OPINION
This appeal, involving a dispute between the Tennessee Valley Authority (“TVA”) and one of its former coal suppliers, raises three questions: (1) whether the district court erred in determining that it had subject matter jurisdiction, pursuant to the Contract Disputes Act of 1978 (“CDA”), 41 U.S.C. § 601 et seq., over the plaintiffs claim for lost profits; (2) whether the district court properly concluded, under standard principles of contract law, that the plaintiff is not entitled to recover damages based on a contract price/market price differential; and (3) whether the unappealed February 27, 2001, administrative decisions which denied the plaintiffs claims for actual damages are entitled to res judicata effect. For the reasons that follow, we AFFIRM the district court’s judgment.
I. Factual Background
For a second time, these parties bring their dispute to this Court.
1
On August 18, 1990, the plaintiff, Diversified Energy, Inc. (“Diversified”), and the defendant,
On March 31, 1997, Diversified filed suit in district court, appealing the Disputes Contracting Officer’s decisions. Upon Diversified’s motion for summary judgment, the trial judge determined that TVA had, through “inept and heavy-handed” behavior, breached the Contract in multiple ways. The trial court also ruled, however, that TVA’s breaches were not tantamount to a unilateral termination of the Contract. Moreover, the trial court determined that Diversified committed prior material breaches of the “Officials not to Benefit” provision, thereby disqualifying it from any damages.
Diversified .appealed the district court’s decisions to this Court, arguing that the district court was precluded from considering TVA’s defense under the Officials not to Benefit provision because TVA’s Contracting Officer had never raised that claim. Diversified also argued that the district court erred in refusing to construe TVA’s conduct as a unilateral termination of the Contract. This Court affirmed the district court on the unilateral termination issue but reversed with respect to TVA’s clajm under the “Officials not to Benefit” provision, concluding that the district court lacked jurisdiction over that claim because TVA’s Contracting Officer had never raised it. We held that the district court could assert jurisdiction over TVA’s defensive claim only if it had been the subject of a valid, final decision by the contracting agency. We further held that a valid, final decision on TVA’s claim could be made only if it had first been raised by a Contracting Officer. However, because the March 19, 1993, letter which first raised TVA’s “Officials not to Benefit” claim was not written by a Contracting Officer,
6
and because the Disputes Contracting Officer who later raised that claim was not simultaneously acting as the Contracting Officer, we determined that TVA’s claim was not properly before the Disputes Contracting Officer. Accordingly, this Court concluded that the district court had no power to consider TVAs defensive claim and remanded the case to the district court with instructions to award damages to Diversified on its contract claims “in accordance
Upon remand, Diversified first sought an award of actual damages under the contract price-market price differential. TVA, attempting to rely on the Court’s reasoning in Diversified I, moved to dismiss that claim, arguing that Diversified’s initial 1993 claim letter to the Contracting Officer submitted only a claim for liquidated damages. On November 6, 2000, the district court, uncertain whether Diversified’s 1993 claim letter was sufficient to state a valid claim for actual, non-liquidated damages, stayed the action for 120 days “to allow for administrative consideration of Diversified’s claim for actual damages.”
In an August 29, 2000, letter sent to Diversified, TVA’s Vice-President of Procurement, Paul R. LaPointe, had advised that Larry A. Mize had been assigned as the new Contracting Officer who would be administering Diversified’s contract claims. On November 14, 2000, Mize informed Diversified that TVA would also be asserting a claim that Diversified had breached the “Officials not to Benefit” Clause — the same claim which we ruled the district court lacked jurisdiction to consider. Mize also asked Diversified to submit any additional materials relevant to its contract claims, indicating that his role was to resolve the matter by agreement. On January 22, 2001, Diversified sent a letter to Mize specifying that it sought actual damages as measured by the difference between the contract price and the market price or, alternatively, the profits it lost due to TVA’s repudiation. In two letters dated February 27, 2001, Mize — now also acting as the Disputes Contracting Officer — refused to award Diversified either measure of damages, concluding that its prior breach of the “Officials not to Benefit” clause precluded it from recovering any damages.
On March 7, 2001, the district court lifted its stay. On the same day, TVA moved for partial summary judgment on Diversified’s claim based on the contract/market price differential, claiming that such an award would not be consistent with standard contract law principles because it would place Diversified in a better position than it would have enjoyed had the Contract been performed fully. The district court granted TVA’s motion, holding that Diversified’s damages would be calculated on the basis of the profits it would have made had the Contract been performed. On May 23, 2001, TVA filed objections to the district court’s jurisdiction, claiming, among other things, that Diversified needed to amend its complaint to appeal the adverse February 27, 2001, decisions in order for the district court to have jurisdiction over any of its damage claims.
On June 7, 2001, Diversified moved for summary judgment on its lost profits claim. TVA opposed the motion, alleging (1) that the district court lacked jurisdiction over that claim because it had not been submitted to a Contracting Officer before Diversified filed its original complaint and because Diversified had not been granted leave to amend its complaint to appeal the February 27, 2001, administrative decisions which denied that claim, (2) that expenses should be deducted from Diversified’s claim for lost profits, and (3) that the February 27, 2001, administrative decisions of the Disputes Contracting Officer were entitled to
res judicata
effect and precluded Diversified’s claim for any actual damages. On July 12, 2001, the district court overruled TVA’s objections and granted, in part, Diversified’s motion for summary judgment. With regard to the jurisdictional issue raised by TVA, the dis
II. Standard of Review
This Court reviews
de novo
a district court’s grant of summary judgment.
Edwards v. TVA,
III. Discussion
A. Jurisdiction over Diversified’s Lost Profits Claim
In this appeal, TVA renews the primary contention that it made to the district court upon remand: that the district court lacked jurisdiction over Diversified’s lost profits claim because that claim had not been presented to a Contracting Officer before Diversified filed its original complaint and because Diversified has not amended its complaint to include an appeal of the February 27, 2001, administrative decisions which rejected that claim. The critical assumption underlying TVA’s position is that Diversified’s May 18, 1993, certified claim — the basis of the district court’s jurisdiction when Diversified initiated suit in 1997 — failed to make a claim for lost profits, but instead stated only a claim for liquidated damages. 7
TVA asserts that Diversified’s failure to refer to lost profits expressly in its claim letter violated its duties under the CDA, specifically, 41 U.S.C. §§ 605(a) and 605(c)(1), to ensure that all of its claims were submitted in writing to a Contracting Officer and to certify that the data supporting its claims was accurate and com-
TVA, as an agency of the United States, enjoys sovereign immunity unless Congress specifically waives it.
See, e.g., Campanella,
The CDA does not define what constitutes a “claim.”
Colon,
Under the CDA, a district court is not deprived of jurisdiction over a contract
TVA contends that Diversified submitted no information regarding its lost profits to the Contracting Officer, thus providing him with no opportunity to make a final decision on that claim. TVA specifically asserts that the claim for lost profits was based on different evidence than the liquidated damages claim. TVA’s position, however, ignores the reason underpinning the rule enunciated in
ThermoCor
and
Cerberonics:
as long as the contracting agency is given an adequate opportunity to make decisions on the issues presented by a contractor’s claim, the subsequent modification (or clarification) of the remedy sought by the contractor does not prejudice the contracting agency and does not, therefore, deprive the district court of jurisdiction over the modified claim.
See, e.g., ThermoCor,
Diversified’s claim for lost profits arose from the same operative facts which were before the Contracting Officer in 1993— TVA’s conduct in repudiating the Contract. Additionally, since the original Disputes Contracting Officer denied Diversified’s claim on the issue of liability, he necessarily refused to award Diversified damages under any available remedy theory. The Disputes Contracting Officer was given an adequate opportunity to address the lost profits claim. Therefore, the district court had jurisdiction over Diversified’s lost profits claim when Diversified filed its complaint in 1997. Furthermore, since its lost profits claim was properly before the district court by virtue of its original complaint, Diversified had no obligation to amend that pleading to appeal the February 27, 2001, administrative decisions.
See Sharman Company, Inc. v. United States,
B. Diversified’s Claim Under the Contract/Market Price Differential
The district court did not err in rejecting Diversified’s claim for damages based on the $5.13 per ton difference between the Contract price and the market price. Upon remand, this Court instructed the district court to determine Diversified’s damages in accordance with standard principles of contract law. Diversified mistakenly argues here that those principles entitled it to a measure of damages reflective of the contract/market price differential under the Uniform Commercial Code (“UCC”), spe-
Sigmon — the entity which actually owned the coal — paid Diversified a fixed commission of $.98 for each ton of coal delivered to TVA. Diversified was obligated to pay a portion of those commissions, $.22 for each ton delivered, to a third party, Billy Evans, as compensation for his assignment of the Contract to Diversified on June 19, 1980. Hence, as indicated in
Diversified I,
if TVA had performed the Contract fully, Diversified’s maximum expectancy would have been $.76 per ton of undelivered coal.
See Diversified I,
A non-breaching party is entitled to be placed in the same position it would have enjoyed had the defendant abided by the contract, but is not entitled to more than the benefit of his bargain.
See, e.g., San Carlos Irrigation & Drainage Dist. v. United States,
Diversified relies principally upon
Trans World Metals, Inc. v. Southwire Co.,
C. The Res Judicata Effect of the February 27, 2001, Administrative Decisions
The February 27, 2001,- administrative decisions which purported to resurrect TVA’s “Official not to Benefit” defense and to deny Diversified’s claims were invalid from the outset and are therefore not entitled to any preclusive effect. Where, as here, a claim for damages under the CDA is in litigation, a Disputes Contracting Officer has absolutely no authority to issue a final decision on that claim.
See Sharman Co. v. United States,
IV. Conclusion
For the foregoing reasons, the district court’s decision is AFFIRMED.
Notes
. This is the second appeal of this case; the factual background is more fully summarized in the Court’s prior opinion,
Diversified Energy, Inc. v. TVA,
. The reopener provision provided:
[T]his contract shall continue through March 27, 1996, unless terminated by agreement or as otherwise negotiated herein. Provided, however, this contract may be reopened by either party three (3) months prior to March 19, 1993 ... for the purpose of negotiating price and other terms and conditions of the remaining portion of the maximum commitment.... If either party exercises this reopener it shall give the other party written notice by December 19, 1992. If the reopener provision has been exercised, this contract will terminate on March 19, 1993, unless TVA and the Contractor [i.e., Diversified] have mutually agreed in writing by March 19, 1993, to continue this contract. Neither party shall be under any obligation or liability to extend this contract if either party desires to terminate deliveries.
. This "Officials not to Benefit” provision read:
[N]or shall the Contractor offer or give, directly or indirectly, to any officer, employee, special Government employee, or agent of TVA any gift, gratuity, favor, entertainment, loan, or any other thing of monetary value, except as provided in 18 C.F.R. § 1300.735-12 or -34. Breach of this provision shall constitute a material breach of this contract and TVA shall have the right to exercise all remedies provided in this contract or at law.
.Pursuant to the CDA, a contractor and the contracting government agency must submit disputes to a Contracting Officer. If the parties are unable to resolve their claims by agreement, the Contracting Officer may issue a decision on the dispute. The terms of the instant Contract, as well as TVA’s implementing regulations, have altered this administrative scheme slightly by requiring that any dispute which cannot be settled by the parties shall be decided by a Disputes Contracting Officer, rather than a Contracting Officer. Under this scheme, a Contracting Officer’s role is to receive claims from a contractor and to raise claim on TVA’s behalf. A Disputes Contracting Officer’s sole function is to decide claims.
See Diversified I,
. The Contract contained a "Unilateral Termination Right” provision which entitled TVA to terminate the Contract unilaterally upon 60 days’ prior written notice. The penalty for invoking this clause was $14 per ton of coal multiplied by the remaining number of tons scheduled for delivery from the effective termination date through the earliest applicable date for termination.
. Vincent — the author of the March 19, 1993, letter — was not authorized to act as a Contracting Officer when he alleged that Diversified breached the "Officials not to Benefit” clause.
. TVA’s assumption is not well-founded, as Diversified’s 1993 claim letter clearly stated that it believed itself "entitled to recover from TVA the amount which [it] would have made from delivery of the remaining portion of the maximum commitment under the Contract.” This language plainly encompasses a claim for lost profits. See,
e.g., Allen, Heaton & McDonald v. Castle Farm Amusement Co.,
.This section provides:
(1) Subject to subsection (2) and to the provisions of this Article with respect to proof of market price (Section 2-723), the measure of damages for non-acceptance or repudiation by the buyer is the difference between the market price at the time and place for tender and the unpaid contract price together with any incidental damages provided in this Article (Section 2-710), but less expenses saved in consequence of the buyer’s breach.
(2) If the measure of damages provided in subsection (1) is inadequate to put the seller in as good a position as performance would have done then the measure of damages is the profit (including reasonable overhead) which the seller would have made from full performance by the buyer, together with any incidental damages provided in this Article (Section 2-710), due allowance for costs reasonably incurred and due credit for payments or proceeds of resale.
. It is unclear the extent to which the UCC applies to government contracts.
See, e.g., Technical Assistance Int'l, Inc. v. United States,
. As observed by the district court, the reo-pener provision allowed either party to reopen the Contract (with certain restrictions) for the purpose of negotiating new terms in the event that the market price of coal changed.
