Delric Constr. Co., Inc. v. New York City Sch. Constr. Auth.Delric Constr. Co., Inc. v. New York City Sch. Constr. Auth.
ROBERT J. MILLER, J.P. JOSEPH J. MALTESE JOSEPH A. ZAYAS WILLIAM G. FORD, JJ.
Welby, Brady & Greenblatt, LLP, White Plains, NY (Thomas S. Tripodianos, Michael I. Silverstein, and Geoffrey S. Pope of counsel), for appellant.
Sylvia O. Hinds-Radix, Corporation Counsel, New York, NY (Scott Shorr, Anna W. Gottlieb, and Geoffrey Stannard of counsel), for respondent.
DECISION & ORDER
In an action to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Kings County (Katherine Levine, J.), dated August 2, 2019. The order granted the defendant‘s motion pursuant to
In July 2014, the plaintiff and the defendant entered into a contract in which the plaintiff agreed to provide labor and materials on an exterior masonry project at a school in Brooklyn. After the plaintiff began work on the project, it submitted a document entitled “Request For Information” to the defendant in which it stated that it was “being asked to go above and beyond” the scope of work provided for in the contract. Specifically, the plaintiff stated that the masonry inspector on the project was “requiring a complete plaster coat prior to [the] installation of brick,” while the contract “merely [spoke] to filling the collar joint“—the vertical longitudinal space between walls of masonry, or between a masonry wall and a backup system—“with mortar.” The defendant responded that “parging” was required by the contract, and thus rejected the plaintiff‘s position that it had been asked to perform additional work for which it was entitled to additional compensation.
The plaintiff performed the disputed work and then commenced this action against the defendant to recover damages for breach of contract. The defendant filed a pre-answer motion pursuant to
“A motion to dismiss a cause of action pursuant to
“On a motion to dismiss a complaint pursuant to
A contractor may properly recover payment for additional work that is not contemplated by the terms of the original agreement, and which is performed at the direction of the defendant (see Arnell Constr. Corp. v New York City Sch. Constr. Auth., 144 AD3d 714, 715). On the other hand, a contractor may not recover for any alleged extra work that was, in fact, covered by the terms of the original contract (see Borough Constr. Co. v City of New York, 200 NY 149, 153; Arnell Constr. Corp. v New York City Sch. Constr. Auth., 144 AD3d at 715; Metro Group Constr. Corp. v Town of Hempstead, 24 AD3d 632, 633-634).
Here, the Supreme Court erred in granting the defendant‘s motion to dismiss the complaint. The contract excerpts and design drawing submitted by the defendant in support of its motion did not utterly refute the plaintiff‘s allegations that the application of a complete plaster coat prior to the installation of brick was outside the scope of the contract (see Leader v Steinway, Inc., 180 AD3d at 887-888). One contract provision cited by the defendant required that, “[i]n solid masonry construction, ensure that entire collar joint is filled between the backup and the face masonry,” and a design drawing submitted by the defendant included language to the same effect. But the plaintiff did not dispute that the collar joint needed to be filled with mortar; rather, it asserted that the application of a layer of plaster was an additional procedure not contemplated by the contract.
The defendant also contended that a contract provision requiring that the “[e]xisting mortar bed for replaced brick shall be thoroughly removed and the back parged with a coat of new mortar to fill the collar joint,” further demonstrated that the disputed work was encompassed by the contract. That
Thus, the materials submitted by the defendant did not warrant dismissal under
The parties’ remaining arguments either are without merit, are not properly before this Court, or need not be addressed in light of our determination.
MILLER, J.P., MALTESE, ZAYAS and FORD, JJ., concur.
ENTER:
Maria T. Fasulo
Clerk of the Court