35 Wash. 414 | Wash. | 1904
This is an action brought by appellant, "William Dickerson, against the city of Spokane, defend
“Spokane? Washington, January 27th. 1895. “To the City Comptroller of the City of Spokane. Dear Sir: Please pay to William Dickerson the sum of $294 out of any moneys belonging to me, or that may hereafter he due me from the city of Spokane, on the water works contract, either in the twenty per cent reserve, or on account of money to he due me on account of final estimate on said water works contract. Said sum of $294 to hear interest at the rate of one and one half per cent per month until paid, which principal sum and interest please pay in the manner as aforesaid. R. A. Jones.”
This cause was here on a former appeal taken by appellant from a judgment of dismissal, rendered by the lower court at the first trial on the ground that the complaint did not state facts sufficient to constitute a cause of action. The judgment of the superior court was reversed and the case remanded. 26 Wash. 292, 66 Pac. 381. The allegations upon which the present cause of action is founded sufficiently appear from the opinion of this court delivered on the former appeal, which renders it unnecessary to restate such averments in this connection. The amended answer of the city of Spokane denies the material allegations of the complaint charging it with any liability whatever to appellant by reason of the drawing and presentation of the above written order to respondent, admits that it has neglected and refused to pay the same, and avers that, under the contract between E. A. Jones and the respondent city, “it was expressly provided that defendant should not he obliged to accept or pay orders like the one described in the complaint.” It is alleged in the first affirmative defense, “That at no time, since the filing of said order, has the defendant had any
On January 5, 1894, E. A. Jones and the city of Spokane entered into a written contract for the construction of a water works system for such city, for the consideration of $339,880, to be paid Jones, the contractor, hy the respondent city in the manner and amounts, and at the times, therein provided. This contract contains the following provision with reference to the times and manner of payments:
“And the said city of Spokane, hereby agrees to malee payment of the said sum for said work in manner and at the times following, to wit: Said payments to be made semimonthly, on or about the first and fifteenth day of every month, upon estimates of the value of the materials •delivered at the site, and the labor performed upon the said work, during the preceding half month, . . . less 20 per centum of the amount of each estimate, which 20 per centum shall be retained by the city of Spokane until all and every part of said work shall he entirely complete, and accepted by the said hoard of public works.”
On September 21, 1895, Jones assigned all of his interest in this contract to Philip Buehner, one of his sureties. At that time he also gave Buehner a general power of attorney authorizing and empowering Buehner to act in his place and stead and complete this contract. The city council of Spokane consented to the change. The 20 per
On behalf of the defense, Mr. E. E. Gill, city commissioner, and a member of the board of Public Works of Spokane in 1895 and 1896, testified, that, when the water works contract was turned over by Jones to Buehner on the 21st of September, 1895, $260,000 had been expended under the contract; that the final estimate, which included all other estimates, was 388,000 and some hundred dollars; and that there was not money enough left of the contract price remaining unexpended, when Philip Buehner took charge of the work, to pay the claims for labor and material then due, or thereafter incurred in completing the works. This witness further testified that more than one thousand dollars was expended over and above the contract price, and that there were a great number of bills not allowed. The evidence of Messrs. Jones and Buehner, as well as the documentary evidence adduced in behalf of the defense, tended to show that there was no money due the contractor, unless, on the final settle^ ment, there was a balance in the reserve fund; that, upon the completion of the contract, there was no money to turn over to the contractor. The transcript shows that the appellant’s counsel objected to nearly every item of evidence, oral and documentary, offered by the city at the trial.
The trial court, among other things, instructed the jury as follows:
“The defendant admits the contract, as alleged; admits that the order, as alleged, was delivered to the comptroller of the city; denies that the comptroller endorsed it or promised to pay anything upon it; admits that the water works plant was completed and accepted by the city. It*419 denies, however, that anything was due to Jones on the contract upon the final settlement, so that the issue raised for you to determine, gentlemen, is whether or not, upon the final settlement between Jones and the city, there was anything due from the city to Jones upon that contract. - . . How gentlemen, this order is that the city pay to the plaintiff out of the reserve that is kept back by the city upon the contract with Jones, or out of anything that may become due him on the final estimate or final settlement. . . . The comptroller had no authority to bind the city by any statement that he may have made to Dickerson, or any one else, with regard to the payment of this order outside of the terms of the contract, and outside of the legal liability of the city, as I have explained to you.”
Appellant excepted to the giving of each of these instructions.
In our opinion these instructions, in connection with the evidence above noted, present the two material questions for our consideration under the assignments of error: (1) the proper interpretation of the terms of the written order described in the complaint, and upon which the present action is founded; (2) the liability of the city of Spokane, respondent, to appellant on such written instrument. The main contention arises as to the proper significance and meaning of the terms contained in this written order: “Out of any moneys belonging to me, or that may hereafter be due me from the city of Spokane, on the water works contract, either in the twenty per cent reserve, or on account of money to be due me on account of final estimate on said water works contract.” The lower court decided that it was payable from the 20 per cent reserve or the amount found due on final estimate.
The learned counsel for appellant forcibly urges that, “instead of designating two funds, as the trial judge held, it designated really three funds: (1) his [Jones’] semi
After a careful consideration of the record in this case, in connection with the arguments of able counsel, we are of the opinion that the trial court committed no error prejudicial to the rights of appellant in its rulings respecting the admission and rejection of evidence, or in any of the instructions given to the jury at the trial, and that there is ample evidence to sustain the verdict. It seems plain to us that this order was drawn upon the 20 per cent reserve fund, or the balance due the contractor upon completion of the water works. This fund was reserved for the protection of the city against any liability which might arise under, or in connection with, the contract between the city and Jones. When the water works system
We think the trial court committed no error in refusing to admit in evidence plaintiff’s exhibit Ho. 1 as to the alleged consideration of this order being for labor or material furnished by Thomas Olsen at the instance of contractor Jones, and that this order was, therefore, a preferred claim against the city under the water works contract, operating as an assignment of Olsen’s claim. The appellant is seeking to recover against respondent on this written order, and not on the original consideration. T'rue^ he alleges such consideration in his complaint, but it is plain that his right of action is measured by the terms of the written instrument upon which this action is founded. It does not lie with appellant to assert that it is payable otherwise than in the manner designated by the instrument itself.
The judgment of the superior court is clearly right, and should be affirmed.