ORDER
Defendant has moved, pursuant to RCFC 12(b)(6), to dismiss plaintiffs takings claim for failure to state an actionable basis for relief due to the dual remedy sought under both a contract and a takings theory. An owner of commercial nuclear power plants contends that the Department of Energy’s delayed disposal of the owner’s nuclear byproduct has forced it to house the nuclear material indefinitely, thereby depriving the owner of the full market value of the storage space. Defendant argues that plaintiffs remedy lies exclusively in contract. Argument is deemed unnecessary.
FACTS
This case arises under to a contract between the Detroit Edison Company (“plaintiff’) and the United States Department of Energy (“DOE”), whereby, in exchange for annual payments, DOE agreed to dispose of spent nuclear fuel (“SNF”) and high-level radioactive waste (“HLW”) generated by plaintiff. The following facts are undisputed.
The contract at issue has its genesis in the Nuclear Waste Policy Act of 1982, 42 U.S.C. §§ 10101-10270 (2003) (the “NWPA”). One of the stated purposes of the NWPA was “to devise a permanent solution to the problems of civilian radioactive waste disposal,” as federal efforts to design such a solution had theretofore “not been adequate.” 42 U.S.C. § 10131(a)(3) (2003). The NWPA recognized that “the Federal Government has the responsibility to provide for the permanent disposal of high-level radioactive waste and such spent nuclear fuel,” but charged the generators and owners of these products with financing the costs of the disposal.. 42 U.S.C. § 10131(a)(4).
The NWPA authorized the Secretary of DOE “to enter into contracts with any person who generates or holds title to high-level radioactive waste, or spent nuclear fuel, of domestic origin for the acceptance of title, subsequent transportation, and disposal of such waste or spent fuel.” 42 U.S.C. § 10222(a)(1) (2003). The contracts were to be executed on or before June 30,1983, or no later than the date when the owner took title to, or commenced generation of, SNF or HLW. See 42 U.S.C. § 10222(b)(2)(A), (B).
DOE implemented the Standard Contract for the Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste (the “Standard Contract”), published at 10 C.F.R. § 961.11 (2003), to set forth the conditions under which DOE “will make available nuclear waste disposal services to owners and generators” of SNF and/or HLW. 10 C.F.R. § 961.1. Under the Standard Contract, DOE agreed to dispose of an owner’s SNF and/or HLW by no later than January 31, 1998, in exchange for the owner’s payment of fees into the Nuclear Waste Fund. See 42 U.S.C. § 10222(a)(5)(A), (B) & (c).
Having executed its Standard Contract with DOE on or about June 27,1983, plaintiff alleges that it paid more than $84 million into the Nuclear Waste Fund as of 2002 and “continues to pay between $8 and $9 million per year.” Compl. filed Aug. 2, 2002, 119. DOE, for its part, did not begin to dispose of plaintiffs nuclear by-product by January 31, 1998; in fact, DOE has made no effort to gather any SNF or HLW, the disposal of which it is contractually obligated to perform. DOE has estimated that it will not begin to eliminate the SNF and HLW until 2010, at the earliest. Because of this failure to dispose of plaintiffs nuclear material, plaintiff alleges that it “has been and will be forced to incur substantial additional costs to provide for extended on-site storage of its SNF.” Compl. 1Í 21.
DISCUSSION
Plaintiffs complaint is one of 21 cases filed in the United States Court of Federal Claims
The complaint presents two takings theories: 1) The Government’s failure to comply with the January 31, 1998 deadline in the Standard Contract constitutes a taking of plaintiffs vested contract rights; and 2) the Government’s failure to remove plaintiffs SNF and HLW has forced plaintiff to house the substances on its real property, thereby depriving plaintiff of the full economic value of that property. See Compl. IfU 33-34.
Plaintiff has withdrawn the first formulation of its takings theory in light of the Federal Circuit’s decision in Castle v. United States,
Responding to the second iteration of plaintiffs takings theory, defendant advances numerous arguments that it contends warrant dismissal. The thrust of these arguments is that plaintiffs takings theory is a disguised breach-of-contract claim. Defendant notes that, absent the Standard Contract, DOE would have “absolutely no obligation to accept or dispose of [plaintiffs] SNF or HLW.” Def.’s Br. filed Jan. 30, 2003, at 7. According to defendant, plaintiff premises its takings claim on the effects of the Government’s breach of the Standard Contract, yet also advocates a constitutional basis for recovery. Based on the decisions of the Federal Circuit, defendant maintains that plaintiffs remedy for DOE’s failure to honor its obligations lies exclusively in contract.
Plaintiff points to the Supreme Court’s recent admonition that the purpose of the takings clause “is to prevent the government from ‘forcing some people alone to bear public burdens which, in all fairness and justice, should be borne by the public as a whole.’ ” Palazzolo v. Rhode Island,
A takings claim has limited application when a claimant has a viable breach remedy. Castle,
This legal axiom, however, applies when “ ‘the relative rights of party litigants ... have been voluntarily created by contract. In such instances interference with such contractual rights generally gives rise to a breach claim not a taking[s] claim.’ ” Hughes Communications Galaxy, Inc. v. United States,
The Federal Circuit’s decision in Maine Yankee,
The decision to allow plaintiffs to maintain their breach claim required affirming the trial court’s denial of the motion to dismiss plaintiffs’ takings claim. Because the takings claim could not “be viewed as constituting avoidable delay[] under that clause,” plaintiffs’ takings theory exceeded the scope of the Standard Contract’s avoidable delays provision.
Defendant notes, correctly, that Maine Yankee arose in the context of a jurisdictional challenge, not a motion to dismiss for failure to state a claim. This court has reviewed the briefing on defendant’s other dis-positive motions in this case. These motions bespeak a reluctance to deal with plaintiffs claim as redressable under the Standard Contract. This court will not make an early ruling that could prevent plaintiff from vindicating its rights — whether under the Standard Contract or takings jurisprudence, assuming, as defendant resists, that plaintiff has rights that are due to be vindicated. The rationale of Maine Yankee also militates against dismissing plaintiffs takings claim at this point in the litigation. A more fully
However, the court views plaintiffs takings theory as an alternative to its contract claim, see Sinclair v. United States,
CONCLUSION
“The purpose of [RCFC 12(b)(6)] is to allow the court to eliminate actions that are fatally flawed in their legal premises and destined to fail.” Advanced Cardiovascular Sys., Inc. v. Scimed Life Sys.,
IT IS ORDERED, as follows:
1. Defendant’s motion to dismiss is granted only insofar as it relates to plaintiff’s claim that its vested contract rights were taken. Defendant’s motion to dismiss is otherwise denied, without prejudice.
2. This case remains stayed pursuant to the Chief Judge’s order of April 16,2003, and this court’s order of April 17, 2003.
Notes
. The court’s analysis draws heavily on Pi Electronics, an opinion issued by this court two months ago.
. In any event, plaintiff's claim for consequential damages based on a taking is fanciful and should not be revived if this action proceeds on a takings theory.