119 Cal. 180 | Cal. | 1897
This is an appeal from the judgment rendered against defendants in an action for the foreclosure of a materialman's lien. The facts were stipulated, and upon them the court rendererd the judgment complained of. The stipulation of facts is under agreement of the parties made a part of the judgment-roll, and may here he considered as the findings upon which the judgment was based. (Muller v. Rowell, 110 Cal. 318.)
Defendant Metcalf had entered into a contract with defendant Burrell whereby he agreed to erect a frame cottage for the latter. The price was the sum of seven hundred and sixty dollars, payable, under the terms of the contract, upon the completion of the building by Metcalf and its acceptance by the owner. Metcalf proceeded with the work until the sixteenth day of April, 1895, when he abandoned it. At the time of the abandonment his contract was half completed. Plaintiffs, materialmen, had furnished material to Metcalf to the value of two hundred and forty-three dollars and sixty cents, which material was actually used in the construction of the building. Upon April 20th Burrell served notice upon Metcalf declaring his willingness and ability to per
The court adjudged that, as half of the work under the Met-calf contract had been done, there was, measured by the contract price, the sum of three hundred and eighty dollars in the hands of Burrell available for the payment of liens, and decreed a lien in favor of plaintiffs for the amount sued for, with attorney’s fees and costs.
The contract price being less than one thousand dollars, the provisions of section 1184 of the Code of Civil Procedure relative to the mode and time of payment, and the withholding of a percentage of the contract price, are not applicable. It was permissible for the parties to contract for the payment o£ the whole amount to the contractor before the commencement of the work, or, as was done in this case, to contract that payment should not be made until the whole building was completed. (Kerckhoff-Cuzner etc. Co. v. Cummings, 86 Cal. 22.) The cases upon which respondent relies, and which he contends oppose this construction, are those of Dunlop v. Kennedy, 102 Cal. 443, and Golden Gate Lumber Co. v. Sahrbacher, 105 Cal. 114, but these cases both had to do with contracts where the price exceeded one thousand dollars, and they are therefore inapplicable.
The contract being valid, it follows and is admitted that plaintiff’s lien could not he for an amount greater than the sum in defendants’ hands due and unpaid to the contractor under the
The judgment appealed from is reversed and the cause remanded.
McFarland, J., and Temple, J., concurred.
Hearing in Bank denied.