Dodsworth v. Hercules Iron Works

66 F. 483 | 6th Cir. | 1895

BURTON, Circuit Judge,

after stating the facts as above, delivered the opinion of the court.

The petition declared on the written contract. It alleged, as required by good pleading, that the plaintiff had fully performed the contract. This the plaintiff should aver, or, in the alternative, a willingness and readiness to perform, but for some conduct of the defendants sufficient in law to excuse; performance1. The plaintiff’s reply to the defendants’ answer admitted that a force pump had not been furnished, but, as an excuse, averred that it had been emitted at the special reepiest and instance of the defendants, and that its value was to be deducted fre>m the contract prie:e\ Upon this admission the defendants moved for juelgment upon the pleadings. This was overruled, and the plaintiff allowed to amend by inserting in the petition the facts as to the pump. This action of the court is the subject of the first two assignments of error. The; insislenete of appellants is that fills was and is a suit upem the contract, and that it is essential to any ree-overy in this suit, there being no common counts, that the plaintiff show a substantial compli-*486anee with, the terms of the contract, and that an admission that the contract was not completed by furnishing the power pump, whether that appears by the reply or on the evidence, is fatal to any recovery in this form- of action. Aside from all question as to the materiality of- this pump, or the effect of the acceptance alleged, the question presented by the refusal of the court to render judgment in favor of defendants, upon the admission in the reply that the pump had not been furnished, became immaterial upon the subsequent amendment of the petition, so as to show that the omission had been waived. The effect of the agreement by which this pump was to be omitted, and instead thereof a deduction made, was to amend the contract by parol before a breach. The contract was not one required by the statute to be in writing. But, if it had been, the result would be the same, under the ruling-in Swain v. Seamens, 9 Wall. 272, 273. That was a bill to compel the defendant to cancel and discharge a certain mortgage according to the terms of an agreement with the complainant. The defendant resisted performance, upon the ground that a building which the plaintiff was to erect on. his part did not in dimensions correspond with the stipulations of the agreement. The plaintiff replied that he (defendant) had acquiesced in the change, and had accepted the mill as built and completed. The court held that the defendant was estopped to deny that the contract had not been performed, or to set up the statute of frauds as a defense to the substituted performance, the court saying that:

“When a person tacitly encourages an act to be done, he cannot afterwards exercise his legal right in opposition to such consent, if his conduct or acts of encouragement induced the other party to change his position, so that he will he pecuniarily prejudiced, by the assertion of such adversary claim.”

In Fleming v. Gilbert, 3 Johns. 528, the plaintiff’s action was upon a bond. The defendant relied upon proof that the plaintiff had not performed the condition of the bond within the time specified therein. The plaintiff answered that the time of performance had by parol been extended; and so was the proof. The court, on appeal, said:

“The plaintiff’s conduct can be. viewed in no other light than as a waiver of a compliance with the condition of the bond, so far as it related to the mortgage on the record; and I see no infringement of any- rule or principle of law in permitting parol evidence of such waiver. It is a sound p>rinciple of law that he who prevents a thing being done shall not avail himself of the nonperformance he has occasioned.”

In Young v. Hunter, 6 N. Y. 207, the court said that:

“Independent of the question of waiver, if the defendants, by their acts, prevented the performance by the plaintiff of the conditions of his contract, he was excused from such performance. It is a well-settled and salutary principle that a party cannot insist upon a condition precedent when its nonperformance has been caused by himself.”

Concerning the manner in which a plaintiff might avail himself of the defendant’s waiver of performance in a particular way or time, it is said by an eminent text writer:

“The action having been brought upon the original contract, if the defendant set up that the plaintiff did not himself perform according to its *487terms, the plaintiff may reply that he was ready to do so, tint that it, was dispensed with by the defendant assenting to a substituted performance; and his proof ot' such assent is not considered a variance from his declarar tion.” Browne, St. Frauds, § 423.

In accord is Long v. Hartwell, 34 N. J. Law, 126, 127.

The conclusion must be that it ‘was not error to suiter the petition to be amended so as to set out this omission and the defendant’s assent thereto.

it was conclusively shown upon the evidence that the possession of this machinery was surrendered to the defendants ,in June or July, 1890, and that defendants had regularly used the same in the ordinary conduct of their business during the ice seasons of 1890, 1891, and 1892, and were still operating the same when this suit was begun and at the time of the trial. Defendants attempted to meet the force of this by putting in evidence two letters written by them in October, 1890, declining to accept the machinery, and notifying the plaintiff to remove it. The circuit judge, in respect to this conduct and its effect upon the defenses of the defendants, said:

“The plaintiff seeks to recover of the defendants, who were at the time the contract was made a partnership, the purchase price of an ice machine which the plaintiff w-as to erect npon the land belonging to the defendants. The purchase price stated in the contract is about $23,000. The plaintiff 'admits that it has received something over $7,000, and asks to recover the balance of the contract price of $23,000. The defendants, answering, say that they ought not to be compelled to pay for the ice machine, because it was not up to the contract. It appears from the evidence undisputed that the machine is still in the possession of the defendants, and that it was operated all the summer of 1890, and has been operated also- during- the summer of 1891, and during the summer of 1892, during the ice season of those years. It appeárs that the defendants in October, 1890, notified the plaintiff that they would not accept the machine, because it was not up to the contract. Now. in my view of the law, it was their duty, if they did not see fit to accept the machine, to- take it out, after notifying the plaintiff to take it out; and, the plaintiff failing, it was the duty of the defendants to take out the machine, and then bring- an action against the plaintiff with all the damages to which they had been put by reason of the failure of the plaintiff to- perform the contract and give them a machine up to contract. They*might, in that, charge the plaintiff with the cost of removing the machine, but they could not go on and use the machine after that, and then say they did not accept the machine. I am obliged, therefore, in my view of the law, which will doubtless be re-examined by a court of error, to hold that the only question in this case for you to consider is not whether the defendants are liable upon the contract, but it is to determine how much less than the contract price they ought to pay for the machine they have accepted under the contract.”

There was no dispute as to what the conduct of the defendants had been in regard to the retention and use of this machinery. While it is true that in October, 1890, the defendants said they would not accept, yet their subsequent conduct was an unqualified contradiction of what they had said. The contract provided that two-thirds of the purchase price should be payable "after the machinery had been running thirty days, provided it has performed the guaranty as herein stated.” The guaranty referred to was "that the machine will be capable of producing 25 tons of good, crystal, merchantable ice each twenty-four hours of continuous operation, *488provided it is kept in good order, and properly handled, and the temperature of the condensing water is hot above 60 degrees Fahrenheit.” It is manifest that the intention was that 30 days’ time should be allowed, after the machinery was put in operation, for testing its capacity, and within which defendants might elect to accept or reject. There was evidence tending to show that in July a test had been made, which established the capacity of the machine, and that defendant Rossa, who was acting as superintendent, declared himself satisfied as to the guaranty, and accepted the machinery. There was also evidence that the machinery Avas operated in the regular course of defendants’ business from that test down to the October letters, near the close of the ice season. Rut the circuit judge passed by all which had occurred prior to the October letters, and put the case, so far as the question of rescission was concerned, on the acts of the defendants after those letters. If it be assumed that defendants had not lost the right to reject the machinery when they wrote the October letters, they clearly did abandon that right by their subsequent conduct. The machinery which had been constructed and delivered was in professed compliance with the contract. The plaintiff delivered it as a compliance, and the defendants so understood. This is evident from their own letters. Under these circumstances, the defendants, at most, were entitled to a reasonable time to determine, after testing and experimenting, whether they would accept it as a substantial compliance with the contract. If the rejection announced in October, 1890, had been adhered to, and the vendor had refused to remove the machinery, it ran the risk of being made liable for all the expenses and hazards of storage, in addition to damages for breach of contract. On the other hand, the defendants became subject to the general rule, that “he who , seeks to reject an article as not in accordance with the contract must do nothing, after he discovers its true condition, inconsistent with the vendor’s ownership of the property.” Brown v. Foster, 108 N. Y. 390, 15 N. E. 608.

The fact which made the conduct of defendants conclusive upon their right of rescission was not the retention, for, under some circumstances, that might amount to little, but their use of the machine in the ordinary course of business for more than two years. There were three remedies open to the defendants when they discovered that this machinery was not in accordance with the contract. The first was to reject, and give notice of their determination to the vendor. This course, if adhered to, would have entitled them to sue for a return of purchase money, and such other damages as they had sustained by the failure of the vendor to furnish them the machinery according to the contract. If the machinery had not been removed by the plaintiff upon notice of rejection, then; the defendants might have removed and stored it, subject to the risk of the seller; or, if suffered to remain, they might have recovered storage. The second remedy open to defendants was to accept the machinery, and bring an action for breach of the warranty in the contract. The third remedy, having paid but part of the price, was to set off by way of counterclaim, when sued by the *489buyer for the balance due, the damages sustained by the failure of the machinery to comply with the contract. Benj. Sales (Corbin Ed.) § 1348. The right of rejection was lost by the long-continued use of the machinery, which use was utterly inconsistent with a purpose to resort to the first remedy which was open to them, and consistent only with a claim of title and ownership. Id. § 1356. The cases of Underwood v. Wolf, 131 Ill. 425, 23 N. E. 598, and Brown v. Foster, 108 N. Y. 387, 15 N. E. 608, and Vanderbilt v. Iron Works, 25 Wend. 665, are precisely in point. The learned counsel for appellants have cited and relied upon a class of cases concerning building contracts, which hold that the mere possession and use of a house constructed on one’s own' land will not, unattended by other circumstances, operate as a waiver of any conditions precedent in the contract under which it was constructed; and that a suit on the contract, for the contract price, may be successfully defended, notwithstanding such use and occupation, unless it is shown that the work was done in substantial compliance with the contract. The reason for distinguishing cases of that class from those concerning the sale or construction of machinery not so annexed to the. soil as to pass with it is well stated in Smith v. Brady, 17 N. Y. 188, where Comstock, J., said:

“The owner of (he soil is always in possession. The builder has a right to enter only for the special purpose of performing his contract. Each material, as it is placed in the work, becomes annexed to the soil, and thereby the property of the owner. The builder would have no right to remove the brick or stone or lumber after annexation, even if the employer should unjustifiably refuse to allow him to proceed with the work. The owner, from the nature and necessity of the case, takes the benefit of part performance, and therefore, by merely doing so, does not necessarily waive anything contained in the contract. To impute to him a voluntary waiver of conditions precedent from the mere use and occupation of the building erected, unattended by other circumstances, is unreasonable and illogical, because he is not in a situation to elect whether he will or will not accept the benefit of an imperfect performance.”

In the case before us the machinery was capable of removal. It had not become annexed to the soil, and for that reason the property of the owner of the soil. That it was capable of removal is shown by the October letters notifying the seller to remove it, and there is no evidence in the case in any way indicating a situation analogous to that of one occupying a house not built according to an agreement. This acceptance, though having the effect to pass the title to the defendants and to cut off any right to rescind did not, under the circumstances, operate to cut off defendants from their right, when sued for the price, to set off or recover by cross petition any damage which they had sustained by the failure of the machinery to comply with the terms and conditions of the contract. Manufacturing Co. v. Phelps, 130 U. S. 525, 9 Sup. Ct. 601. In Vanderbilt v. Iron Works, heretofore cited, the question involved was a contract to equip a steamboat with an engine. In an action for the price, it wTas held that the acceptance of the engine, though deficient in some particulars, would prevent the buyer, in an action for the price, from insisting upon the defects as a nonperformance of the condition precedent; yet the *490buyer was 'not cut off from showing such defects, and obtaining a reduction of the price, when sued for a balance due. The cases of Brown v. Foster and Underwood v. Wolf, heretofore cited, are also in point as to remedy of a buyer who has waived his right to reject in toto.

These conclusions operate to overrule defendants’ assignments of error Nos. 1, 2, 5, 6, 7, 8,‘ 9, 10, 11, 12, 13, and 17. Assignments Nos. 3, 4, and 16 were withdrawn on the argument.

The evidence that the power pump was omitted by consent, and that its value was $150, was quite conclusive. There was no error in the instruction to that effect, and the fourteenth assignment must be overruled.

The question as to whether the blue-print plans for the building and for the foundation for the freezing tank, as prepared by the plaintiff’s draftsman, were sent to and received by defendants, was submitted to the jury. There was evidence sufficient to support a finding to that effect. The court construed those plans, in connection with the contract, as imposing on the defendants the duty of building a foundation of five or six wall’s under the compressor, and that the plans showed that between those walls there should be cinders close up to the floor above. He also charged that if the defendants failed to build the foundation and fill in with cinders, as they were obliged to do, any failure of proper insulation' attributable to the failure to use cinders, as indicated on the blueprint plans, could not be charged to the plaintiff. We think there was no error in this, and the fifteenth assignment is therefore not: Well taken.

The defendants were given every opportunity to show, if they: could, any defects in the machinery furnished, or any want of capacity to perform the work it had been warranted to do. The verdict can bear but one construction, which is that the machinery was in substantial accord with the contract, and that the defendants had sustained no damage by reason of any failure to perform the contract..

On the whole case, we are entirely satisfied with the result. The judgment must therefore be affirmed.

midpage