164 Conn. 540 | Conn. | 1973
The plaintiff, the Diamond National Corporation, brought an action to foreclose a mechanic’s lien against the property of Edwin R. Dwelle and Dolores D. Dwelle, hereinafter called the defendants for materials furnished to the G- & G Home Improvement Company and Gustavo Passa
The central issue in this appeal is whether the trial court was correct in dismissing the action for lack of jurisdiction over the subject matter. The basis of the court’s decision was that § 49-39 of the General Statutes, as amended in 1965 by Public Act No. 193, established time limits on the validity of the mechanic’s lien and that in failing to meet these limitations, the plaintiff lost his cause of action and the court consequently lost jurisdiction over the subject matter.
Before discussing the issues raised by the court’s construction of § 49-39, it first must be determined whether the court was correct in deciding that the action was subject to §49-39, as amended, which states in relevant part: “No mechanic’s lien shall continue in force for a longer period than four years after such lien has been perfected, unless the party claiming such lien commences an action to foreclose the same and files a notice of lis pendens
At this point it might be argued that because the lien was limited by §49-39 and was created by a different section, § 49-33, the general rule of construction stated above does not apply. This argument, however, is based on a misunderstanding of the general rule. Davis v. Mills, 194 U.S. 451, 454, 24 S. Ct. 692, 48 L. Ed. 1067, quoted with approval in Thomas Iron Co. v. Ensign-Bickford Co., 131 Conn. 665, 669, 42 A.2d 145, stated that “[t]he common case [for application of the general rule] is where a statute creates a new liability and in the same section or in the same act limits the time within which it can be enforced, whether using words of condition or not. . . . But the fact that the limitation is contained in the same section or the same statute is material only as bearing on construction. It is merely a ground for saying that the limitation goes to the right created and accompanies the obligation everywhere. The same conclusion would be reached if the limitation was in a different statute, provided it was directed to the newly created liability so specifically as to warrant saying that it qualified the right.” (Emphasis added.) Here, the limitations are contained in the same statute and are directed so specifically to the cause of action that under the general rule as well as under ordi
It also might be argued that the 1965 amendment limiting the time for judgment is merely a statute of limitation even though the limit for bringing an action based on a lien is a limitation on the right. This would create the curious situation that § 49-39 would be both a condition on the right and a statute of limitation. Although it is not clear from the section precisely how the time limitations operate— whether, for example, the lien expires only after four years, or whether it can expire two years after an action has been brought when final judgment has not been obtained—we do not believe the legislature intended such a result. The amendment was passed to deal with the problem presented in Stanley Svea Coal & Oil Co. v. Willimantic Savings & Loan Assn., 23 Conn. Sup. 329, 183 A.2d 285, where the Court of Common Pleas had to determine under § 49-39, prior to its amendment, whether final judgment had to be obtained within two years of the perfection of the lien. The court held that it did not. The legislature, in amending the section, obviously intended that the limitation on the time for obtaining final judgment be treated exactly as the limitation on the time for commencing the action.
Having concluded that the time limitations on a mechanic’s lien are limitations on the right, the next problem is to determine whether a court on its own motion can dismiss an action brought on a mechanic’s lien because of failure to comply with the time limits. “The defense of the Statute of Limitations must be specially pleaded. Practice Book § 120. In certain cases the defense may be raised by demurrer.” Barney v. Thompson, 159 Conn. 416, 419, 270 A.2d 554. (Emphasis added.) But here the
“It is stated in . . . [Fleshman v. Whiteside, 148 Ore. 73, 34 P.2d 648] that the rule in most jurisdictions is that the failure to bring the suit to enforce a mechanics’ lien within the time prescribed by the mechanics’ lien law is not waived by failure to raise 'such objection by demurrer or answer.” Note, 93 A.L.R. 1462. Generally, “limitations on actions . . . are considered procedural or personal and thus subject to waiver. . . . This is so because it is considered that the limitation merely acts as a bar to
The plaintiff makes a further claim based on the theory of unjust enrichment, but it will not be pursued because the record reveals that it was not raised at the trial. Practice Book § 652; State v. Mortoro, 157 Conn. 392, 393, 254 A.2d 574.
Since our holding above is dispositive of the remaining assignments of error they need not be discussed.
There is no error.
In this opinion the other judges concurred.