19 Colo. 539 | Colo. | 1894
delivered the opinion of the court.
The correctness of the judgment appealed from depends upon the construction to be given to clause 12 of the contract above set forth. It is contended by counsel for appellant that this clause should be construed to provide for the payment of the sum of $5.00 per day for each house, or $40.00 per day for each day that elapsed after the period of ninety days from the execution of the contract, during which the
The contract was for the building of eight houses, to be commenced at the same time and completed at the same time. In other words, it was a contract that in terms .provided for the erection and completion of the entire number of houses specified, and its full performance required the completion of them all. The sum specified as liquidated damages was to he paid in case of default in the performance of this contract within the time limited, and is expressly fixed at $5.00 per day for the number of days such default continued.
Such is the purport of the language used. It is, that if the party of the first part shall “fail to complete the work upon any of the said houses * * * it shall pay * * * the full sum of five dollars per day for each and every day thereafter that work upon either of the said houses shall so remain unfinished.”
It is to be presumed that the parties used language to express their meaning, and if the}r had intended to provide for the forfeiture of $5.00 per dajr for each house they would have made that intention clear by adding those words, instead of using language that imports a different intention and meaning. And, furthermore, this construction must be given in order to effectuate the intention of the parties to provide for liquidated damages. The total valuation of the houses under the terms of this contract was about $22,000, and the amount claimed as liquidated damages upon appellant’s contention amounts to $1,200 per month, over 60 per cent per annum on the contract price.
Clauses of this character are generally construed as penalties, and the amount usually awarded thereunder is actual compensation for the loss accruing upo'n the default and failure to perform the contract within the time limited.
If, therefore, the construction contended for by appellant should he adopted, the amount specified as liquidated dam
It is unnecessary to determine whether the trial court erred in requiring the appellant to assume the affirmative and open the case. The evidence introduced for the purpose of explaining the clause of the contract under consideration was inadmissible, and the court so adjudged in its final decision. The rights of the parties under the pleadings were dependent alone upon the meaning to be given to the provisions of the contract relating to liquidated damages, and this meaning was to be ascertained from those provisions themselves.
The court acted upon this view, and construed the clause in question without regard to extrinsic evidence, and therefore the error, if any, in requiring appellant to assume the burden of proof was an immaterial one, and in no way prejudiced appellant’s rights. No error sufficient to justify a reversal appearing upon the record, the judgment must be affirmed.
Affirmed.