DeSimone v. City of New YorkDeSimone v. City of New York
The decision and order of this Court entered herein on May 27, 2014 (117 AD3d 614 [1st Dept 2013]) is hereby recalled and vacated (see 2014 NY Slip Op 85221[U] [2014] [decided simultaneously herewith]).
Order, Supreme Court, Bronx County (Norma Ruiz, J.), entered January 4, 2013, which, insofar as appealed from as limited by the briefs, granted defendants’ motions for summary judgment dismissing plaintiff Paul DeSimone‘s
The court providently exercised its discretion in denying plaintiff‘s cross motion to submit a disclosure of his expert professional engineer, since it was first submitted in opposition to defendants’ motions for summary judgment dismissing the complaint, and subsequent to the filing of the note of issue and certificate of readiness (see Garcia v City of New York, 98 AD3d 857, 858-859 [1st Dept 2012]).
Plaintiff‘s
The court properly dismissed plaintiff‘s common-law negligence and
Similarly, Danco met its burden by submitting testimony and documentary evidence indicating that it was retained by O‘Kane, the prime electrical contractor, merely to perform the initial installation of temporary lighting, which was completed on the fifth floor well before the accident occurred. According to the relevant testimony, Danco had no continuing responsibility for maintaining or replacing the temporary lighting. Plaintiff is correct that the court improperly excluded some of his submissions in opposition to Danco‘s motion. He relies on alleged business records of DASNY, the owner, referring to Danco‘s work repairing damaged wires on the fifth floor nine days before the accident, and on nearby floors on the subsequent days leading up to and including the accident. Although these records were admissible under the “party admission” exception to the hearsay rule (see K & K Enters. Inc. v Stemcor USA Inc., 100 AD3d 415, 415-416 [1st Dept 2012]), there is no indication that any such repairs were connected to the temporary lighting; Danco also performed work on the building‘s fire alarm system. Plaintiff also testified that he heard the site safety manager for defendant Bovis, the general contractor or construction manager, discussing a power outage on the fifth floor and instructing electricians to fix it immediately. This testimony was admissible under the “principal/agent admission” exception to the hearsay rule (Navedo v 250 Willis Ave. Supermarket, 290 AD2d 246 [1st Dept 2002]). However, this evidence failed to raise an issue of fact as to whether Danco breached a duty to maintain or repair the temporary lighting.
The court properly conditionally granted summary judgment in favor of DASNY and Bovis‘s contractual indemnification claim against O‘Kane. The relevant provision of the contract between DASNY and O‘Kane broadly required O‘Kane to indemnify DASNY and Bovis for any injuries “caused by, resulting from, arising out of, or occurring in connection with the execution of the Work.” It is uncontested that plaintiff‘s injuries were caused by or occurred in connection with O‘Kane‘s work. Moreover,
Concur—Sweeny, J.P., Acosta, Saxe, Manzanet-Daniels and Clark, JJ.