DEPARTMENT OF TRANSPORTATION, an agency of the State of Florida, Appellant,
v.
RONLEE, INC., a Florida Corp., Appellee.
District Court of Appeal of Florida, Third District.
A.J. Spalla, Gen. Counsel, and Robert I. Scanlan, Deputy Counsel, and Maxine F. Ferguson and James W. Anderson, Tallahassee, for appellant.
Sparber, Shevin, Shapo, Heilbronner & Book and Glenn J. Waldman and Jeffrey M. Weissman, for appellee.
Before SCHWARTZ, C.J., and HENDRY and FERGUSON, JJ.
PER CURIAM.
The threshold question presented is whether the successful bidder for a government road construction contract is entitled to reformation of the contract to increase the price by $317,463 based on a unilateral mistake, after the competing bids are all opened, where the new contract price would still be lower than the second lowest bid.
The Department of Transportation (DOT) solicited bids pursuant to section 337.11, *1327 Florida Statutes (1985), for the construction of an interchange at the intersection of State Road 826 and Interstate 75 in Hialeah. On December 7, 1983, DOT declared Ronlee, Inc. the apparent low bidder with a bid of $15,799,197.90. The second lowest bid exceeded Ronlee's bid by $610,148.[1]
On February 13, 1984, DOT entered into a contract with Ronlee to construct the project based on the bid, and on March 7, 1984, gave Ronlee notice to proceed with the project. Five days later, Ronlee advised DOT that the bid contained a "stupid mistake" in the amount of $317,463. The letter alleged an error with respect to the unit bid price for concrete culverts which occurred when an employee of Ronlee erroneously transcribed a phone quote of $525 for each culvert as $5.25 each. By letter dated March 21, 1984, DOT informed Ronlee that it was aware of the apparently unbalanced unit price for the concrete culverts, but that it was unable, as a matter of state policy, to permit an increase in the contract price.
Nevertheless, on March 22, 1984, having made no effort to withdraw the bid, Ronlee began construction of the project. Twentyone months later, with the project seventyfive percent completed, Ronlee filed suit against DOT seeking reformation of the contract. Both sides moved for summary judgment, agreeing that the material facts were not in dispute. Ronlee's motion for summary judgment was granted, the trial court holding that DOT's silence about Ronlee's apparent error in price calculations constituted inequitable conduct and that reformation of the contract would not undermine the competitive bidding process. In addition to the $317,463, the court awarded Ronlee $60,000 in prejudgment interest and costs. We reverse.
Where a contractor makes a unilateral error in formulating his bid for a public contract, the remedy is rescission of the contract. Jones, The Law of Mistaken Bids, 48 U.Cin.L.Rev. 43, 49 (1979); Annotation, Right of Bidder for State or Municipal Contract to Rescind Bid on Ground that Bid was Based Upon His Own Mistake or that of His Employee,
No reported Florida decision has permitted reformation by belated request of a bid contract for a public project in order to make it profitable to the contractor.[2]Graham v. Clyde,
The Florida Supreme Court, citing a number of cases from other jurisdictions, reversed, holding that unilateral errors are not generally relieved and that there was no equitable basis for relief. In an opinion by Justice Terrell the court stated the reason for the firm rule:
If errors of this nature can be relieved in equity, our system of competitive bidding on such contracts would in effect be placed in jeopardy and there would be no stability whatever to it. It would encourage careless, slipshod bidding in some cases and would afford a pretext for the dishonest bidder to prey on the public... . After the bid is accepted, the bidder is bound by his error and is expected to bear the consequence of it.
The prevailing view is that reformation is not the appropriate form of relief for unilateral mistakes in public contract bids where the bidder is negligent. Dale Ingram, Inc. v. United States,
A written instrument may be reformed where it fails to express the intention of the parties as a result of mutual mistake, or unilateral mistake accompanied by inequitable conduct by the other party. Camichos v. Diana Stores Corp.,
Competitive bidding statutes are enacted to protect the public and should be construed *1329 to avoid circumvention. Wester v. Belote,
Further, Ronlee forfeited any right it may have had to reformation or rescission. It had knowledge of its own mistake at least ten days before commencement of construction. Ronlee's conduct in performing according to the terms of the agreement for twenty-one months instead of seeking to withdraw the bid, after DOT had advised that it could not administratively correct the error, effected a waiver of rights. See Farnham v. Blount,
Reversed and remanded with instructions to enter judgment for the Department of Transportation.
HENDRY and FERGUSON, JJ., concur.
SCHWARTZ, Chief Judge (dissenting).
With respect, I must dissent. The majority does not say that the record shows and the trial judge found just the inequitable conduct by the DOT which, under principles it acknowledges, renders reformation an entirely appropriate remedy: although the DOT was aware of the mistake when the bids were opened and well before construction commenced, it deliberately failed to inform the contractor of this fact. The final judgment under review contains, among others, the following, essentially undisputed determinations:
(e) The Defendant acknowledged receipt of notice, prior to commencement of construction, of the existence of the error and further acknowledged that the Plaintiff's bid "error was unintentional" and "resulted from inexperienced personnel" generating a simple mathematical error by misplacing a decimal point and "not comprehending the reasonableness of the money figures being used." (Exhibit "D" to Plaintiff's Motion).
(f) Indeed, the Defendant even admitted that prior to the Plaintiff's March 12, 1984 notification to the Defendant, the Defendant had already been "aware of the apparent unbalanced unit price of the item of Class II Concrete Culverts" (Exhibits "D" and "C" to Plaintiff's Motion; Plaintiff's Motion at 5-6, 9). Exhibit "C", a December 19, 1983 computer print-out (entitled "summary of bids") produced by Defendant during discovery, demonstrates that the "apparent unbalanced unit price" with respect to the bids "opened at Tallahassee, Florida on December 7, 1983" was known to Defendant promptly upon examination of the bids.
3. The Court is therefore of the view that Plaintiff has proved inequitable conduct by the Defendant by clear and convincing proof. Clearly, the Defendant was aware, or certainly should have been aware, that the unit item bid price for 400-2-1 Class II Concrete Culverts was one hundred (100) times less than the nearest unit price for the same item. However, the Defendant chose wrongfully to remain silent as to the existence of this error and, further, refused to act *1330 equitably after the Plaintiff had discovered the error and promptly acted to notify the Defendant of the error.
On this basis, the trial court held:
4. While the Court is not unmindful of the fact that competitive bidding statutes should be construed to avoid circumvention, under the unique facts of the case sub judice, the integrity of the competitive bidding process will not be undermined with the granting of contract reformation. Where, as here, the differential between the mistaken bid and the second lowest bid exceeds the amount of the error sought to be reformed, no frustration or harm to beneficial purpose can fairly be demonstrated.
I entirely agree.
It is undisputed that, through a simple mistake in decimal point transcription, Ronlee was out and the DOT was in over $300,000 in material expenses. Short of reliance on the well-known playground maxim about keepers and weepers, there is no reason why the state should be entitled to retain this found money. Under ordinary reformation law, the combination of a unilateral mistake and inequitable conduct fully justifies that relief, Camichos v. Diana Stores Corp.,
The very salutary Florida rule of unilateral mistake which represents a minority view on the question, Maryland Casualty Co. v. Krasnek,
NOTES
[1] The four sealed bids received were:
Ronlee, Inc. $15,799,197.90 Triple R. Paving, Inc. $16,409,345.63 Capeletti Bros., Inc. $18,996,533.56 State Paving Corp. $19,186,879.40
Notes
[2] Appellee cites two cases, Hotel China & Glassware Co. v. Board of Public Instruction,
Hotel China & Glassware holds that one who files a bid pursuant to an invitation issued under the competitive bidding statutes of this state has no right as a matter of law to withdraw such bid after all bids have been opened and the results made known. The Clutter case set out equitable conditions which justified allowing a contractor to withdraw its bid.
[3] Appellee calls our attention to Chernick v. United States,
First, the court recognized a duty on the part of government contracting officers under the circumstances to call the bidder's attention to the manifest mistake. Reformation was then approved because the plaintiffs discovered their mistake too late for rescission as a feasible remedy. The instant case, however, is easily distinguishable because there was no disparity in expertise, or other special circumstances, which imposed a special duty or obligation on government contracting officers. Here, unlike in Chernick, the bidder was aware of its mistake soon after the bids were opened and before commencement of construction while rescission was still a feasible remedy.
[1] Unlike the majority, I do not believe that Graham v. Clyde,
