OPINION
This contract dispute is before the Court on defendant’s RCFC 12(b)(1) motion for partial dismissal for lack of jurisdiction. Defendant argues that plaintiffs failure to submit a claim requesting monetary relief to the contracting officer precludes the Court from exercising jurisdiction over plaintiffs request for damages arising from the termination of its lease for default. Plaintiff opposes the motion on the ground that the contracting officer’s final decision terminating the lease for default enables the Court to exercise jurisdiction over both its termination claim and its request for money damages. For the reasons discussed below, the Court GRANTS defendant’s partial motion to dismiss.
BACKGROUND
On August 24, 1998, the General Services Administration (GSA) awarded Lease No. GS-07-14651 (the Lease) to plaintiff for construction and leaseback of a building to .house the Social Security Administration in Gallup, New Mexico. The building was to be com
GSA declined plaintiffs request for a further extension of the construction completion date. On January 12, 2001, GSA directed plaintiff to stop work on the project. On February 21, 2001, defendant wrote a letter to plaintiff terminating the Lease for default effective February 22, 2001. The letter was characterized as “the final decision of the Contracting Officer” in accordance with the Lease’s disputes clause. GSA’s letter also informed plaintiff of its right to appeal the termination decision to the General Services Board of Contract Appeals or this Court. Plaintiff subsequently filed a claim with the Board, which dismissed the claim as untimely. DePonte Investments, Inc. v. General Services Administration, GSBCA 15,601,
Plaintiffs complaint alleges breach of contract in the form of unlawful termination for default and seeks relief in the form of damages for breach of the lease’s termination clause, interest and attorney’s fees in an amount to be determined. As grounds for damages, plaintiff further alleges that GSA “took action in connection with unrelated lease procurements to ensure that Deponte was denied award of each of these procurements,” and that “[tjhese lost opportunities have had a significant and material impact on the business and business reputation of Deponte.” Compl. ¶ 13.
ANALYSIS
Subject matter jurisdiction is a threshold matter which must be addressed before the Court reaches the merits of the plaintiffs claims. Steel Co. v. Citizens for a Better Env’t,
The Tucker Act confers jurisdiction on the Court to entertain a claim against the United States founded upon an express or implied contract. 28 U.S.C. § 1491(a)(1) (1988). The Tucker Act does not create a substantive right enforceable against the United States for money damages. United States v. Testan,
The Court’s jurisdiction under the CDA is predicated on the contractor’s fulfillment of two fundamental requirements: the submission of a written claim to the contracting officer, § 605(a), and the agency’s issuance of a final decision, § 609(a)(3). See Rex Sys., Inc. v. Cohen,
The Federal Acquisition Regulation (FAR) defines a monetary claim as “a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain.” 48 C.F.R. 2.101 (2002); see Reflectone, Inc. v. Dalton,
Plaintiff has failed to establish that these jurisdictional requirements have been satisfied with respect to its claim for money damages. Plaintiff does not contend that it filed a claim for money damages with the contracting officer prior to or after the issuance of a final decision on the lease termination. Rather, relying primarily on Federal Circuit precedent related to non-CDA disputes, plaintiff argues as a matter of law that the final decision on the lease termination for default is an adequate jurisdictional substitute for a CDA claim and final decision on money damages.
Plaintiffs argument that the Tucker Act provides independent jurisdiction over the money damage claim based on the final decision of termination is insupportable. The Federal Circuit has made it abundantly clear that a termination decision does not constitute a final decision on a money damage claim under the CDA for jurisdictional purposes. In Sharman, the Federal Circuit held that the CFC lacked jurisdiction over both the government’s and the contractor’s claim to unliquidated progress payments following a termination for default because there had been no final decision of the contracting officer regarding the claims for progress payments prior to the filing of the suit. As the Court noted, “the default claim and demand for return of unliquidated progress payments are separate and distinct ... for jurisdictional purposes.” Id. at 1570. Similarly, the Federal Circuit held that “the Claims Court will only entertain suits on claims, and those claims are limited to demands for money presently due and owing. A default termination is not such a claim.” Overall Roofing & Construction,
The eases plaintiff relies upon to establish this Court’s jurisdiction over the money damage claim are readily distinguishable. Daff v. United States,
The contracting officer’s final decision in this case makes no reference to a claim for money presently due because no such claim was ever submitted. The contracting officer’s decision to terminate the contract for default is a government claim against the contractor, not a contractor claim against the government. Malone v. United States,
The Court must either exercise jurisdiction over or dismiss the monetary claim. The Court does not have the option to grant a stay to allow the plaintiff to cure the jurisdictional defect by filing a certified claim with the contracting officer so that the plaintiff may obtain a final decision and amend the complaint. Once a claim is in litigation, the Department of Justice has the exclusive authority to act in the pending litigation, 28 U.S.C. §§ 516-20 (1988), thereby divesting the contracting officer of his authority to issue a final decision on the claim. Sharman,
CONCLUSION
For the reasons discussed above, defendant’s motion for partial dismissal is GRANTED. Pursuant to RCFC 54(b), as there is no just reason for delay, the Clerk of the Court is directed to enter judgment on plaintiffs claim for money damages and dismiss it without prejudice.
As discussed at oral argument, the Court will proceed with a determination on the issue of liability. Toward that end, the parties shall submit a proposed discovery and briefing schedule on the remaining issues by October 15, 2002.
IT IS SO ORDERED.
Notes
. For example, MPE Business Forms, Inc. v. United States,
