60 Mo. 224 | Mo. | 1875
delivered the opinion of the court.
The petition alleges that defendant instituted a suit by injunction against Thos. D. Price, Leroy D. Dewey and the plaintiff, and that upon his executing a bond to them a temporary injunction was granted; that upon a hearing of the cause the injunction was dissolved and the petition dismissed; but no assessment of damages was had at the time of the dissolution. This action is now instituted by the plaintiff alone on the bond to recover damages for alleged breaches.
A demurrer was sustained to the petition because the other obligees in the bond were not made plaintiffs.
Where'an obligation is executed to two or more jointly, all the obligees must sue upon it. They cannot separate the liability and bring an action in favor of each. If the plaintiff can maintain this suit, then Leroy D. Dewey can maintain one, and Thos. D. Price still another, and thus the defendant will be harassed with three suits on the same-obligation which was j ointly made to the three persons. By our law all con tracts are joint and several and a party may sue any one or more debtors against whom he has a demand. But the principle has no application to the obligees in a contract,who must sue jointly as plaintiffs. Where the contract made by the obligor-is a joint
To permit one party to sue might result in great injury in a case of this kind. One plaintiff' might recover the entire penalty of the bond, yet this would be no bar to another action by a plaintiff who was not a party to the suit; and as there could be no apportionment the party would be made liable for obligations that he never entered into. It is true that it may happen in some instances that one obligee has sustained more damage than some of his co-obligees, but this would present no insuperable objection, as under our practice act I think the judgment might be adjusted so as to secure the respective rights of the parties.
The judgment must be affirmed ;