186 A.D. 334 | N.Y. App. Div. | 1919
Lead Opinion
On the 2d of June, 1915, the appellant entered into a contract with the Mount Sinai Hospital • for the excavation of the premises described in the complaint in the borough of Manhattan, New York, and the erection thereon of certain buildings, and thereafter the appellant sublet the excavation work to the defendant the F. H. Chapman Contracting Company. The respondent company Dittmar Powder Works, Inc., furnished explosives to the subcontractor for use and which were used in making the excavation,, and the other respondents performed labor for the subcontractor in making the excavation and they all duly filed liens therefor. The uncontroverted evidence shows that at the time these liens were filed, no amount was due or owing by the general contractor to the subcontractor, but the subcontractor had at those times performed work and labor and furnished material amounting in value to more than the amount of the liens filed, for which it had not been paid but no part thereof became due and payable owing to the usual provision of the contract by which only eighty-five per cent of the value of the work performed was due and payable at the contract rates, as the work progressed, and by which the remaining fifteen per cent was not to become due and payable until forty days after the entire completion of the work by the subcontractor. The lien
The appellant’s contention is that in these circumstances there was no fund to which the liens of the respondents ever attached, and the respondents contend that the amounts of their respective hens had been earned by the subcontractor at the time the hens were filed, and that upon the work being performed by the appellant the amounts earned at the time the hens were filed became due and payable from the owner to the general contractor, and that their hens attached thereto.
It follows that the findings of fact and conclusions of law inconsistent with these views should be reversed and appropriate findings and legal conclusions in accordance herewith made and the judgment in so far as appealed from reversed, with costs, and the liens of the respondents dismissed, with costs'.
Clarke, P. J. and Smith, J., concurred; Dowling and Merrell, JJ., dissented.
Dissenting Opinion
I believe that the respondents have brought themselves within the protection of the statute. The fund upon which they seek to impress their lien is “ the sum earned and unpaid on the contract at the time of filing the notice of lien.” (Lien Law [Consol. Laws, chap. 33; Laws of 1909, chap. 38], § 4, as amd. by Laws of 1916, chap. 507.) While it may be difficult to find any equitable basis on which the contractor or subcontractor should be subjected to a greater risk or liability than an owner, yet the fact remains that the Legislature has chosen to differentiate between them in what seems to me clear and unmistakable language. Section 2 of the Lien Law (as amd. by Laws of 1916, chap. 507) defines an owner and as well a contractor and a subcontractor, and the terms are not interchangeable. The Legislature must be credited with as full a knowledge of their difference in meaning as the courts possess, and must be deemed to have distinguished them accurately and knowingly.
I favor the affirmance of the judgment appealed from, with costs.
Mebbell, J., concurred.
Judgment in so far as appealed from reversed, with costs, and liens of the respondents dismissed, with costs. Order to be settled on notice.