148 F.2d 746 | 5th Cir. | 1945
In culmination of a loop line construction program of long standing,
In their motion for rehearing before the Commission, petitioners did formally make the point that the applicant had not shown itself possessed of sufficient reserves to adequately perform the service to the public for which the certificates were sought. But the real point made against the order in the rehearing was, and the real point made against it here is, that the certificates of public convenience and necessity may not stand because they were issued to perr mit the withdrawal of gas, and irreplaceable natural resource, for burning under boilers, an industrial use, that is regarded as inferior and wasteful, and, therefore, the granting of the certificates was not in, but against, the public interest.
The subordinate claim that the proof is insufficient to support the finding that the company has adequate supplies to enable it to properly serve the public interest may be disposed of in short order by saying that the record ámply supports the commission’s finding both that there was a public need to be served and that the applicant for the certificates showed itself adequately equipped to perform it.
The main contention, that the order is invalid and the certificates may not stand because issued for a wasteful use of gas, is, we think, no better taken, but a demonstration of this will require some further reference to the Act, to the proceedings before the commission, and to the authorities governing the review of its orders.
The Natural Gas Act was enacted to vest, and it did vest, the commission with jurisdiction to regulate the transportation and sale of natural gas for re-sale in interstate commerce.
Petitioners do not claim that the Memphis Natural Gas Co. is not a qualified applicant or that it has not the financial ability to constitute, finance and operate the proposed facilities. The commission has found on evidence amply supporting it that the applicant has assured itself adequate gas reserves for the operation of the line. The commission has also found that the proposed extension is, or will be, required by the present or future public convenience and necessity, and viewing the matter entirely from the standpoint of consumer demand for the gas, the evidence is of such conclusive character that it demands the finding that was made. Petitioners’ reliance, however, is not on the ordinary considerations which control where the dispute is between rival companies, as it was
We agree with the commission. Assuming, without deciding, that the commission could properly consider as one of the facts entering into the granting or de
Beginning its operations as an interstate pipe line company in 1928, its system consisted of an 18-inch pipe line extending from the Monroe, Louisiana, gas field through the States of Arkansas, Mississippi, and to Memphis, Tenn. For the past seventeen years it has supplied natural gas to various city gate utility distributing companies, in the States of Arkansas, Mississippi and Tennessee, the principal customer being the City of Memphis, Tennessee.
In 1940, it began a construction program of a loop line paralleling its original 18-inch pipe line from the Monroe field to Memphis. The proposed plan was to loop completely this line over a period of years. The purpose of the construction program was to provide pipe lino capacity to meet the increased demands of its city gate customers.
In .1940, 92 miles of the looping were completed; in 1941, an additional 55 miles were constructed; in 1942, and also in 1948, the company attempted to complete the loop line construction, but, due to war emergency conditions, the materials and priority assistances were unavailable, and it was not until December, 1948, that the War Production Board granted approval and permit to construct the balance of the loop line.
In connection with the construction of the lines in 1940 and 1941, it was not necessary for the company to obtain a certificate from the Federal Power Commission. However, Section 7 of the Natural Gas Act was amended as of Feb. 7, 1942, and it became necessary for the company to obtain from the Federal Power Commission, a certificate of public convenience and necessity to construct the balance of the loop line.
On Jan. SI, 1944, it filed with the Federal Power Commission its application for a certificate of public convenience and necessity for the construction and operation of 02.5 miles of loop lines. Intervening in this proceeding were the State of Tennessee, the Memphis Light, Gas & Water Division of the City of Memphis, Tennessee, and The Independent Natural Gas Association of America, supporting the application, and the Public Service Commission of Louisiana, the Department of Conservation of the State of Louisiana, the National Coal Association, the United Mine Workers of America, the Order of Railway Conductors, the Brotherhood of Locomotive Engineers, the Brotherhood of Locomotive Firemen and Bnginemen, and the Switchmen’s Union of North America, opposing it.
On May 20, 1944, the company filed with the Commission an application for a certificate of public convenience and necessity for the construction and operation of a gas transmission line from1 Guthrie, Louisiana, in the Monroe gas field to Lisbon gas field in Claiborne Parish, Louisiana.
The same parties supporting and opposing the granting of the first certificate! oppose this one also.
On Juno 10, 1944, the Commission, stating in its opinion and order that a sufficient showing of adequate gas reserve had not been made, denied and dismissed without prejudice the application for the* certificate in the looping project. A petition for rehearing, reconsideration and' reversal of the Commission’s order of June .1.0, 1944, was made and granted.- and an opportunity to present further-evidence was provided.
The two Dockets involving the certificates for the looping project and the-Lisbon line were consolidated by order" of the Commission, and a hearing in trieconsolidated causes began on September" 7, and was concluded on Oct. 5; 1944;.
Petitioner here filed application for rehearing and stay order in the consolidated Docket, and it was denied on Dec. 12, 1944, and on Dec. 21, 1944, this petition was filed.
As material here, it provides 15 IT. S.O.A. § 717r: “Any party to a proceeding under this act aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the circuit' court of appeals * * *. No objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the application for rehearing unless there is reasonable ground for failure so to do. The finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive.”
15 U.S.C.A. §§ 717-717W.
Illinois Natural Gas Co. v. Central Illinois Public Service Co., 314 U.S. 498, 62 S.Ct. 384, 86 L.Ed. 371; Natural Gas Pipeline Co. v. Federal Power Commission, 315 U.S. 575, 62 S.Ct. 736, 86 L.Ed. 1037; Public Utilities Commission v. United Fuel Gas Co., 317 U.S. 456, 63 S.Ct. 369, 87 L.Ed. 396; Federal Power Commission v. Hope Natural Gas Co., 320 U.S. 591, 64 S.Ct. 281, 88 L.Ed. 333.
In opinion of dune 10, 1944, refusing the certificate on the loop lino, the commission did comment, on the capacity of standby-fuel equipment on the premises of certain industrial consumers, and on the fact that the estimated demand anticipated demands of now customers, including a number proposed to be converted from the use of other available fuels to natural gas for boiler fuel purposes.
Too, it concluded: “(3) In view of the limited natural gas reserves shown by the record to bo available to applicant, their present rapid rate of depletion, and the effect of excessive rates of withdrawal of the ultimate recovery of gas therefrom, it is necessary and appropriate in the public interest that such natural gas resources be conserved in so far as possible foj- domestic, commes'cial and superior industrial purposes. (.4) The record does not contain sufficient showing that the proposed construction and operation are, or will be required by the public, or future public, convenience and necessity. (5) Dismissal of the instant application without prejudice is appropriate in the public interest.”
In its second opinion on rehearing, entered November 21st, after hearing new evidence, the commission found that applicant had sufficiently and satisfactorily increased its gas supplies; and that in thc public interest the certificates for the proposed loop line and Lislxm line should be granted. The opinion dealt fully with the contention as to the use ol natural gas for inferior purposes, including the increased use from change over from coal to natural gas in future by customers of the plant. After pointing out that the question of the supply of natural gas had been a subject of communication by it to congress, it concluded that the small amount of additional gas to be sold by applicant (o3ily about 1.3 percent of the total natural gas production of Louisiana) was not sufficient to cause any groat loss.
The opinion concluded: “While we are not unsympathetic with the effort of the producing state of Louisiana to protect and conserve its natural gas resources for the beneiit of its citizens, it is apparent that denial of applicant’s request for these certificates will not afford the State of Louisiana a satisfactory solution of the problem posed by it. Such problem cannot be determined within the limits of these proceedings. It is reasonable, however, to condition the certificates so that the facilities herein authorized shall not be used for the traiisportation or sale of natural gas to any new customers of either Applicant or United, except upon specific authorization by this commission.”
Penn. v. West Virginia, 262 U.S. 553, 43 S.Ct. 658, 67 L.Ed. 1117, 32 A.L.R. 300; State of Missouri v. Kansas Gas Co., 265 U.S. 298, 44 S.Ct. 544, 68 L.Ed. 1027; Foster-Fountain Packing Co. et al. v. Haydel, 278 U.S. 1, 49 S.Ct. 1, 73 L.Ed. 147; West v. Kansas Gas Co., 221 U.S. 229, 31 S.Ct. 564, 55 L.Ed. 716, 35 L.R.A.,N.S., 1193.