204 Mass. 461 | Mass. | 1910
The certificate of the architects was properly excluded. In the adjustment of differences, as the work progressed, the decision of the architects as to the quantity and quality of the work within the true meaning of the drawings and specifications was to be final. But they were not empowered to act as arbitrators whose decision as to the interpretation of the contract, made nearly a year after the date of the writ,
The amended declaration is for the balance due under the contract, which is alleged to have been fully performed. The amended answer, while containing an itemized statement of deductions including the cost of furnishing and putting in place of the iron frames, with a claim in recoupment, does not plead an adjustment of the matters in issue by arbitration or decision of the architects. It is well settled that an award or settlement must be pleaded, or it is not admissible in bar of the suit. Parker v. Lowell, 11 Gray, 353, 358. Furthermore by the written stipulation of the parties filed in the case it was expressly agreed that the plaintiff was entitled to the full amount unless the defendant was allowed the expense of providing and setting the frames. It is not disputed that all the woodwork contracted for by the plaintiff has been provided, and in the present controversy the only questions are, whether the plaintiff became bound to furnish exterior iron frames for ten of the large windows, and for two of the large doors. The answer depends upon the interpretation which should be given to the words “ window frames ” and “ door frames ” found in the contract. The only expression separate from the specifications which seems to indicate the nature of the materials, appears after the clause relating to the stationary furniture, which the plaintiff also was- to furnish, set and complete ready for use. If by implication there is ground for construing the words “ all other woodwork ” as referring to the preceding window and door frames and sash, because otherwise they appear to be meaningless, the defendant insists that the material of the items in dispute was to be of iron. The first paragraph of the contract not having expressly defined the kind of material to be used, resort must be had to the specifications. But as only one set of specifications and drawings had been prepared covering in detail the construction and completion of the building, the defendant, when making subordinate contracts, used by reference that part where the work to be done and materials to be furnished by the under contractor were described. The parties having agreed that the several specifications relating to
If the report had stated, that by agreement of parties the architect’s testimony, which was admissible only on the ground that an ambiguity existed in applying the contract to the subject matter, should be accepted and treated as a final explanation as to the meaning of the plans and specifications, the first ruling, that the contract was not ambiguous although inconsistent, with the second ruling fixing the amount due, would have become immaterial. It then would have been open for us to have determined whether the second ruling was correct, and to have ordered judgment for the plaintiff for either the amount found due by the trial judge, or the larger sum, if by the interpretation of the contract as explained by the architect the iron window and door frames were extraneous. But the parties not having so stipulated, and the plaintiff having excepted to the
It is unnecessary to discuss further or in detail the various and numerous offers of proof, as the ruling excluding oral evidence was general, and apparently they were not considered or dealt with specifically. Offers of proof moreover are not evidence until introduced, and supported by testimony, and at the second trial some of them may not be established while others may become irrelevant.
The questions asked and admitted in cross-examination, to which the plaintiff excepted, were within the discretion of the presiding judge. Jennings v. Rooney, 183 Mass. 577.
The verdict must be set aside and a new trial granted.
So ordered.