Dierks & Sons Lumber Co. v. Pearman

172 Mo. App. 107 | Mo. Ct. App. | 1913

JOHNSON, J.

This is a suit to enforce a mechanic’s lien begun in the circuit court of Jackson county October 19, 1910. The lien paper was filed on the same day. The acount is for lumber and material sold and delivered by plaintiff to defendant Pearman for the construction of a dwelling house and barn. The first item was delivered September 10, 1909, and the last August 5, 1910. The whole account amounted to :$773.90, but this was reduced to $513.90 by payments made by Pearman between September 20, 1909, and April 20, 1910. The buildings were erected on a lot Pearman bought on the installment plan. He received .a warranty deed March 11, 1910 and on March 16, 1910, borrowed $1400 from the defendant Loan and Building Association securing the payment of the indebtedness by a deed of trust on the lot. On August .3, 1910, he and his wife deeded the lot to defendant Anna Englehardt.

On August 9, 1909, Pearman, who had just entered into a contract for the purchase of the lot, applied to plaintiff for the material to build a house and barn. Plaintiff’s manager testified: “He (Pearman) came •in the office and said ‘I just bought a lot at Forty--sixth and Agnes and I want to get material, enough to build a bam and later on build a house. ’ I asked him if he had any money and he said he didn’t, that he would pay for it at twenty-five dollars a month and I •studied the matter over and I finally says, well, you take out some insurance on it and I will accept those .terms and he made out a little bill in the office. I *111can’t recall the exact amount. He said ‘I will need this for the rough, material in the barn and I will keep on going and adding to the material as I need it, and when I get my barn finished I am going to start oil my house.’ ” According to the evidence of plaintiff, all of the material for the house and barn was furnished from time to time under this oral agreement which was the only contract plaintiff had with Pear-man. The jury, in obedience to' a peremptory instruction, returned a verdict in favor of all of the defendants except Pearman. Plaintiff appealed.

There are other facts in the record but those stated compel an affirmance of the judgment and other facts and the issues they present will be ignored.

The contract bn which a right to a lien is predicated contemplated that plaintiff should furnish Pear-man materials for the house and barn he purposed erecting of the value of about $800, and that unconditional credit should be given him for the payment of the account extending over a period of more than two and one-half years. The account was to be paid in monthly installments of twenty-five dollars each without any provision for the whole to become due in case of default in the payment of any of the installments. Plaintiff is presumed to have known that it was giving credit extending far beyond the time the statute would afford for bringing suit to enforce a mechanic’s lien. It knew that the lien paper would have to be filed within six months after the date on which the last item of material was furnished (Sec. 2817, Rev. Stat., 1909) and that suit to enforce the lien would have to be commenced within ninety days after the lien was filed (Sec. 8228, Rev. Stat. 1909).

The rule in this State and elsewhere is that where the contract under which a lien is claimed provides that the debt- shall not become due until after the expiration of the statutory time for bringing suit to enforce the lien, the right to a lien is regarded as *112waived by the vendor. [Mfg. Co. v. Barnes & Co., 59 Mo. App. 391; McMurray v. Taylor, 30 Mo. 263.] “Where by the agreement of the parties the contract price is not payable until after the expiration of the time within which the lien might be enforced an agreement that there should be. no lien is implied.” [20 Am. & Eng. Ency. of Law (2 Ed.), 362.]

“This is not upon the ground merely that credit has been given, but because no action could be maintained for the purpose of enforcing the lien after the statutory period for doing so had expired.” [Flenniken v. Liscoe, 64 Minn. 269.]

“The necessary consequences would seem to be that if a party places himself in a position which renders him unable to bring suit to enforce the lien within the time limited, he thereby virtually waives it, having deprived himself by his own voluntary act of the right to enforce it.” [Pryor v. White, 55 Ky. 605; see, also Phillips on Mechanic’s Liens, sec. 281 Willison v. Douglas, 66 Md. 99; Ehlers v. Elder, 51 Miss. 495; Scudder v. Balkam, 40 Me. 291; Mehan v. Thompson, 71 Me. 492.]

Of course where the contract provides for only a conditional extension of time the condition to be performed within the time for bringing the suit to enforce the lien, a waiver will not be implied if the condition be broken by the vendee. [McMurray v. Taylor, supra; Ashdown v. Woods, 31 Mo. 465; Baumhoff v. Railway, 171 Mo. 120.] But where, as here, there is an absolute agreement to extend the time of payment beyond that allowed for the enforcement of the lien the vendor must be held to have intended to forego the security of a mechanic’s lien as to that part of the debt not due at the commencement of the suit.

So far as the record discloses the payments made by Pearman on the account paid the installments that had matured at that time. The remainder of the ac*113count was not lienable for the reason that it was not due and no action for a personal judgment could he maintained npon it. The court did not err in directing a verdict for the respondents.

The judgment is affirmed.

All concur.
midpage