DeMicco Bros. v. Consolidated Edison Co. of New York, Inc.DeMicco Bros. v. Consolidated Edison Co. of New York, Inc.
Order, Supreme Court, New York County (Karla Moskowitz, J.), entered March 31, 2003, granting plaintiff’s motion to reargue the order of the same court and Justice entered September 11, 2002, which, to the extent appealed from, and upon reargument, adhered to its prior grant of defendants’ motions to dismiss the complaint pursuant to CELR 3211 (a) (7) and prior denial of plaintiff’s cross motion to amend the complaint to add the cause of action of prima facie tort, unanimously reversed, on the law, without costs, the motions denied and the cross motion granted to add the cause of action of prima facie tort. Appeal from order, same court and Justice, entered September 11, 2002, unanimously dismissed, without costs, as superseded by the appeal from the order of March 31, 2003.
It is well settled that a court’s inquiry is narrowly defined on a motion to dismiss under CELR 3211. The court must “accept the facts alleged as true . . . and determine simply whether the facts alleged fit within any cognizable legal theory” (Morone v Morone,
Accepting the allegations of the complaint as true and construing the inferences that may be drawn therefrom in plaintiffs favor, we find that the instant complaint sufficiently alleges a claim of prima facie tort, namely: (1) the intentional infliction of harm, (2) resulting in special damages, (3) without excuse or justification, and (4) by an act or series of acts that would otherwise be lawful (see Burns Jackson Miller Summit & Spitzer v Lindner,
In its complaint, plaintiff alleged that certain overhead electric, cable and telecommunication wires owned and operated by defendants were interfering with its public works contract with the City of New York for the milling and grinding of certain public streets. In light of defendants’ affirmative legal obligation to remove or alter their wires for public works construction (Administrative Code of City of NY § 24-521; see City of New York v Consolidated Edison Co.,
Likewise, plaintiffs submission of the letters it sent to each of the defendants delineating the damages which it had allegedly incurred by defendants’ failure to remove or alter the subject overhead wires sufficiently identified the actual losses necessary to satisfy the element of special damages of prima facie tort.
We have considered defendants’ remaining contentions and find them unavailing. Concur—Nardelli, J.P., Mazzarelli, Saxe and Lerner, JJ.