5 Indian Terr. 537 | Ct. App. Ind. Terr. | 1904
The appellant has filed assignments of error, containing 18 specifications, in which objection was niade and exceptions saved, the first of which is that “the court erred in refusing to direct the jury to return a verdict for defendant.” Appellant insists under this specification, first, that the building of its road into the Indian Territory by plaintiff was ultra vires, and that neither the building of it nor an obligation so to do
Under this specification appellant further insists that there was no agreement between appellant and appellee, and, if there was an agreement, that the evidence does not show a performance of the same by appellee. There are questions that were very properly submitted to the jury. The court could not take the case from the jury where there was evidence to support
The second specification of error is as follows: “The court committed error in giving contradictory instructions and instructions calculated to confuse the jury. The instructions complained of in this assignment being the entire charge as found on pages 115 to 120 of the transcript, and which the court is asked to consider without compelling the appellant to set it out in full.” This is not compliance with the rules of the court, and deserves no consideration whatever. But from a careful reading of the charge given by the court no one able to comprehend the English language clearly and forcibly stated, could regard said instructions as contradictory, or calculated to confuse the jury.
The third specification of error is the refusal of the court to allow witness Bayless to be asked on cross-examination the following: “Was the question of the interest that the Arkansas & Oklahoma Railroad Company should have in the town that would be laid out there discussed at that first meeting?” As the only conditions of the contract were that “said extension be of standard gauge, laid with new steel rails of not less than 60 lbs. per yard, all material to be new,” and the subscription should become due when> the railroad was completed to the town of Grove, Ind. Ter., and the first train is run thereon, and the subscription to become void if these conditions were not complied with on or before December 31, 1900, it was wholly immaterial
The fourth specification was the refusal of the court to allow witness Bayless to be asked 'whether the company did not put in ties after it had completed its road, and whether it had a schedule for its trains; both questions incompetent and immaterial, and were properly excluded by the court.
The fifth specification was permitting the appellee to ask witness Mayes if, when the subscription was deposited in the 'Bank of Southwest City, the company did not accept the proposition, and go to work along that line. This went to the question of liability of appellant on his subscription, and was material, and the court ruled correctly.
The sixth specification was a question as to the speed of the trains run, and was wholly immaterial.
The seventh specification was the refusal of the court to allow appellant to ask several questions, which were irrelevant and immaterial, and were properly excluded. Appellant also excepts to the striking out the following: “Well, they have changed it. The kind they have got there now is old and narrow.” This refers to the steel placed on that railroad, and should be considered in connection with what preceded the words stricken out. Both together are as follows: “Q. Do you- know the kind of steel that was put on this track, Mr. Remson? A. Yes, sir; it was' first-class. Q. What kind is there now? A. Well, they have changed it. The kind they have got there now is old and narrow.” It thus appears that the steel originally placed on that track was “first-class,” but that subsequently it was changed — by whom does not appear. This objection and exception simply represents the frjvolous character of many of the alleged errors.
The ninth specification was the giving of the following-instruction: “The court instructs the jury that if the defendant, among others, subscribed to the said railroad company for the purpose of inducing it to build its road into the town of Grove, Ind. Ter., and the representatives of the railroad company accepted the subscription, and acted on the same, and began work, then the court instructs you that the defendant is bound, and could not, at a subsequent date to the time the plaintiff acted upon said subscription, withdraw his subscription, or release himself from the obligation he had undertaken.” This instruction is a clear statement of the law applicable to the facts, as appellee contended had been shown in the evidence. 1 Beach, Con. 65. Philomath College vs Hartless, 25 Am. Rep. 511; Bates County vs Winters, 112 U. S. 327, 5 Sup. Ct. 157, 28 L. Ed. 744; Marie vs Garrison, 83 N. Y. 26; Ft. Worth & R. G. Ry. Co. vs Lindsey (Tex. Civ. App.) 32 S. W. 716; Armstrong vs Karshner (Ohio) 24 N. E. 897; Amherst Academy vs Cowls, 6 Pick. 427, 17 Am. Dec. 387.
The tenth specification was the refusal of the court to give the instruction No. 1 requested by appellant, and modifying and giving the same, as follows: “The plaintiff, before it can recover in this case, must prove, first, that the writing sued on by the plaintiff was signed by defendant or his duly authorised -agent; second, that the plaintiff accepted the same, or that defendant, after signing the same, allowed the plaintiff to build and complete the road without notifying the plaintiff that he
The eleventh specification was the refusal of the court to
The twelfth specification is a request for an instruction upon a proposition not mentioned in the pleadings, and foreign to the issues in the cause, and was properly refused.
The thirteenth specification was the refusal of the court to give the instruction No. 4 requested by appellant, and giving the same in a modified form, as follows: “In order for the defendant to recover in this case, it must have completed its road to Grove on or before December 31, 1900. The fact that rails and a train run over them is not conclusive that the road is entitled to recover, but the company, in order to recover, must show that the road on December 31, 1900, complied with the conditions of the defendant’s subscription.” The instruction requested was that the court should tell the jury that it was necessary, in order to find that the road had been completed, to find a state of facts not mentioned in the contract. The court very properly refused the request, and instructed the jury that they must find that the road on December 31, 1900, “complied with the conditions of the defendant’s subscription.” Substantial' compliance with the terms of the contract was sufficient tó entitle appellee to collect the subscription.
The fourteenth specification was the refusal of the court to give instruction No. 5 requested bjr appellant, and giving the same in a modified form, as follows: “If you believe from the evidence that after the writing sued on was signed by the defendant the plaintiff demanded that a new and additional writing be signed by the defendant, and that with the demand to sign an additional writing the plaintiff stated that, if the demand of the plaintiff was not complied with, the plaintiff would not build the road, the defendant had a right to treat the negotiations at an
The fifteenth and sixteenth specifications were the refusal of the court to give certain instructions requested by appellant. The first goes to the question as to whether a contract had been made, and the instructions which had already been given by the court, in our opinion, had fully covered that question. The second does not cover any question contained in the contract, or issue made in the pleadings, and both were properly refused.
The seventeenth specification was the alleged error of the court in giving certain instructions, which have already been considered under previous specifications.
The eighteenth specification was the refusal of the court to grant a new trial. We think the judgment of the court in