraph numbered 13 is to be numbered 9 and to be amended by striking out in the second and third lines the words “within thirty days after the entry of this decree,” and substituting therefor the words “forthwith upon the entry of final decree after rescript,” and by striking out from the third and fourth lines thereof the words “the sum of $7,253.23 being,” and by changing the orders for payment of interest on the several principal sums named therein by computing it to the date of decree after rescript.
The paragraphs numbered 14, 15 and 16 are to bear respectively the numbers 10, 11 and 12.
When so amended the decree is affirmed with costs.
Ordered accordingly.