104 F. Supp. 549 | Ct. Cl. | 1952
Lead Opinion
delivered the opinion of the court:
A motion to dismiss plaintiff’s petition in this case has been filed by the intervenor, the Board of Levee Commissioners of the Tensas Basin Levee District, State of Louisiana, hereinafter referred to as the Levee Board.
' According'to the petition, on April 8,1949, plaintiff entered into a contract with the United States in which it undertook to perform work in connection with a channel improvement project in the Parishes of Ouachita and Morehouse .in the State of Louisiana; The contract called for the excavation by plaintiff of a drainage, canal. Plaintiff received notice to proceed on the contract on June 11,1949. On November 11, 1949, while only about seven days from the completion of the contract plaintiff was forcibly prevented from further .excavation, by one George Franklin, • Jr., who appeared on the scene armed with a revolver- and. a double-barreled shotgun- and informed plaintiff’s employees that he was the "owner of the land on which they were excavating the drainage canal and.that they had better stop operations on his •property. The petition does not disclose what portion of the -contract work, if any, had been completed on Franklin’s land prior to the forcible work stoppage on November 11, 1949, or whether, plaintiff at any time prior to that date had actually made entry onto any land claimed by Franklin. Apparently the canal crossed a number of tracts of land owned by others.
Plaintiff was thus halted in the performance of its work until a court order was obtained by the Levee Board enjoining Franklin from interfering with the progress of the work. Immediately after the forcible work stoppage occurred plaintiff requested that defendant relieve it of its obligation to perform the remaining work, but defendant’s contracting officer insisted upon the immediate progress and completion of the contract. As a result of the forcible work stoppage plaintiff was unable to perform any work under the contract for a period of 39y2 days between November 11, 1949, and December 27, 1949, and it is averred that, plaintiff thereby incurred damages in excess of $36,000 from labor, overhead, equipment rental, and other expenses. The time ■for completion was ultimately extended to February 17,1950, and the work finally completed and accepted as of December 31, 1949.
. Plaintiff alleges that the defendant has breached its duty under paragraph SC-13 of the specifications of the contract which states that “the lands, easements, and rights-of-way necessary for all the work under this contract will be provided without cost to the Contractor”; that plaintiff is entitled to an equitable adjustment of the contract price as provided in Article 4 of the contract by reason of changed conditions within the meaning of that article; and that defendant breached its duty to disclose- to plaintiff that Franklin for a long time prior.to the entering of the contract had vigorously disputed the right of the Levee Board to take his land, had contended the project was unnecessary and the procedure improper, and had maintained that he, Franklin,- would carry the matter to the state courts, if the Levee Board persisted;
In connection -with the last allegation plaintiff alleges further that the Levee. Board was the agent of the defendant United States in the procurement of the rights-of-way for the drainage project (which the Levee Board conceded .on oral argument of this motion) ; that the knowledge by the
It appears that after Franklin’s armed appearance upon the scene of the work, injunction proceedings were instituted against him by the Levee Board in the Louisiana State courts which ultimately terminated in a decision by the Supreme Court of Louisiana in favor of the Levee Board.
The Levee Board contends here on its motion to dismiss that since the appropriation of Franklin’s land had been valid and it had had the right all along to make excavations on Franklin’s land there was no failure on the part of the defendant to obtain and to provide the lands, easements, and rights-of-way necessary for the work under the contract. The Levee Board asserts further that plaintiff’s contract contains no warranty, express or implied, against damage to plaintiff by the illegal acts of third persons who might interfere with plaintiff’s progress. The Levee Board appears to view Franklin as a sort of armed trespasser for whose actions neither defendant nor the Levee Board can be held accountable to plaintiff. To so characterize Franklin in the circumstances of this case is an oversimplification. Franklin was no mere stranger to the events herein. He was the actual owner of the land through which the canal was being cut, acting through a claim of right, and it was known to the Levee Board at the time defendant contracted with plaintiff that Franklin objected to the work for which the contract called, and intended vigorously to oppose it on the grounds that the appropriation by the Levee Board of the right-of-way across his land was unlawful.
In reaching this conclusion we rely in part upon Weissbaum v. United States, 72 C. Cls. 423, where the United States, lessee of certain premises, upon abandonment of the use of the premises contracted with Weissbaum to deliver title and put Weissbaum in possession of certain improvements constructed thereon by the United States, for the purpose of wrecking and removing those improvements. The United States in that case, just as in the instant case, represented that Weissbaum would be given free access to the
* * * These facts establish that there was a direct misrepresentation by the defendant of the conditions under which the work was to be performed. * * * This suit is not an action sounding in tort. The representation that the improvements were accessible and that the contractor would have free ingress and egress was the very foundation of the whole undertaking. The plaintiff did not pay * * * for a lawsuit. * * *
*****
* * * In these circumstances it may not be said that the defendant is in nowise responsible to the plaintiff for his actual losses sustained by reason of the failure of the defendant to place him in possession of the improvements and to give him the right and uninterrupted privilege of removing the same.
* * # # *
* * * The position taken in this case by counsel for defendant that * * * whatever loss plaintiff sustained was due to the interference by a third person [the lessor], for which the United States was in nowise responsible, is overcome by the peculiar facts in this case and by the decision in favor of the Government in the district court in which the United States recovered a judgment * * * [against the lessor]. [Citing cases.]
Accordingly the intervenor’s motion to dismiss plaintiff’s petition will be denied and an opportunity afforded for full development of the facts and circumstances surrounding plaintiff’s claims. The case will be referred to a Commissioner of the court for such further proceedings as may be necessary. . ’ ' '
It is so ordered.
The Levee Board’s motion for leave to intervene stated that it. had a pecuniary interest in the action by virtue of an obligation contracted with the' united States to save and hold the United States harmless from any and all damages resulting from or occasioned by the construction of the .project in .question. ...
Board of Commissioners, etc. v. Franklin, No. 39,793 (La.), appeal dismissed, 342 U. S. 844 (per curiam), rehearing den., 342 U. S. 889. The appropriation appears to have been effected by notification to Franklin by registered mail that rights-of-way across his land were appropriated. It was this procedure, inter alia, that Franklin challenged unsuccessfully.
Cf. Fred R. Comb Co. v. United States, 103 C. Cls. 174, holding the united States liable for negligently involving plaintiff contractor in litigation concerning the site of tbe work. ’
Dissenting Opinion
dissenting:
I cannot agree with the opinion of the-majority. The Levee Board did furnish the right-of-way, as the. defendant agreed would be done. Neither the defendant nor the Levee Board kept plaintiff off of it. This was done by one Franklin, a stranger to the contract, who was under.the control of neither the defendant nor the Levee Board. It is true that Franklin denied the right of the Board to dig the canal
This was a course of action the defendant should not be expected to have foreseen, especially since the man of arms was a substantial and respected citizen in a civilized community. As soon as he did take such action, the defendant immediately appealed to the courts to stop him and diligently prosecuted the case until he was stopped.
I do not see how the defendant could be expected to have done more.
Plaintiff’s action, if any, is against Franklin, and not against the defendant.