160 Wash. 2d 786 | Wash. | 2007
Lead Opinion
¶1 The parties before us agreed to resolve their underlying dispute in binding arbitration. Fluor Daniel, Inc., prevailed and moved to reduce the arbitration award to judgment. Concluding that the arbitration award liquidated previously nonliquidated damages, the trial court reduced that award to judgment and added prejudgment interest from the date the arbitrator rendered the award to the time it was entered into judgment. We conclude that an arbitration award does not transform an unliquidated claim into a fully liquidated sum entitling the prevailing party to prejudgment interest. Unliquidated damages accrue interest from the date of judgment, not the date of an arbitration award. We affirm the Court of Appeals and remand to the trial court for entry of judgment without prejudgment interest.
FACTS
¶2 The Department of Corrections (Department) contracted with Fluor to build a prison. Clerk’s Papers (CP) at 3. The parties tell us that “major disputes developed,” leading to “extremely expensive” litigation. CP at 3.
¶3 Twenty-one days later, Fluor reduced the award to judgment. Fluor asked, over the Department’s objection, for prejudgment interest from the date of the arbitration until
ANALYSIS
¶4 Only questions of law are presented. Our review is de novo. Parents Involved in Cmty. Sch. v. Seattle Sch. Dist. No. 1, 149 Wn.2d 660, 670, 72 P.3d 151 (2003).
¶5 A party is entitled to prejudgment interest if the damages awarded are liquidated. Historically, contract damages were considered “liquidated” if they could be determined by “reference to a fixed standard contained in the contract, without reliance upon opinion or discretion,” and interest has long been available from the moment of breach. Mall Tool Co. v. Far W. Equip. Co., 45 Wn.2d 158, 176, 273 P.2d 652 (1954) (emphasis omitted); see also Wright v. City of Tacoma, 87 Wash. 334, 353, 151 P. 837 (1915) (same); 14A Karl B. Tegland, Washington Practice: Civil Procedure § 35.13, at 434 (2003). It is comparatively easy to determine whether damages are liquidated when the parties’ own contract so provides. E.g., Trompeter v. United Ins. Co., 51 Wn.2d 133, 316 P.2d 455 (1957) (claim was liquidated where the amount due was specifically provided for in the insurance policy). Sometimes statutory law will provide fixed standards that will allow damages to be liquidated. E.g., Egerer v. CSR W., LLC, 116 Wn. App. 645, 653-56, 67
¶6 If damages are liquidated, interest accrues from the time they were incurred. Hansen, 107 Wn.2d at 473 (“plaintiff should be compensated for the ‘use value’ of the money representing his damages for the period of time from his loss to the date of judgment” (emphasis added)). Nothing in our case law or the underlying jurisprudence supports the proposition that the character of damages changes from unliquidated to liquidated by virtue of being decided. See generally Weyerhaeuser Co., 142 Wn.2d at 686 (character of the claim determines whether damages are liquidated).
¶7 Generally, interest on a damage award begins to run when judgment is formally entered by a trial court, not
¶8 We turn now to Pluor’s arguments. Fluor does not argue that its damages were liquidated before the arbitrator reached his decision.
¶10 Fluor contends that a binding arbitration award is more like an entered judgment than a jury’s verdict, on the theory that a jury’s verdict is subject to substantial revision; a binding arbitration award, Fluor argues, is not. Cf. Kiessling, 38 Wn.2d at 297 (noting that one reason interest
¶11 Next, Fluor argues that one Washington court has already approved prejudgment interest upon an arbitration award, City of Moses Lake v. Int'l Ass’n of Firefighters, Local 2052, 68 Wn. App. 742, 847 P.2d 16 (1993). Firefighters arose out of a binding arbitration proceeding authorized in the State’s collective bargaining statutes to resolve certain types of collective bargaining disputes. See ch. 41.56 RCW. Under that statutory scheme, if “uniformed personnel” and a government subdivision are unable to agree upon wages, they are authorized to refer the problem to a three-judge arbitration panel. RCW 41.56.450. This panel’s decision is subject to review by the superior court “solely” to determine whether it was arbitrary and capricious. Id. Essentially, the superior court acts in an appellate capacity.
Prejudgment interest is allowable when the amount claimed is liquidated, i.e., “where the evidence furnishes data which, if believed, makes it possible to compute the amount with exactness, without reliance on opinion or discretion.” The salary increase meets the definition of liquidated. As of May 31, 1991, the date of the award, the City was under a duty to raise the firefighters’ salaries in the amount specified, subject only to review as provided in RCW 41.56.450. Contrary to the City’s argument, the signing of a collective bargaining agreement in accordance with that award is not a prerequisite to the legal obligation to abide by the award.
The judgment of the Superior Court is affirmed, except for that portion denying prejudgment interest. Prejudgment interest is allowed from May 31, 1991.
Firefighters, 68 Wn. App. at 749 (emphasis added) (quoting Prier v. Refrigeration Eng’g Co., 74 Wn.2d 25, 32, 442 P.2d 621 (1968) and citing Hansen, 107 Wn.2d at 472). The Court of Appeals decided that the salary increase that had been ordered by the arbitration panel was properly characterized as liquidated and that “prejudgment interest” was appropriate. Thus, the Firefighters court’s holding was based upon its conclusion that under the statute in question, the salary increase could be calculated with certainty and was therefore liquidated. The Court of Appeals did not hold that the award became liquidated by virtue of the arbitration award.
Once the Arbitrator issues a decision, either party may submit the decision to the King County Superior Court in the action now pending. The parties agree the judgment to be entered will be in full and complete compliance with the decision of the Arbitrator. Once said judgment is entered the judgment will be final and binding on Fluor and DOC. Fluor and DOC each waive any and all rights to appeal the Arbitration Award.
CP at 6 (para. 8 of the Partial Settlement & Alternative Dispute Resolution Agreement). Fluor reasons that because the Department waived any right to appeal the arbitration award, the binding nature of the arbitration liquidated the damages.
¶14 The goal of contract interpretation is to carry out the intent of the parties as manifested, if possible, by the parties’ own contract language. Hearst Commc’ns, Inc. v. Seattle Times Co., 154 Wn.2d 493, 504, 115 P.3d 262 (2005). We find nothing in the words the parties used that suggests they explicitly agreed to postarbitration award of interest.
CONCLUSION
¶15 Generally, an arbitration decision does not convert unliquidated damages into liquidated damages and does not entitle the winner to prejudgment interest between the date of the arbitration decision and entry of judgment. We hold that unless the parties agree otherwise in their arbitration agreement, interest on an award does not begin to accrue until it is entered as a judgment. We affirm the Court of Appeals and remand to the trial court for entry of judgment on the arbitrator’s original award.
Alexander, C.J., and C. Johnson, Madsen, Bridge, Owens, Fairhurst, and J.M. Johnson, JJ., concur.
The record before us does not provide details of the underlying construction dispute.
It appears to us that the arbitrator properly could have found that some or all of the breach of contract damages were liquidated and provided for prejudgment interest from the time the damages were incurred until judgment. No such issues are before us.
We note that CR 54(f)(2)(C) permits entry of judgment at the time the verdict or findings are entered while opposing counsel is in open court.
Nothing in this opinion should be read to suggest that an arbitrator could not have found that damages could be calculated based upon a fixed standard and awarded prejudgment interest from the date damages were incurred.
In Westmark, the Court of Appeals vacated a trial judge’s award of prejudgment interest on an arbitration award. Unfortunately for our purposes, the court did not distinguish between pre- and postawards of prejudgment interest, and thus it does not necessarily answer Fluor’s arguments.
The 2005 legislature repealed Washington’s former Uniform Arbitration Act, chapter 7.04 RCW, and replaced it with a revised Uniform Arbitration Act, chapter 7.04A RCW. See Laws op 2005, ch. 433, §§ 1-32, 50. While the changes do not appear to be material to this case, we have not scrutinized the revised act.
We note that the Court of Appeals in Firefighters calculated the liquidated interest from the date of the arbitration award instead of the date the wage increase accrued. However, it appears that the Court of Appeals was asked
The State argues that Fluor is violating the arbitration agreement by seeking prejudgment interest. We disagree. The fact the parties disagree on the meaning of the contract does not mean either one seeks to violate it.
Dissenting Opinion
¶16 (dissenting) — Fluor Daniel, Inc., and the Department of Corrections (DOC) agreed to resolve their legal dispute in binding arbitration. The arbitrator issued a decision in favor of Fluor, and Fluor moved the superior court to confirm the award and enter judgment. The court did so and awarded Fluor prejudgment interest dating back to the date of the arbitration decision. DOC appealed. The Court of Appeals directed entry of judgment but denied any award for prejudgment interest. Our majority now affirms. Because Fluor is entitled to prejudgment interest from the date of the arbitration decision, I dissent.
¶17 The Court of Appeals properly approved prejudgment interest on an arbitration award in City of Moses Lake v. International Ass’n of Firefighters, Local 2052, 68 Wn. App. 742, 847 P.2d 16 (1993). There the city of Moses Lake entered into negotiations with the city’s fire fighters for a new collective bargaining agreement governing the terms and conditions of the fire fighters’ employment. After negotiations stalled on several issues, the issues were referred to an interest arbitration panel pursuant to RCW
¶18 Here, the majority holds Fluor’s award was not liquidated at the time of the arbitrator’s decision, and therefore Fluor was not entitled to prejudgment interest. To support its position the majority analogizes arbitration awards to jury verdicts, contending an arbitrator’s award, like a jury verdict, “is also subject to modification prior to entry of judgment even outside of the appeal provisions.” Majority at 793. Therefore, reasons the majority, because “the parties did not contract to remove the trial court’s power to make modifications under former RCW 7.04.170, only to forgo their appeal rights,” the arbitrator’s award was “not completely fixed until entered into judgment.” Id. (emphasis omitted).
¶19 The majority’s analogy of arbitration awards to jury verdicts is problematic. Jury verdicts must be reduced to judgment by a court to become final. Cox v. Charles Wright Acad., Inc., 70 Wn.2d 173, 179, 422 P.2d 515 (1967). And there is always the prospect the verdict will never be reduced to judgment pursuant to a successful motion for judgment notwithstanding the verdict. CR 50(b). By con
¶20 Furthermore, contrary to the majority’s contention, Fluor and DOC did explicitly contract to remove the superior court’s power to make modifications. Their arbitration agreement provides,
Once the Arbitrator issues a decision, either party may submit the decision to the Kang County Superior Court in the action now pending. The parties agree the judgment to be entered will be in full and complete compliance with the decision of the Arbitrator. Once said judgment is entered the judgment will be final and binding on Fluor and DOC. Fluor and DOC each waive any and all rights to appeal the Arbitration Award.
Clerk’s Papers at 6 (emphasis added). The sentence “The parties agree the judgment to be entered will be in full and complete compliance with the decision of the Arbitrator” indicates the parties’ intention to remove the superior court’s ability to modify the award in addition to waiving their appeal rights.
¶21 Because the majority’s decision is at odds with the parties’ language in their arbitration agreement and because I would uphold the trial court’s grant of prejudgment interest from the date of the arbitration decision, I dissent.
RCW 41.56.450 provides the arbitration panel’s determination “shall be final and binding upon both parties, subject to review by the superior court upon the application of either party solely upon the question of whether the decision of the panel was arbitrary or capricious.”
Under Washington’s repealed arbitration statute, former chapter 7.04 RCW, repealed by Laws of 2005, ch. 433, § 50, a party to arbitration had the right to seek review of the award. See former RCW 7.04. Í60, .170 (authorizing vacation and modification of arbitration award).