44 Barb. 81 | N.Y. Sup. Ct. | 1865
In construing the agreement under which the claim is made by the plaintiff to determine the sufficiency of the excuse which the plaintiff
It is not claimed but that the contract was faithfully performed in every other respect. Certificates of such performance have been given by the city surveyor to that effect, which have been furnished to the defendant. The final certificate that the contract has been entirely performed can not be furnished because of this omission to pave a small strip by direction of the surveyor.
The plaintiff, however, being justified in his non-performance in that particular, it of course becomes unnecessary to procure and file with the defendant that certificate as a prerequisite of his recovery.
The judgment should be affirmed, with costs.