The facts, insofar as they are relevant to the instant appeal, are as follows: Appellant-defendant Department of Transportation (DOT) undertook a highway construction project which included the construction of some 15 bridges. DOT contracted with appellee-plaintiff Fru-Con Construction for the construction of these bridges. The contract specified that appellee would complete the bridges by a specified date and that, if it did not, it would be liable for liquidated damages. Appellee failed to complete the bridges within the time specified in its contract and, for this delay, DOT withheld liquidated damages from the amount of its final payment to appellee. Appellee filed suit against DOT, seeking not only to recoup the liquidated damages which had been withheld from its payment, but also seeking to recover damages for DOT’s alleged breach of contract. The case was tried before a jury and a substantial verdict, including an award of OCGA § 13-6-11 attorney’s fees, was returned in favor of appellee. DOT appeals from the judgment that was entered by the trial court on the jury’s verdict.
1. Grading work was preliminary to appellee’s bridge construction work. However, the graders with whom DOT had contracted for this preliminary work did not complete the grading within the time specified in their contracts. Alleging that it was this delay in the preliminary grading work that had caused the delay in its bridge construction work, appellee sought damages for losses and expenses it incurred as the result of the graders’ untimely performance. DOT enumerates as error the trial court’s denial of a motion for directed verdict as to appellee’s recovery on this claim.
In the absence of a contractual duty, there can be no breach of contract. The graders certainly owed a contractual duty
to DOT
to have the grading completed within the time specified in their grading
Moreover, Paragraph 105.07 of appellee’s contract with DOT provides: “When separate contracts are let within the limits of any one project, each contractor shall conduct his work so as not to interfere with or hinder the progress or completion of the work being performed by other contractors. Contractors working on the same project shall assume all liability, financial or otherwise, in connection with his contract and shall protect and save harmless [DOT] from any and all damages or claims that may arise because of inconvenience, delay, or loss experienced by him because of the presence and operations of other contractors working within the limits of the same project.” This is a clear and unambiguous expression of the mutual intent that DOT would
not
assume vicarious contractual liability for untimely performance by its various contractors and would
not
be liable to appellee for “damages relating to late delivery of [the bridge sites].”
Rhode Island Turnpike &c. Auth. v. Bethlehem Steel Corp.,
supra at 354. Compare
Department of Transp. v. Arapaho Constr.,
It follows that the trial court erred in failing to grant DOT’s motion for a directed verdict as to appellee’s claim for damages based upon delay allegedly attributable to the untimely performance of the preliminary grading work.
2. The holding in Division 1 would not preclude appellee from seeking to recoup liquidated damages withheld by DOT for appellee’s failure to complete the bridge work within the time specified. Paragraph 105.07 merely precludes appellee from recovering damages from DOT based upon delay attributable to untimely performance by the other contractors engaged in the highway project. It does not purport to authorize DOT to recover liquidated damages from appellee based upon delay which is not attributable to appellee.
DOT nevertheless enumerates as error the denial of its motion for a directed verdict as to appellee’s entitlement to recoup the withheld liquidated damages. According to DOT, appellee cannot contest its liability for liquidated damages because appellee did not make a timely written request for an extension of time as required under Paragraph 108.07 (D) of the contract, which provides as follows: “If the normal progress of the work is delayed for reasons beyond his control, the contractor shall within fifteen days after the start of such a delay, file a written request to the engineer for an extension of time setting forth therein the reasons for the delay which he believes will justify the granting of his request.”
Pursuant to this provision, if appellee wished to excuse any untimely performance of
its
work based upon the untimely performance of the preliminary grading work, appellee would be required to give DOT
written
notice within
15 days
of the date that the graders were otherwise contractually required to have completed their work. “[U]nder the terms of the contract, if [appellee’s] performance was delayed for reasons beyond its control, the proper contractual remedy was for it to apply, in writing, to the project engineer and [DOT] for an extension of time. . . . Assuming that [appellee] experienced any . . . delay for reasons beyond its control, the proper time for raising the issue was [“within fifteen days after the start of such a delay”] and the proper method for excusing the delay was that method identified in the contract. However, this contractual right to excuse . . . delays in performance was not asserted by [appellee] in a timely and proper fashion.”
Dan-D, Inc. v. Burnsed Enterprises,
The most that the evidence shows is that, in response to appellee’s untimely written requests for extensions of time, no extensions of time were forthcoming. “Viewing the evidence in the light most favorable to [appellee], it is clear . . . that [appellee] failed to substantially complete its contractual obligations within the time agreed upon by the parties, and that [appellee] produced no evidence of a contractual defense to [DOT’s] claim for liquidated damages. Accordingly, the trial court [erred] in [failing to hold], as a matter of law, that appellee was [not] entitled to [recoupment] of liquidated damages.” Dan-D, Inc. v. Burnsed Enterprises, supra at 207-208 (1).
3. Appellee urges that, even if the trial court erred in failing to grant DOT’s motion for a directed verdict as to the contractual claims for damages and recoupment of liquidated damages based upon delay attributable to the graders, the judgment as to those claims must nevertheless be affirmed because, in addition to recovery under the terms of the contract, appellee sought recovery under an alternative eminent domain theory. Appellee urges that, under the “right for any reason” rule, the judgment in its favor must be affirmed under this alternative theory.
There is authority for the proposition that one who has contracted with the state can sue and recover based upon an eminent domain theory. C.
F. I. Constr. Co. v. Bd. of Regents &c. of Ga.,
The state
no
longer has a sovereign immunity defense to contract actions brought against it. “[T]he state’s defense of sovereign immunity is . . . waived as to any action ex contractu for the breach of any written contract. . . entered into by the state or its departments and agencies.” Art. I, Sec. II, Par. IX (c) of the Ga. Const, of 1983. Accordingly, the present constitutional provision waiving the defense of sovereign immunity has obviated the holdings in C.
F. I. Constr. Co.
and
Fonda Corp.
One
can
now sue the state on an express contract and this viability of a claim on the express contract
precludes
recovery on an implied contract theory. “There cannot be an express and implied contract for the same thing existing at the same time between the same parties. It is only when the parties themselves do not expressly agree, that the law interposes and raises a promise; and no agreement can be implied where there is an express one existing.”
Ramsey v. Langley,
Moreover, even if appellee could rely upon implied contract as a viable alternative theory of recovery, the judgment for damages and recoupment of liquidated damages discussed in Divisions 1 and 2 still could not be affirmed under that theory. The jury returned a general verdict and did not specify under what
theory
the award of damages was being returned, and the verdict may well have been based upon the erroneous legal theory that DOT was liable on those claims under the express contract.
England v. Ga.-Fla. Co.,
4. In addition to the claim for damages for delay discussed in Division 1 and the claim for recoupment of liquidated damages discussed in Division 2, appellee also sought to recover certain “direct costs.” DOT does not enumerate any error with respect to its liability
5. The partial grant of new trial discussed in Division 4 requires that we address certain rulings which may recur at that limited retrial. Those rulings all relate to appellee’s recovery of OGCA § 13-6-11 attorney’s fees.
“OCGA § 13-6-11 does not create an independent cause of action. That statute merely establishes the circumstances in which a plaintiff may recover the expenses of litigation as an additional element of his damages. [Cit.]”
Brown v. Baker,
The trial court refused to admit certain evidence which DOT asserted was relevant to its defense to liability for OCGA § 13-6-11 attorney’s fees. The trial court acknowledged the relevancy of the evidence,. but nevertheless excluded it on the ground that it “would be misleading to the jury and prove a significant problem for them to focus on the issues that we have in this case.” The trial court was correct in recognizing the potential relevancy of the excluded evidence to DOT’s defense to the recovery of OCGA § 13-6-11 attorney’s fees. Even assuming that the trial court was further correct in ruling that the evidence was nevertheless excludable because its potential for confusing the jury outweighed its relevancy, that rationale will certainly not exist at the limited retrial, wherein the sole issue will be DOT’s liability for the “direct costs” and its bad faith, stubborn litigiousness or causing unnecessary expense as to appellee’s recovery of those costs. Accordingly, if DOT seeks to introduce the evidence at retrial, the trial court should admit it for the jury’s consideration.
Finally, DOT enumerates as error the trial court’s failure to give
appellee’s
timely written request to charge on OCGA § 13-6-11 attorney’s fees. It would appear that the language of appellee’s request was
6. Remaining enumerations of error have been considered and are found to be moot or to be unlikely to recur at the limited retrial.
7. The judgment is reversed as to appellee’s claims for damages and for recoupment of liquidated damages based upon delay, with direction that the trial court enter judgment in favor of DOT as to those claims. The judgment is reversed as to appellee’s claim for “direct costs” and OCGA § 13-6-11 attorney’s fees, with direction that a new trial be held as to that claim.
Judgment reversed with direction.
