*1 The Robinson Dilem- ized Procedures”: 141).
ma, Sup.Ct.Rev. majority’s definition of custodial arrest
and the distinction drawn between it and arrest, cornerstone of the
non-custodial
opinion, scrutiny. does not withstand careful arrest,
By categories establishing distinct has created tenuous and bur- distinction, extremely
densome one difficult practical application by police comply Fourth
must Amendment law.
The officers this case did not violate the rights.
defendant’s Fourth Amendment suppress
would cocaine found on the
defendant, therefore, I and concur with the
majority’s only. result say
I am authorized to that Justice VOL- join
LACK Justice MULLARKEY
this concurrence. CONTRACTOR,
DENNIS I. SPENCER
INC., corporation, a Colorado
Petitioner, AURORA, Colorado,
CITY OF Municipal corporation,
Respondent.
No. 93SC529. Colorado,
Supreme Court of
En Banc.
Nov. Benson,
Faegre Cook, & Michael J. Nata- Hanlon-Leh, Denver, petitioner. lie City Atty., Office of the Charles H. Rich- ardson, Aurora, Gulley Gaar, P.C., Dale Gaar, Associates, Englewood, A. York & O’Brien, Littleton, Marcia G. respondent. Opinion Justice VOLLACK delivered the of the Court. Contractor,
Dennis I.
(Spenc-
Inc.
Contractor), petitions
er
this court to review
*2
by
appeals
requested
the
of
in Den- Contractor
additional
time
decision
the court
and
Spencer
City
Inc. v.
compensation
nis
Auro-
complete
to
the construction
of
1993)
ra,
(Colo.App. Mar.
No. 92CA0176
granted
fourteen-day
contract. Aurora
(not
publication),
selected for official
affirm-
extension,
compensate
time
but
to
refused
ing
ruling that
respon-
the trial court’s
the
Spencer Contractor for additional construc-
dent,
(Aurora),
City
the
which
of Aurora
subsequently
tion costs. Aurora
assessed
by
to
found
the trial court
have breached a
liquidated damages
Spencer
Contrac-
agree-
construction contract
a settlement
and
complete
project
tor when it failed to
the
on
ment,
prevailing
was the
on the settle-
time.
agreement
ment
entitled to
and
August
In
Spencer Contractor filed a
fees.
action,
civil
claiming that Aurora had breach-
granted
to
We
certiorari
decide the
by refusing
ed the construction contract
determining
prevailing par
standard for
the
change
by failing
issue time
and
orders
ty
purposes
awarding attorney
for
of
good
performing
exercise
faith in
its duties.
pursuant
fee-shifting provision
in
a set
later,
Approximately
year
Spencer
one
Con-
provides
agreement
tlement
which
rea
complaint
tractor amended its
to add a claim
sonable
fees to the
alleging that Aurora had breached a settle-
that,
any
enforcement action. We hold
by
parties
ment
executed
where
claim exists for
violation of a
lawsuit,
connection with a
which
re-
obligation,
contractual
in whose
involving
a dispute
Emporia
solved
favor the decision
or verdict
(the
Project
Storm Sewer
Street
rendered is the
agreement).
of
We
reverse the
According
complaint,
to the
Au-
amended
appeals’
court of
decision
remand to the
provision
rora
of
breached a
the settlement
court of
directions
remand
agreement
prohibited
which
Aurora from
this matter to the trial court for a determina
“treating Spencer
any
Contractor or
bid sub-
tion of the
fees to
reasonable
by
differently
any
mitted
[than]
other con-
Spencer
prevail
Contractor is entitled as the
by
retaliating
tractor”
Con-
ing party.
bidding
tractor
connection with the
performance
Parkway
of the Alameda
Pro-
I.
ject construction contract.1 Aurora filed a
August
Spencer Contractor en-
alleging
counterclaim
of
the settle-
agreement
tered into an
with Aurora for
agreement by Spencer
Contractor.
underground sanitary
construction of an
sew-
line,
part
Parkway
proceeded
er
as
to trial
of the Alameda
The case
October
(the
contract).
trial,
Project
jury
During
Following
construction
1991.2
returned
construction, Spencer
finding
special
the course of
Contrac-
verdict
that Aurora had
of unexpected
tor encountered a number
both the
contract and
de- breached
construction
lays resulting
agreement.3
jury
from site conditions.
the settlement
addi-
change
appropriate
granting
1. The settlement
remained in effect at
orders
additional
complained
by Spenc-
compensation materially differing
the time of the conduct
of
time and
conditions,
failing
good
er
site
to exercise
Contractor.
performance
faith in
of its duties
under the
contract, or both?
trial,
2. At the
of
commencement
both
defendant,
Aurora,
City
2. Did
of
stipulated
of
award
fees would
Agreement?
breach the Settlement
post-trial
jury
be calculated as a
matter after the
plaintiff,
3. Did the
Dennis I.
Con-
rendered
the court
its verdict and
entered final
tractor,
Inc. incur
as a result of the
judgment.
defendant,
City Aurora's
breach of the
Parkway
contract for the Alameda
construc-
Special
given
3. The
Verdict
the court to the
project?
tion
questions:
contained five
plaintiff,
Dennis I.
Con-
Did the
defendant,
tractor,
Aurora,
City
as a result
1.Did
Inc. incur
defendant,
City
Parkway
Aurora's breach of the
breach the contract for
Alameda
by failing
Agreement?
project
Settlement
construction
either
to issue
tionally
and must have achieved some of the bene-
concluded
$57,000
sought
actual
as a
fits that
lawsuit.”
had incurred
he
Over-
Development
Slopes
result of Aurora’s breach of the construction
land
Co. Marston
Development
contract. The
found that Aurora had
(Colo.App.1989).
breached the settlement
but did
*3
any damages
Spencer
not award
to
Contrac-
Here,
arguing
Aurora succeeded in
that
agreement.
tor on
any
agreement
breach of the settlement
Spencer.
did not
result
to
As
requests
Both
then submitted
for
result,
goal
avoiding
it achieved its
of
attorney
fee-shifting provi-
on a
fees based
payment
Spencer.
of
to
Con
agreement entitling
sion in the settlement
trary
position
by Spencer,
to the
taken
“prevailing party” in
enforcement action
previously recognized
court
that
such
attorney
to recover all costs and reasonable
by
sup
result
a defendant is sufficient to
County
Subsequently,
Arapahoe
port a trial court’s conclusion that
de
District Court ruled that Aurora was the
pur
fendant was the
for
“prevailing party” on the claim for the
poses
awarding attorney
of
fees. Oden
agreement
breach of the settlement
y
Weld,
baugh v.
$30,-
of
attorney
Count
awarded
fees
the amount of
(Colo.App.1990).
000 to Aurora.4
Contractor,
Spencer
slip op. at 2-3.
Spencer
appealed
Contractor
the trial
appeals.
court’s
court
order to the
II.
appeals
part,
court of
affirmed in
reversed in
Spencer Contractor
that it
maintains
part, and remanded the case to the trial
succeeded on the merits of its
for
claim
appeals
court. The court of
affirmed the
breach of both the construction contract and
ruling
trial court’s
that
Aurora was the
agreement
the settlement
and should be
vailing party on
the settlement
purposes
deemed the
for
2-3,
slip op. at
but reversed and remanded
awarding attorney fees.5
grounds
findings
on the
that the trial court’s
appellate
were insufficient for the
court to
question
prevailing
of who is a
that
determine
the fees awarded were actual-
awarding attorney
for
fees
ly incurred and were reasonable. The court
pursuant
to a settlement
which
appeals
reasoned as follows:
provides
attorney
prevailing
to
fees
In order to
party,
litigation regarding
receive the benefit of a con-
a breach of a
provision
tract
which calls for an award of
construction contract and a breach of a set
attorney
contract,
prevailing party,
fees to the
appropriate
tlement
and the
stan
applicant
upon
making
must “have succeeded
presents
dard
this determination
significant
presented by
litigation
issue
impression
an issue of first
for this court.6
appeals
5. State the total amount of actual dam-
Whether the court of
erred in con-
ages,
any,
by
plaintiff,
if
incurred
cluding
respondent
petitioner
Dennis I.
that
and not
Contractor, Inc.,
and caused
“prevailing party”
entitled to a contractual
defendant,
City
conduct of the
of Aurora in
attorney
award of
fees when a
found that
breaching
Parkway
the Alameda
contract,
construction
respondent had breached its
but
contract,
Agreement,
the Settlement
or both.
petitioner
awarded no
to
for that
objected
Special
to the
breach.
Verdict, claiming
erroneously required
that it
appeals
Whether the court of
erred in con-
speculate
separate
about the
effects of
cluding
respondent
“prevailing par-
that
was a
each of Aurora's breaches while
Con-
ty”
entitled to a contractual award of
case,
evidence,
theory
tractor’s
and the
juty
respondent
fees when a
found that
had
essentially
showed that
the same conduct consti-
breached its
but awarded no dam-
tuted a breach of both contracts.
ages
petitioner
for that breach.
interrelated,
Because these two issues are
we
$32,-
sought
to recover
together.
now consider them
363.50 in
fees from Aurora for breach of
agreement.
the settlement
party prevailed
6. The determination of which
is
granted
following
5. We
certiorari
consider the
committed to the discretion of the trial court and
subject
issues:
to an abuse of discretion standard of
claim,7
Development
ing party
Relying on
Co. v.
on the breach of contract
Overland
Slopes Development
despite
Marston
the fact that no actual
were
appeals
(Colo.App.1989),
the court of
appeals disagreed.
awarded. The court of
that, pursuant
fee-shifting
to a
determined
Relying on the
standard enunciated Hens
provision in a settlement
which
Eckerhart,
ley v.
461 U.S.
103 S.Ct.
provides
for reasonable
to the
fees
(1983),
331
Pools, Inc.,
263,
461,
120 Idaho
815 P.2d
465 no more than nominal
MFD Part-
denied, (Idaho
reh’g
App.1991)
509,
(App.1991),
Murphy, Haw.App.
ners v.
9
850 P.2d
(evaluating
following criteria in
713,
(1992);
determin-
Three-Seventy
715-16
see also
(1)
ing
prevailing party:
the final
who is a
Leasing Corp. Ampex Corp.,
v.
for
The claims
relief.
agreement and the breach
you
of the settlement
and on which
have
Spencer has sued
the construction contract since the same
Alame-
are: breach of the
been instructed
by
constituted a breach of
conduct
Aurora
and
Parkway construction contract
da
agreements.15 Spencer
ar-
both
Contractor
Agreement.
breach of Settlement
gued
court that
to the trial
than
you
Spencer
If
for
on more
one
find
Spencer’s
[tjhroughout
this case
taken
relief, you may
damages
it
award
claim
damages it
position
incurred
only
damages or losses.
once for the same
by
...
were caused
actions which
consti-
NO. 41
JURY INSTRUCTION
of both the settlement
tuted a breach
follow-
You are instructed to answer the
agreement and a breach of the Alameda
ing questions which will be on a form
contract,
Parkway
forcing
construction
Special Verdict:
jury
separate
separate ques-
answer
—to
defendant,
City Auro-
1. Did the
damages Spencer
tions about the
incurred
ra,
contract for the Alameda
breach the
[FJorcing
jury
to attribute dam-
...[.]
by
Parkway
project either
construction
separate
may
ages to
breaches
confuse the
failing
change
granting ap-
to issue
orders
jurors
jury, may
feeling
result in the
compensa-
propriate additional time and
they
apportion
damages
need to
conditions,
materially differing
site
tion
Spencer
by
believes were caused
breaches
by failing
good
to exercise
faith
agreements
of both
and cannot be distin-
performance of its duties under the con-
guished,
may severely prejudice
tract, or both?
forgiven parties
Spencer’s right to be the
defendant,
City
2. Did the
of Auro-
on its claim for breach of the settle-
[sic]
ra,
Agreement?
breach the Settlement
agreement.
plaintiff,
Spencer
Did the
Dennis I.
3.
Contractor,
damages
Inc. incur
as a result
object
special
...
to the
verdict
[W]e
defendant,
City
of the
of Aurora’s
object[
form for the same reasons that we
]
breach of the contract for the Alameda
to Instruction 41....
Parkway
project?
construction
was instructed under Instruction
Spencer
plaintiff,
4. Did the
Dennis I.
damages only
No. 40 that
could award
once
Contractor,
Inc. incur
as a result
for the same losses. The
adhered to
defendant,
City of Aurora’s
prohibited
this instruction and
therefore
Agreement?
breach of the Settlement
awarding damages
No. 41 from
Instruction
5. State the total amount of actual
on both contracts since Aurora’s conduct in
damages,
any,
plaintiff,
if
incurred
breaching
agreement gave
the settlement
Contractor, Inc.,
Dennis I.
rise to the breach of the construction con-
defendant,
caused
the conduct of the
Therefore,
special
tract.16
verdict for
City
breaching
of Aurora in
the Alame-
damages in the breach of the construction
Parkway
da
construction
the Set-
implicitly
contract
includes
attribut-
Agreement,
tlement
or both.
agree-
to the breach of the settlement
able
ment.
objected
special
to the
Jury
verdict form and
Instruction No.
III.
claiming that both were inconsistent with
theory.
appeals’
Contractor’s
reverse the court of
decision
We
Spencer Contractor maintained that
and remand to the court of
occurred,
argument
Contractor’s main
is that
technical harmless breach
then it is
disparate
received
treatment
prevailing party. Contrary
to Aurora's
*9
Parkway Project
contention,
on the Alameda
constitut-
jury did
not rule that the breach
agree-
ed a violation Aurora of the settlement
of the settlement
constituted a harm-
underlying
ment as well as a
of the
violation
Rather,
jury
less technical breach.
found
agreement.
construction
that Aurora breached the settlement
damages given
and did not award
the instruc-
that,
argues
parly
16. Aurora
when a
seeks mone-
provided.
tions
tary damages
only
and it is determined that
a
this matter to the trial
I
directions to remand
reasonable
court for a determination
A
attorney
is
fees to which
Contractor
majority
adopts
We further
The
a rule that
entitled as the
defines
prevailing party
upon
finding
based
of lia
trial court to consider whether
direct
bility
explains
alone and
that
this view re
attorney
bringing
should
awarded for
be
majority
maj.
approach,
op.
flects the
at
appeal.17
relying
Murphy,
on MFD Partners v.
9 Haw.
(1992)
App.
also relied
1992).
recovery
of attor
In
the court was called
interpretation of the Texas
Brown
Though the court ex
ney’s
party prevailed
fees statute.3
a
when
to decide whether
finding
damages
of zero
does
plained that a
full amount
dam
awarded less than the
attorney
preclude
award of
not
ages requested.
explained party
court
a
is unsettled. A different
Texas rule
prevails when the court renders an affirma
interpreting the same statute has
district
judgment, “even if the amount is less
tive
satisfy
requirements
party
must
two
held
originally sought.”
(empha
at 155.
than
first,
attorney
fees:
to obtain an award
supplied).
sis
While the court discussed the
prevail on the cause of action for
must
culpability
deciding
importance of
in
who
recoverable,
attorney
and sec
fees are
liability
prevails, it did not state
is the
ond,
damages.
must
recover
prevails.5
sole determinant of who
Investments, Ltd.,
Rodgers v. RAB
816
Finally,
Three-Seventy Leasing Corp.
both
1991);
(Tex.App.
see also
S.W.2d 543
— Dallas
(5th Cir.1976)
Co.,
Ampex Corp.,
F.2d
v.
Layne
Cook v.
Texas
S.W.2d
1973)
Co.,
(where
and Buza v. Columbia Lumber
(Tex.Civ.App.
no recov
— Waco
1964)
(Alaska
ery
plaintiff
attorney
prevails
no
was awarded
deal with who
authorized). Thus,
were
Atlantic
the award of costs under the rules of civil
Richfield
interpreting
in
provides little assistance
procedure.6 I am not convinced however
Texas statute.4
prevailing party
for costs under the
procedure provide adequate
rules of civil
majority also relies on I.A
v.
Schafer
guidance
prevailing party
in
decide the
Co.,
Railway
266 N.C.
Southern
ordinarily
fee cases. Costs do not
(1966).
trespass
S.E.2d 887
case the
E.g.,
Marriage
include
In re
damages
court
that a verdict of nominal
held
Wright,
(Colo.App.1992).
337
exists,
adopt
I would
a rule that
always
recognized.8
be
fee
fees will
language of our cost
Additionally,
plain
requires
plaintiff
attorney'fees
who seeks
requires plain-
supports a rule that
statutes
prevailing party to
as a
establish both a
receiving an
before
tiffs to recover
and an award of actual
breach
13-16-104,
attorney fees.
award of
Section
(1987
Initially,
recognize contracting parties
Repl.Vol.) provides that
6A C.R.S.
any
dam-
to
plaintiff
when a
“recovers
debt or
remain free
define
See
action,
plaintiff
ages in such
then the
[civil]
Magnetic Copy
Specialists,
Serv. v. Seismic
judgment
shall have
to recover
demandant
Inc.,
1161,
(Colo.App.1990)
805 P.2d
against
to
the defendant his costs
be taxed.”
(“an unambiguous agreement must be en-
Conversely,
(emphasis supplied).
section 13-
terms”).
according
express
forced
to its
Be-
provides that when “a verdict
16-105
provided
cause no definition is
this case
plaintiff],
passed
then the defen-
[the
policies promoted by
shifting provi-
fee
judgment to recover his
dant shall have
costs
significant.
sions are
Both Aurora and
plaintiff....”9
agree
shifting
fee
Basing prevailing party status on breach
provisions encourage compliance with con-
recovery
support
also finds
discourage
tracts and
unfounded lawsuits.
Solari,
Malagon
case law. See
Brokers, Ltd.,
See also Ferrell v. Glenwood
1990) (“It
352,
(Fla.App.
is well
So.2d
(Colo.1993) (fee
936,
shifting
848 P.2d
pre
plaintiff
that a
is considered the
settled
agreements
“discourage
serve to
non-merito-
vailing party if he recovers less than he sued
disputes
encourage
rious contract
and to
set-
”
for,
long
something ap
so
as he recovered
tlement”);
Freedman,
Hartman v.
197 Colo.
analysis.);
plying quasi-civil rights
see also
(1979) (statuto-
Ladd,
(Fla.App.
Militana v.
rationale in of Aurora B inability pre plaintiffs fees. A to not, however, damage on the issue does vail majority regarding As no clear view automatically into a definition of a convert defendant court, (citing §§ majority correctly points 13- out that there can the discretion of the trial 8. The claim, -109, (1987 any liability Repl.Vol.)). to 6A C.R.S. be but one on 16-108 maj. op. prevailing at but should automatically prevailing majority correctly for at- 10.The addresses one of the translate to underlying shifting agree- torney purposes. argument policies fee While an exists contractual fee could, ments, equity, encourage compliance with a that the trial court reduce the plain- maj. op. recovery fees awarded when the at 333 n. Because amount success, only any I believe re- amount over one dollar would entitle a tiff achieves limited vailing plaintiff requir- quiring clearly I believe trial courts to consider fees when compliance. only litigation ing recovery adequately encourages party prevailed prolongs no majority's Making I remain concerned with the failure further burdens the trial court. policy discouraging requirement plaintiff seeking that a consider the coexistent threshold damages prevail only Under when awarded actual dam- nonmeritorious actions. breach, contracting party ages provides equitable view a could use a more resolution. insignificant, bring an action and however Woolley I do not Co. v. Bear Creek ensure the award of 9. See also W.H. & Manors, (when (Colo.App.1986) contracting parties believe intend for a coerce, parties pre- injury or as a that causes no to be used to several claims are asserted and both litigation. solely in basis for needless vail the award or allocation of costs is out, party. majority points majority’s As the fers the same frailties as the defi- *12 unjust a would be to award fees to nition of The do Maj. op. defendant found liable for breach. not define “enforcement.” law Black’s dictio- 333; nary “putting at v. see also Nouri Wester & defines enforcement as some- effect; (Colo.App.1992). thing carry- P.2d 848 such as law into ... the ing a out of mandate or command.” Black’s When claims a defendant are dis- (6th 1990). Here, Dictionary Law ed. missed, however, the defendant achieves two jury respect issued no command with to respect significant results —one with to liabil- agreement. Spencer the settlement Contrac- Thus, ity respect and one with agree- tor did seek enforcement of the can defendant show he was through declaratory injunctive ment or relief. claim, against an unfounded forced to defend Instead, Spencer sought to en- promoting deterring policy baseless agreement by seeking damages force the Similarly, plaintiff suits. who seeks and breach, its but I received none. am not damages significant receives achieves two re- Spencer convinced that Contractor enforced respect sults —one with and one agreement solely the settlement because the respect damages.11 plaintiff A who jury found the had been breach- alone, proves liability absent an award of ed. damages, prevailed actual has not with re- and, believe, spect to I disagree majority’s the desired outcome I also with the conclu- jury should not be a support sion that instructions purposes.12 fee I Spencer prevailed. would therefore affirm the decision that appeals ruling Maj. court of that op. jury Contrac- at 333-334. The form of in- prevailing party, given tor was not the and consis- structions at trial is within the discre- majority, tent with the reverse the court of tion of trial court. Armentrout v. FMC (Colo.1992). appeals’ ruling prevailing Corp., that Aurora was a To Here, party. party prevailed. no decide requires whether instructional error
reversal, jury instructions must be con- together they sidered to determine whether II adequately jury informed ap- of the law plicable to the case. Contrac- plain language of the settlement argues jury tor that verdict forms parties’ stipulation regarding jury cluded the from damages on principles13 contract and dis- both contracts. As the court of cor- puted jury compel verdict do not forms out, rectly pointed jury verdict form “did different result. contends, suggest not as majority contends that apportion Con- should resulting “enforcing” breach; instead, tractor the settle- from each the verdict form jury expressly merely because the required to determine agree- found that Aurora had breached the Op. whether were incurred.” Maj. Further, op. argument ment. at 332. This at stating suf- 338. the instruction every This rule does not address combination decision not to award fees in this case. plaintiff may bring of claims a when an action Maj. op. at 332 n. 12. While the infers prayer damages. Every involves more than regarding result means success liabili- successful today, combination need not be decided as ty, Roa does not define a successful result. A requested only damages. Although being successful result could be defined as Spencer attempts complaint to recast its as one successfully defending awarded or only declaratory injunctive that in effect seeks damage claim. relief, plead these matters were never and never only suggest decided the trial court. that a agree majority’s 13.I with the conclusion that requests damages who alone does not principals support basic contract when none are received. the denial of Maj. op. fees to Aurora. at 332-333. Miller, appeals holding 12. The court of in Roa v. (Colo.App.1989), is consistent with damages only “you may award once for the Colorado, not make the or losses” does The PEOPLE State
same Plaintiff-Appellee, together when read erroneous.14 instructions dispute jury instruc- Much of the over the stipulation pri- parties’ tions results from Jimmy GREEN, Defendant-Appellant. C. prevails trial that the or to agreement would be the No. 92CA1575. fees. Each now entitled *13 Appeals, Court of Colorado prevailed; Spencer asserts that Div. I. the verdict that Aurora breached becaus^of the agreement, and Aurora because it avoid- May 1994. paying damages. following language ed The Rehearing As Modified on Denial stipulation implies that for June 1994. an award of Denied Nov. 1994. Certiorari appropriate: would be Spencer’s 2. Second Claim Relief
against Aurora in this action is for breach According- Agreement.
of the Settlement
ly, Spencer requested has an award of
attorneys’ in addition to dam- awarded, ages if it it is Relief, (em-
party on its Second Claim
phasis supplied). agree with the court of that the complain cannot now settle- as a was used standard prevailing party. Slip op. at
decide the 3.
Accordingly, I would remand this case to appropriate
district court to award costs as party’s attor-
and to dismiss both motions for
ney fees. Parkway Jury provided construc- as follows: are: breach of the Alameda instruction no. 40 of a Settlement tion contract Contractor, plaintiff, Dennis I. you Agreement. on more If find for Inc., of the same has sued for some relief, you may award it than one claim for on two different claims for relief. and losses damages only losses, once for the same claims for relief on which (emphasis supplied). you and on which have been instructed sued
