Affirmed by published opinion. Judge LUTTIG wrote the opinion, in which Judge WILKINSON and Judge JOSEPH ANDERSON, Jr., joined.
OPINION
Appellees, the Secretary of the Army and an Army Contracting Officer, awarded a contrаct to a competitor of appellant Delta Chemical Corporation. After the General Accounting Office denied Delta’s bid protest, Delta sоught declaratory and injunctive relief in federal district court, pursuant to the Administrative Procedure Act, 5 U.S.C. §§ 702-705, arguing inter alia that the Army was required to cancel the Invitation for Bids where, as here, the invitation overstated the Army’s minimum needs. The district court refused to cancel the invitation. For the reasons that follow, we affirm.
I.
In August 1993, the Army Corps of Engineers, Bаltimore District (“Army”), issued an Invitation for Bids (“IFB,” “solicitation,” or “invitation”), soliciting bids on a contract to supply the Army with aluminum sulfate. Although Delta Chemical submitted the lowest bid, the Contracting Officer rejected its bid as “nonresponsive,” and awarded the contract to Kemira Water Treatment, Inc., the next lowest bidder. Delta filed a bid protest with the General Accounting Office (“GAO”). In reviewing the IFB specifications in connection with Delta’s protest, the Army discovered that- the IFB overstated its needs and it revised its specifications to reflect the actual, more permissive requirements. 1 The GAO denied Delta’s protest in March 1994. The GAO concluded that Delta’s bid was properly rejected as nonresponsive. It found that the inaccurate specification in the IFB could not have prejudiced Delta, because Delta’s nonresрonsiveness was unrelated to the overstatement, and hence its bid would have been denied regardless. J.A. at A43-47.
Delta then sought declaratory and injunc-tive relief in thе United States District Court for the District of Maryland, pursuant to the Administrative Procedure Act, 5 U.S.C. §§ 702-705. On April 28, 1994, the district court held (1) that the Army’s conclusion that Delta’s bid was nonresponsive wаs not arbitrary or capricious, and (2) that the Army was not required to cancel the IFB simply because it overstated the Army’s minimum needs. Delta challenges only the seсond of these rulings on appeal.
II.
A.
Appellant contends that “[w]hen a solicitation overstates the government’s actual minimum needs, the Contracting Officer has no discretion and must cancel the' solicitation.” Appellant’s Br. at 10. Section 14.404-1 of the Federal Acquisition Regulation governs the cancellation of invitations after opening. 48 C.F.R. § 14.404-1 (1993). This provision, which was not discussed by either party, governs the sole issue on appeal, that is, whether an agency must cancel an IFB that includеs an overstatement.
*382
Subsection (b) of § 14.404H defines a single circumstance that
requires
cancellation, namely, “[w]hen it is determined before award but after opening that thе requirements of 10.008 (relating to the availability and identification of specifications) have not been met.”
Id.
§ 14.404-l(b). Section 10.-008 ensures that IFB specifications are сlearly identified and equally accessible to potential bidders.
Cf. Alpha Q, Inc.,
B-248706,
Subsection (c) lists ten circumstances where, if a “compelling reason” exists, 48 C.F.R. § 14.404-l(a)(l), “[i]nvitations may be cancelled and all bids rejected bеfore award but after opening,” within the sound discretion of the agency head. Id. § 14.404-l(e) (emphasis added). 2 In this case, the only provision that possibly applies is subpart (c)(2) which permits cancellation when “[specifications have been revised.” Here, the Army decided not to cancel the invitation, presumably for the reasons discussed by the GAO, viz., the overstatement did not prejudice Delta. Nothing suggests that this determination was arbitrary or capricious. Therefore, contrary to appellant’s arguments, the question of cancellation where specifications have been changed is committed to the discretion of the contracting agency, and the Army has exercised that discretion soundly in this case.
B.
Both parties cite legal opinions of the Comptroller General of the United States as authority to suppоrt their respective positions. Opinions of the GAO, a political arm of the Congress,
see Bowsher v. Synar,
Appellant relies extensively on two GAO decisions,
Donco Indust., Inc.,
B-230159.2,
Appellees rely on
Diversified Energy Sys.; Essex Electro Eng’rs, Inc.,
B-245593.3,
The appropriate standard of review under the Administrative Procedure Act is whether the agency’s action was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A);
Aquino v. Stone,
CONCLUSION
The judgment of the district court is affirmed.
AFFIRMED.
Notes
. The IFB erroneously stated that the aluminum sulfate should include at least 0.3% water soluble alumina by weight, whеreas the specification should have permitted a basicity in the range of 0.0% and 0.4%.
. We recognize that subsections (b) and (c) refer to cancellations "before award but after opening.” 48 C.F.R. § 14.404-1. However, the presumptions against cancellation are even stronger after the contract is awarded, as in this case.
