Lead Opinion
In May, 1919, the appellee, Paul W. Torrans, procured a mineral lease on a tract of land from E. B. Colgin and wife for a term of years, the lessors reserv-.
Among other defenses interposed by the appellant was a plea in abatement objecting to maintenance of the suit because of the nonjoinder of Hussey & Wheelan, who, it was alleged, were jointly interested with Torrans in the contract with the .appellant. The court overruled that plea and submitted the merits of the case upon special issues, in response to which the jury found substantially as follows: That oil in paying quantities was found at the depth alleged by Tor-rans in his pleadings, that the well at that stage would have produced 25 barrels per day for eight years, and that the oil was worth $2 per barrel. The jury also found that the appellant did not act in good faith in refusing to install a pump at the stage demanded by Torrans. Upon those findings the court entered a judgment in favor of Torrans for the net sum of $10,000 as his portion of the damages resulting from the conduct complained of.
The disposition made of the case renders it unnecessary to'discuss the remaining assignments of error.
For the reasons stated, the judgment will be reversed, and the cause remanded for a new trial.
d5=»For other cases see same topic and KEY-NUMBER in all Key-Numbered Digests and Indexes
Rehearing
The finding relative to the probable future production of the well was founded upon the testimony of experienced oil men, who gave their opinions based upon their knowledge of that and the surrounding territory and the indications presented by that well. There was no other practicable method for showing the capacity of the well. While there is an element of speculation in their estimates, they are not for that reason to be wholly disregarded. The jury took what we regard as a safe estimate in reaching their conclusion.
Appellant objected to the introduction of the contract between Torrans and Hussey & Wheelan and the Dempsey Oil Company, on the ground that it varied the contract set out in the pleadings of the plaintiff. In the plaintiff’s petition he described the very contract which was offered in evidence The objection was untenable.
The judgment is affirmed.
Lead Opinion
Among other defenses interposed by the appellant was a plea in abatement objecting to maintenance of the suit because of the nonjoinder of Hussey Wheelan, who, it was alleged, were jointly interested with Torrans in the contract with the appellant. The court overruled that plea and submitted the merits of the case upon special issues, in response to which the jury found substantially as follows: That oil in paying quantities was found at the depth alleged by Torrans in his pleadings, that the well at that stage would have produced 25 barrels per day for eight years, and that the oil was worth $2 per barrel. The jury also found that the appellant did not act in good faith in refusing to install a pump at the stage demanded by Torrans. Upon those findings the court entered a judgment in favor of Torrans for the net sum of $10,000 as his portion of the damages resulting from the conduct complained of.
The refusal of the court to sustain the plea in abatement based upon the nonjoinder of Hussey Wheelan is assigned as error, and we are of the opinion that the assignment should be sustained. Both the pleadings of Torrans and the evidence showed that Hussey Wheelan were jointly interested with him in the contract with the appellant. If Torrans had a cause of action for damages for the breach of that contract, or for an injury to the common property, Hussey Wheelan also had one for an equal sum. Their interest in the contract and in the property was in every respect equal to that of Torrans. That parties jointly interested in a written contract must join in a suit for damages resulting from a breach by the obligor is well settled by the decisions in this state. May v. Slade,
The ruling of the court is defended upon the ground that in this case the damages were apportioned so that Torrans recovered only those which he alone sustained. That fact might be a sufficient reason for sustaining the judgment when the objection to that nonjoinder is not made till after issue had been joined upon the merits of the controversy, but it does not justify overruling a plea in abatement filed at the proper time and in due order of pleading. A defendant has a right to be protected against a multiplicity of suits growing out of the same contract, and his plea in abatement is the legal method of asserting that right. No reason is shown in this record why Hussey Wheelan were not made either parties plaintiff or defendant.
The disposition made of the case renders it unnecessary to discuss the remaining assignments of error.
For the reasons stated, the judgment will be reversed, and the cause remanded for a new trial. *Page 857
Appellant assails the findings of the jury upon the issues of fact. It is insisted that the evidence did not support the finding that Dempsey acted in bad faith in drilling the well deeper over the objection of Torrans, and that the testimony that the well would produce 25 barrels per day for eight years is too speculative to form the basis of a judgment for damages. If the testimony offered by the appellee be true, it tended strongly to show that Dempsey did act in bad faith in refusing to stop drilling at the point suggested by Torrans. The fact that there was testimony tending to show the contrary created only a conflict, which the jury alone could settle.
The finding relative to the probable future production of the well was founded upon the testimony of experienced oil men, who gave their opinions based upon their knowledge of that and the surrounding territory and the indications presented by that well. There was no other practicable method for showing the capacity of the well. While there is an element of speculation in their estimates, they are not for that reason to be wholly disregarded. The jury took what we regard as a safe estimate in reaching their conclusion.
Appellant also complains that the judgment is excessive. A mathematical calculation based upon the findings of the jury will support the judgment rendered by the court. There was no reversible error in canceling the lease made by Colgin and wife to Torrans, because the undisputed facts show that that lease had practically expired by its own terms.
Appellant objected to the introduction of the contract between Torrans and Hussey Wheelan and the Dempsey Oil Company, on the ground that it varied the contract set out in the pleadings of the plaintiff. In the plaintiff's petition he described the very contract which was offered in evidence. The objection was untenable.
The judgment is affirmed.