139 Mo. App. 584 | Mo. Ct. App. | 1909
This action is on four special tax-bills issued by the city of Brookfield, a city of the third class, in payment of the cost of grading, curbing and paving Main street. Defendant owned two lots on the street. A taxbill for $64.58 was issued against each lot on account of the grading and paving and one for $9.65 against each lot on account of the curbing. The answer pleaded defects in the regularity of the proceedings leading to the issuance of the bills, fraud and collusion between certain city officers and the contractors, and that the work was not done in substantial compliance with the contract. The case was tried to the court- and findings of fact were filed as follows:
*587 “1. I am of the opinion the record in the proceedings leading np to and touching the paving involved in this case is sufficient.
“2. I find that there was no fraud or collusion between the plaintiffs Dick & Gannon and the city engineer and his assistant, in the matter of the preliminary estimates for the grading, paving and curbing, or either of them.
“3. I find that the grading and curbing were done in substantial compliance with the plans and specifications and contract put in evidence and are sufficient.
“4. As to the brick used in the pavement the court finds that said brick were wholly insufficient and were not good, sound, vitrified paving blocks as required by the contract and specifications, and that great numbers of said brick were not vitrified but were soft and wholly unfit and have been and are crumbling down and rapidly disintegrating, leaving said pavement inferior and much below the character of pavement required by the plans, specifications and contract and the court therefore finds that said brick were defective and insufficient and that the pavement is not a substantial compliance with the contract.”
On these findings the court entered judgment for defendant on all the counts of the petition including those founded on the taxbills issued to pay for curbing.
The sole contention of plaintiffs is that the court erred in refusing to give plaintiffs judgment for the cost of the grading and curbing on account of their failure to perform the work of paving in compliance with the requirements of the contract.
The points made by plaintiffs in their brief are, first, “The contract between the plaintiffs and the city is severable and divisible.” Second, “The law contemplates that the contract for curbing • shall be separate and divisible from the contract for paving and grading and that separate taxbills be issued for the curbing.”
The improvement of the street was initiated by a resolution entitled “A resolution declaring the necessity of paving, curbing, guttering and grading that portion of Main street, etc. This was followed by an ordinance entitled “An ordinance providing for the paving, curbing, guttering and grading ... of Main street, etc.”
In response to the published notice for bids, plaintiffs submitted a bid in which they agreed to do the work for a consideration of $1.08 per square yard for paving, twenty-five cents per cubic yard for grading and thirty cents per lineal foot for curbing. This bid was accepted and a contract was entered into between the city and plaintiffs for the entire improvement at the prices stated. After the completion of the work an assessment of $2.58 1-3 per front foot was levied to pay the cost of the paving and grading and special taxbills were issued pursuant thereto. A separate assessment of 38.6 cents per lineal foot was levied to pay for the curbing and separate taxbills were issued pursuant to that assessment. It is manifest that the city engineer in arriving at the combined cost of the paving and grading made a separate estimate of the cost of each part of the improvement. Necessarily under the contract, he was compelled to find that so many cubic yards of grading had been done which, at twenty-five cents per yard,-amounted to a certain sum; that so many square yards of paving had been laid which, at $1.08 per yard, amounted to a certain sum, and that the total of these two sums divided by the front footage called for the assessment of $2.58 1-3 per front foot. The taxbills for grading and paving do not state the computation and the evidence is not before us but since, as we shall show, the judgment must be reversed and the cause remanded
Whether a contract is to be construed as entire or divisible, whether its different obligations (in contracts which impose the performance by one of the parties of more than one obligation) are to be treated as independent or interdependent obligations is a question, the solution of which depends at last on the intention of the parties to. be gathered from the language of the contract and the subject-matter. Among the rules applied in snch cases for the purpose of ascertaining the real intention of the parties are the following:
“A contract is entire when by its terms, nature and purposes it contemplates and intends that each and all of its parts, material provisions and the consideration, are common each to the other and interdependent. A divisible contract is one in its nature and purposes susceptible of division and apportionment, having two or more parts in respect to matters and things contem plated and embraced by it, not necessarily dependent upon each other.” [7 Am. and Eng. Ency. of Law (2 Ed.), 95.] ■ “The test chiefly relied upon in such cases is whether the parties have apportioned the consideration on the one side to the different covenants on the other. ... If the consideration is apportioned so that for each covenant there is a corresponding consideration, the contract is severable.” [3 Page on Contracts, sec. 1484.]
The following rule applied in the construction of mutual covenants is declarative of the same principle: “Where covenants go to the whole of the consideration on both sides, they are mutual conditions, the one precedent to the other. But where they only go to a part where a breach may be paid for in damages, the defendant has a remedy on his covenant and shall not plead it as a condition precedent.” [Boone v. Eyre,
With these rules in mind, let us see what was the manifest intention of the parties in the present case. While the improvement was initiated by a single resolution and ordinance and was provided for in but one contract, we find its main component parts — i. e. grading, curbing and paving — separated in the entire proceedings in a manner to preserve their individuality. Particularly is this true with respect to the consideration plaintiffs were to receive. They were to have so much for grading, so much for paving, and so much for curbing. They gave a statutory bond conditioned for the performance of the contract and may be held in damages on that bond for the breach of any of their covenants. The damages resulting from the breach of their obligation to pave the street in compliance with the terms of the contract may be ascertained with certainty and their liability to respond cannot be questioned. Why enforce a forfeiture against them? For that is what the judgment before us attempts to do. They did the grading and the curbing in compliance with the contract and we perceive no reason in morals or in law for punishing them with a fine. The ordinary rule of damages will afford the city and property-owners adequate recompense for the breach and there is no occasion or warrant for inflicting exemplary damages.
We are cited to no authority that sustains the position of defendant. What we have said demonstrates that the question before us was not considered by the Supreme Court in Heman v. Loevy, 179 Mo. 1. c. 471. In Excelsior Springs v. Ettenson, 120 Mo. App. 215, we permitted a recovery on curbing bills and not on the paving bills and said nothing at variance with our present views. In Kansas City v. O’Connor, 82 Mo.
The judgment is reversed and the cause remanded.