DLN HOLDINGS, L.L.C. VERSUS KEITH GUGLIELMO, LAND RECORDS SUPERVISOR FOR PARISH OF ORLEANS
NO. 2021-CA-0640
COURT OF APPEAL FOURTH CIRCUIT STATE OF LOUISIANA
June 29, 2022
Judge Rosemary Ledet
APPEAL FROM CIVIL DISTRICT COURT, ORLEANS PARISH NO. 2019-07477, DIVISION “L-6” Hоnorable Kern A. Reese, Judge. (Court composed of Judge Roland L. Belsome, Judge Rosemary Ledet, Judge Sandra Cabrina Jenkins)
COUNSEL FOR INTEGRATED COMMERCIAL CONTRACTORS, INC./APPELLANT
Donald C. Douglas, Jr. Christopher K. LeMieux RIESS LEMIEUX, LLC 1100 Poydras Street, Suite 1100 New Orleans, LA 70163
COUNSEL FOR TRAPOLIN-PEER ARCHITECTS, A.P.C./APPELLEE
John I. Hulse, IV Brian A. Gilbert CONROY LAW FIRM, PLC 3501 N. Causeway Blvd., Ste. 500 Metairie, LA 70002
COUNSEL FOR DLN HOLDINGS, LLC AND DAVID FRANCIS/APPELLEES
AFFIRMED
FACTUAL AND PROCEDURAL BACKGROUND
This dispute arises out of a renovation project at the Pelham Hotel (the “Hotel“), located in downtown New Orleans (the “Project“). There are five parties to this dispute: (i) DLN, the owner of the property on which the Hotel is situated; (ii) Pelham Hospitality, LLC (“Pelham“), the Hotel‘s operator; (iii) Mr. Francis, the managing member of both DLN and Pelham: (iv) TPA, the Project‘s architect; and (v) ICC, the Project‘s general contractor.
From the Project‘s commencement through December 2017, ICC submitted ten Contractor‘s Applications for Payment; all ten applications were directed to “Pelham Hospitality 444 Common St., New Orleans, La. 70130.” In March 2018, Pelham terminated ICC for cause. ICC, in response, filed a lien on DLN‘s property for sums it claims were due it under the Construction Contract. Seeking to have the lien removed from the public records, DLN filed this mandamus action, in July 2019, against Keith Guglielmo, the Lands Records Supervisor for Orleans Parish, and ICC. Thereafter, ICC voluntarily removed the lien. DLN, however, remained a
In July 2020, ICC filed, in the mandamus action, a reconventional demand against DLN and an incidental, third-party demand against both Mr. Francis and TPA.4 The gist of ICC‘s reconventional demand was that it was improperly terminated for cause—as opposed to for convenience—under the Construction Contract.5 ICC asserted claims for breach of contract, termination-for-convenience damages, fraud, detrimental reliance, and unfair trade practices.
In response, the defendants-in-reconvention—Mr. Francis and DLN together, and TPA—filed peremptory exceptions of no cause of action and no right of action. Following a hearing, the trial court sustained all the exceptions and dismissed all of ICC‘s claims against all the defendants-in reconvention. The trial court refused ICC‘s request to allow leave to amend pursuant to
This appeal followed.
STANDARD OF REVIEW AND GOVERNING LEGAL PRINCIPLES
Whether a plaintiff has a cause of action and a right of action are both legal questions; hence, in detеrmining whether the trial court was legally correct in sustaining those exceptions, an appellate court is required to conduct a de novo review.6 No cause of action and no right of action are both peremptory exceptions. The function of a peremptory exception is “to have the plaintiff‘s action declared legally nonexistent, or barred by effect of law, and hence this exception tends to dismiss or defeat the action.”7
No cause of action and no right of action are legally distinct, are designed to serve different purposes, and are governed by different procedural rules. A major difference in the procedural rules governing these exceptions is that on an exception of no right of action, evidence is admissible at a hearing on the exception to either support or rebut the exception.8 Conversely,
When, as here, the issue is the lack of privity between the parties necessary to support a contract-based claim, an exception of no cause of action is the proper procedural device.11 In ruling on a no cause of action exception, a trial court must accept as true the facts alleged in the petition and decide whether the law affords any relief to the plaintiff assuming those facts can be proven at trial.12 Nonetheless, Louisiana has a fact-pleading system; hence, the pleader‘s mere conclusions, unsupported by facts, are insufficient to state a cause of action.13 To the сontrary, the court must discard allegations purporting to be factual that are merely self serving and allegations that are nothing more than conclusions.14
DISCUSSION
The sole issue presented by this appeal is whether the trial court erred in sustaining the defendants-in-reconvention‘s peremptory exceptions of no cause and no right of action. Proper analysis of this issue requires that we first identify the causes of action available to ICC.
In its reconventional demand, ICC divides its causes of action into two parts—those against both DLN and Mr. Francis, and those against only TPA. As to DLN and Mr. Francis, ICC asserts five causes of action: (i) bad faith breach of contract; (ii) fraud, pursuant to
The trial court‘s characterization of all of ICC‘s claims as contract-based is legally correct. As to TPA, ICC‘s allegations in its reconventional demand are two fold. First, it alleges a fault claim—TPA “failed to perform and disregarded its obligations” under the contract between ICC and the owner (the Construction Contract). Second, it alleges a failure to perform claim—TPA failed “to perform its services consistent with the professional skill and care ordinarily provided by architects.” Both of these claims are contract-based and stem from the Construction Contract and the Architect Agreement.
- [Mr.] Francis and DLN willfully failed to perform their contractual obligations. Accordingly, ICC has been deprived of the benefits of the [Construction] Contract. Pursuant to
La. Civ. Code Art. 1994 , ICC may recover damages for defendants’ nonperformance of their contractual obligations. - DLN and [Mr.] Francis terminated ICC as general contractor on the Project for convenience. Pursuant to Article 14.4.3 of the General Conditions to the Contract, ICC is entitled to damages which include “payments for Work executed, and costs incurred by reason of such termination, along with reasonable overhead and profit on the Work not executed.”
- ICC may recover damages for the bad faith failure of [Mr.] Francis individually and DLN to fully pay the subcontractors working on the Project (
La. Civ. Code Art. 1997 ). - Pursuant to Article 14.4.3 of the General Conditions to the Contract, ICC is entitled to damages which includе “payments for Work executed, and costs incurred by reason of such termination, along with reasonable overhead and profit on the Work not executed.”18
- Pursuant to
La. Civ. Code Art. 1967 , ICC is entitled to actual damages which include the expenses incurred or the damages suffered as a result of their reliance on the promise of continued employment and the other representations made by [Mr.] Francis and DLN throughout the Project.
Given the reconventional demand asserts only contraсt-based claims, the dispositive issue is whether the trial court erred in rejecting ICC‘s attempts to establish a contractual relationship between it and the defendants-in-reconvention. Addressing this issue, we divide our analysis into two parts, as did the trial court—ICC‘s claims against DLN and Mr. Francis; and ICC‘s claims against TPA.
ICC‘s Claims against DLN and Mr. Francis
The trial court, in its written reasons for judgment, observed that ICC‘s lack of privity with DLN, Mr. Francis, or both dictated sustaining the exceptions filed by DLN and Mr. Francis. The trial court observed that “because DLN Holdings and [Mr.] Francis were neither a signatory to the contract nor a personal guarantor of the contract, there is no privity of contract between ICC and DLN Holdings and/or [Mr.] Francis that would allow ICC to bring these claims.”
On appeal, ICC asserts four arguments in support of its argument that it, nonetheless has a cause or right of action against DLN, Mr. Francis, or both: (i) misnomer of naming of “Pelham Hospitality” as the owner in the Construction Contract; (ii) Change Orders signed by Mr. Francis that reference DLN as owner; (iii) judicial confession by DLN, in original mandamus petition, that it was the owner under the Construction Contract; and (iv) Mr. Francis’ liability under
Misnomer
The gist of ICC‘s first argument is that the omission of the LLC abbreviation after the company‘s name—“Pelham Hospitality“— on the
Contrary to ICC‘s contention, the principle on which it relies is inapposite here. At all pertinent times, Pelham Hospitality was an existent Louisiana limited liability company; indeed, it was the entity that was the Hotel‘s operator. The applicable principle here, as DNL and Mr. Francis contend, is that a variant of a bona fide entity‘s name has no legal effect.21
The conclusion that an existent entity—Pelham Hospitality, LLC—was the Project owner identified on the cover page of the Construction Contract is buttressed by the following four factors. First, it is undisputed that Pelham Hospitality, LLC, was the Hotel‘s operator. Second, ICC, as
Change Orders
ICC next argues that an ambiguity as to the identity of the contracting parties was created by the discrepancy between the party appearing on the cover page of the Construction Contract—“Pelham Hospitality“—and the party appearing on the executed Change Orders—“DLN Holdings/Pelham Hospitality.” Given this ambiguity, ICC contends that parole evidence is needed to determine the parties’ intent.24 Given this need to consider evidence outside the petition—here, the reconventional demand—to resolve the ambiguity, ICC contends that the granting of the exception of no cause of action was improper.
At the hearing on the exceptions, the trial court commented that the Change Orders issue was ICC‘s strongest argument. The trial court framed the question presented as whether the Change Orders conferred standing on ICC to bring the reconventional demand against Mr. Francis, DLN, or both. Answering the question in the negative, the trial court observed that the Change Orders altered neither the nature of the Construction Contract nor the identity of the contracting parties. The trial court observed that the juridical entity—Pelham Hospitality, LLC—was “the оnly entity that is involved [in the Construction Contract]” and that Mr. Francis had “the protection of being behind two LLCs.” The trial court emphasized the lack of privity between ICC and the defendants-in-reconvention—DLN and Mr. Francis. The trial court, thus, sustained the exceptions as to DLN and Mr. Francis. We agree.
As noted elsewhere in this opinion, the Construction Contract is a standard AIA construction contract. Change Orders, by definition, cannot change the identity of the parties to a standard AIA construction contract. As provided in AIA General Conditions §7.2:1,25 the only effects of a Change
Judicial Confession
ICC‘s third argument is that DLN judicially confessed it was a party to the Construction Contract in its original mandamus action petition, which was filed on July 18, 2019. The averment on which ICC relies states as follows:
On or about March 17, 2017, DLN hired ICC as a general contractor on the Pelham Hotel renovation project (“Project“). ICC served in that capacity throughout the Project and obtained subcontracts with other trades and professions. The contract between DLN and ICC (“Contract“) is attached hereto as Exhibit “A.”
DNL, however, corrected this error by filing an amended petition for mandamus less than two weeks later, on July 31, 2019, in which the erroneous reference to DLN was replaced with “Pelham Hospitality, L.L.C.‘’26
A party may amend the pleadings to cure any errors or omissions absent a showing that the adverse party was misled or deceived.27 The jurisprudence recognizes that the “amended petition constitutes the plaintiff‘s principal action or demand as fully as if it had been set forth in the original petition.”28 Here, the correction was consistent with the Construction Contract, which is an attachment to not only the mandamus petition but also the reconventional demand. Thus, there could be no deception. Indeed, as DNL and Mr. Francis point out, a party cannot
Mr. Francis’ Liability under La. R.S. 12:1320(D)
Although a member of a limitеd liability company can be subject to personal liability to third parties on limited grounds set forth in
Although this statute does not define fraud,
- Mr. Francis’ signature on the last page of the Construction Contract may have been a naive error on his part stemming from lack of or incompetent legal counsel, however, that does not excuse the subsequent course of dealings tainted by fraud in his clumsy attempt to avoid the personal liability consequences of that signature.
- Mr. Francis did not act on behalf of an LLC when he signed the Construction Contract, he acted in his individual capacity only. He had the option to sign with the name of the cоmpany or adding “on behalf of Pelham” but did not, demonstrating he acted individually.
- Unlike the Architect Agreement, which was correctly in the name of DLN, the true owner, Mr. Francis meant or subsequently attempted to “suppress the truth” and create confusion as to the true party to the Construction Contract. He executed all of the Change Orders in the name of DLN/Pelham.
- All funds to pay ICC came from Chase accounts in the name of either DLN or Pelham. Stated otherwise, DLN and Pelham paid ICC interchangeably through DLN‘s and Pelham‘s Chase bank accounts.
- DLN judicially confessed that it was the true owner of the property, as opposed to the representation on the first and last page of the Construction Contract that Pelham Hospitality—which has no existence as a legal entity—and not DLN, title owner of the immovable property, was owner.
- On February 8, 2018, Mr. Francis, who had committed the day before to the contractor Pelham hired to replace ICC to complete the Project, lied to ICC‘s representations when he represented that he intended a termination for convenience and thereby obtained monetary concessions and ICC‘s ongoing cooperation.
- Mr. Francis did not disclose that he had already interposed Pelham Hospitality, LLC, as a party to the contract with the new contractor (ICC‘s replacement). Nor did he disclose that he would hire counsel to terminate the Construction Contract based on false allegations of fault and falsely claim that Pelham Hospitality, LLC, whose name is not mentioned in the Construction Contract and who is just a lightly capitalized operator, was a party to the Construction Contract in which Pelham Hospitality appeared as owner.
- There was no disclosure that the defendants-in-reconvention were going to make up claims of defective work and of failure to pay the subcontractors. DLN undertook to pay the subcontractors in Change Order 6 and used that and other money due ICC to pay the new contractor and complete the Project; and
- Mr. Francis, in the Notice of Termination, deceived ICC by interposing Pelham Hospitality L.L.C., thereby attempting to avoid his personal liability.
ICC‘s allegations in support of its fraud claim, as DLN and Mr. Francis observe, can be grouped into the following four categories, none of which is sufficient to establish fraud:
- “Naive error” by Mr. Francis signing the Construction Contract in a personal capacity—A naive error, by definition, is not fraudulent;
- Change Orders identifying the Project‘s owner as DLN Holdings/Pelham Hospitality—Change orders do not affect the identity of the Project‘s owner;
- Source of Funds used to pay ICC—All payments to ICC were submitted pursuant to Applications for Payment that ICC directed only to Pelham; and
- DLN‘s judicial confession that it was the true owner—DLN was the owner of the property and the Hotel; but Pelham was owner of the Project. Indeed, ICC sought progress payments from Pelham; but it attempted, after its termination, to lien DLN‘s property.
Given none of ICC‘s allegations suffice to establish fraud, ICC‘s argument regarding Mr. Francis’ liability under
To recap, none of the four arguments ICC makes in support of establishing a cause or right of action against DLN, Mr. Francis, or both is persuasive.
ICC‘s Claims against TPA
In sustaining TPA‘s exceptions, the trial court observed that both the Construction Contract and the Architect Agreement contain integration provisions that preclude the creation of a contractual relationship between TPA, as the Project‘s architect, аnd ICC, as the Project‘s general contractor. In so finding, the trial court, in its written reasons for judgment, explained as follows:
ICC‘s Reconventional Demand . . . does not allege any contractual relationship between itself and TPA, and, after a review of the contracts at issue, nor could it. The AIA Al01-2007 [Construction Contract] entered into by ICC and Pelham incorporated AIA Document A201-2007, which includes the following provision:
§ 1.1.2 The Contract. The Contract Documents for the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship or any kind (1) between the Contractor and the Architect or the Architect‘s consultants, (2) between the Owner and a Sub-contractor or a Sub-subcontractor; (3) between the Owner and the Architect or the Architect‘s consultants, or (4) between any persons or entities other than the Owner and the Contractor. The Architect shall, however, be entitled to performance and enforcement of obligations under the Contract intented [sic] to facilitate performance of the Architect‘s duties (emphasis added).
Further, the AIA Document Bl01-2007 [Architect Agreement] еntered into between TPA, Pelham, and DLN Holdings, specifically states:
§10.5
Nothing in this Agreement shall create a contractual relationship with or cause of action in favor of a third party against either the owner or the architect.
The trial court, thus, concluded that there was no privity of contract between ICC and TPA that would allow ICC to bring the claims it asserted in its reconventional demand.
On appeal, ICC argues that those integration provisions do not preclude its detrimental reliance claim against TPA.34 TPA counters that ICC did not plead a detrimental reliance claim against it in the reconventional demand and that, even if
To establish a detrimental reliance claim, a party must prove three elements by a preponderance of the evidence: (i) a representation (promise) by conduct or word; (ii) detrimental reliance; and (iii) a change in position to one‘s detriment because of the reliance.35 Even assuming TPA made any representations (promises) to ICC, it contends that the two contracts—the Construction Contract and the Architect Agreement—directly prohibit and preclude any claim by ICC that it reasonably relied on those representations (promises). According to TPA, ICC did not plead any facts that TPA made any representation to it, but even if it did, reliance would not be reasonable as a matter of law. We find this argument persuasive.
The jurisprudence has held that integration provisions make a detrimental reliance claim based on alleged promises made outside of the integrated agreements unreasonable as a matter of law.36 Such is the case here. Additionally, ICC, in its appellant brief, acknowledges the contract-based nature of its detrimental reliance claim against TPA; it alleges “[t]he contractual relationship that resulted from detrimental reliance establishes ICC‘s right of action against TPA, the architect.” Again, the integration provisions, as TPA contends and the
In sum, none of the arguments ICC makes in support of establishing a cause or right of action against TPA is persuasive.
Denial of Leave to Amend
ICC‘s final argument is that the trial court erred in denying its request, pursuant to
The entire universe of facts regarding the relationships of the various parties to ICC‘s purported claims, as TPA points out, is defined by the contracts that ICC attached to its reconvеntional demand—the Construction Contract and the Architect Agreement. ICC cannot amend its reconventional demand to cure its
DECREE
For the foregoing reasons, the trial court‘s judgment is affirmed.
AFFIRMED
Rosemary Ledet
JUDGE
Notes
Nothing in this Chapter shall be construed as being in derogation of any rights which any person may by law have against a member, manager, employee, or agent of a limited liability company because of any fraud practiced upon him, because of any breach of professional duty or other negligent or wrongful act by such person, or in derogation of any right which the limited liability company may have against any such person because of any fraud practiced upon it by him.
When the grounds of the objection pleaded by the peremptory exception may be removed by amendment of the petition, the judgment sustaining the exception shall order such amendment within the delay allowed by the court. If the grounds of the objection raised through the exception cannot be so removed, or if the plaintiff fails to comply with the order to amend, the action, claim, demand, issue, or theory shall be dismissed.
