Delon Hampton & Associates, Chartered Envirodyne Engineers, Incorporated v. Washington Metropolitan Area Transit AuthorityDelon Hampton & Associates, Chartered Envirodyne Engineers, Incorporated v. Washington Metropolitan Area Transit Authority
OPINION
Thе question we decide is whether the district court correctly determined that the Washington Metropolitan Area Transit Authority’s (“WMATA”) claim against an architectural and engineering firm was barred by Virginia’s statute of limitations and statute of repose. Holding that the statutes did not bar WMATA’s claim, we reverse.
Delon Hampton & Associates and Envi-rodyne Engineers, Inc.,
1
formed a joint venture (DHWN, but for simplicity, hereafter called “Hampton”), to provide architectural and engineering services to build the Alexandria Service and Inspection facility (“Alexandria facility”), a part of the Metrorail system of WMATA. WMATA claims that Hampton, which was awarded the contract to perform the services, committed numer
I. Factual Background
WMATA was established by an interstate compact аmong Virginia, Maryland and the District of Columbia to provide a regional system of transportation for the Washington, D.C., metropolitan area (“WMATA Compact”). Congress consented to the WMATA Compact and adopted it for the District of Columbia.
See
The Act of November 6,1966, Pub.L. No. 89-774, 80 Stat. 1324 (1967). The Virginia and Maryland legislatures separately adopted the WMATA Compact.
See
As part of its functions, WMATA constructed and now operates the rapid rail system known as Metrorail. In March 1974, WMATA awarded Hampton the contract to design and furnish engineering services for the Alexandria facility. In February 1979, Hampton submitted design drawings to WMATA and the latter made them available to contractors for bids. 3
In August 1979, WMATA awarded the construction contract to build the Alexandria facility to Blake Construction Company (“Blake”). Blake startеd work in September 1979 and substantially completed construction in April 1982. During the course of construction, the Resident Engineer for Blake informed WMATA of numerous “design-related discrepancies” in Hampton’s plans. At WMATA’s request, Blake corrected the design defects and WMATA attempted to recover the resulting expenditures from Hampton.
4
In April
On November 21, 1989, Hampton filed suit in United States District Court asking for a declaration that WMATA’s claim did not fall under the Dispute Clause of the contract and that the claim was barred both by Virginia’s statute of limitations and statute of repose. In December 1989, WMATA filed its answer and counterclaim, seeking damages for the design defects.
On February 9, 1990, following oral argument, the district court granted Hampton’s motion for summary judgment, holding that “the claim of the defendant for defective design drawings and cost changes needed to rectify design errors or omissions ... is barred by the five year statute of limitations.” In an amended Order, the district court added that the claim was also barred by the “five year statute of repose.” Hampton subsequently moved for Judgment on the Pleadings, asking for a definitive order that WMATA’s claim was not subject to the Dispute Clause of the cоntract. In its Final Order, the district court granted Hampton declaratory and in-junctive relief on both the timeliness and forum issues. It, of course, did not reach the merits of WMATA’s claim for damages. WMATA appeals only the timeliness issue.
II. The Virginia Statute of Limitations
Subject to the provisions of § 8.01-243 regаrding injuries to person and property and of § 8.01-245 regarding the application of limitations to fiduciaries, and their bonds, actions founded upon a contract, other than actions on a judgment or decree, shall be brought within the following number of years next after the cause of action shall have accrued:
2. In actions on any contract which is not otherwise specified and whiсh is in writing and signed by the party to be charged thereby, or by his agent, within five years whether such writing be under seal or not[.]
However, § 8.01-231 of the Virginia Code provides that the Commonwealth of Virginia is not subject to a statute of limitations unless the limitation expressly applies to the Commonwealth. 5 Specifically, it states:
Commonwealth not within statute of limitations. — No statute of limitations which shall not in express terms apply to the Commonwealth shall be deemed a bar to any рroceeding by or on behalf of the same.
WMATA concedes that the Virginia statute of limitations requires a claim based on a written contract to be brought within five years after the cause of action has accrued. It contends, however, that as an agency and instrumentality of Virginia it has sovereign immunity that shields it from the limitations bar. It also seems to argue, albeit somewhat confusingly, that it has
As a general proposition, an agenсy of the state shares the same privileges as that of the state, including sovereign immunity.
See Beatty v. WMATA,
Hampton contends, however, and the district court agreed that WMATA did not enjoy sovereign immunity from application of the statute of limitations in the instant case because
No statute of limitations which shall not in express terms apply to the Commonwealth shall be deemed a bar to any proceeding by or on behalf of the same. This section shall not, howеver, apply to agencies of the Commonwealth incorporated for charitable or educational purposes.
The first sentence was identical to that of the current statute. The second sentence, however, contained a qualification that state agencies incorporated for charitable and educational purposes were not еxempt. The
Burns
court held that while state agencies were entitled to the protection of
Had the provision [§ 8-35, the predecessor to§ 8.01-231 ] concluded with the first sentence, its meaning would have been clear for, by its terms, only the Commonwealth itself would be exempt from the bar of а statute of limitations, unless otherwise expressly stated. The second sentence is the source of additional meaning and is thus central to this appeal.
The second sentence excludes two types of state agencies from the saving grace of the provision: state agencies incorporated for charitable purposes and state agencies incorрorated for educational purposes. Because the legislature specifically excluded these two categories of state agencies, it appears that it intended to include other state agencies.
Id.
at 357,
conduct a study of accounts receivable due the Commonwealth. The study shall examine current policies and approaches and recommend appropriate changes to maximize the collection of receivables. The study shall be submitted to the Governor and the Chairmen of the House Appropriations and Senate Finance Committees by November 15, 1987.
1987 Va. Acts 1448. The resulting report included a number of recommendations, one of which was to amend
As written now,§ 8.01-231 establishes a statute of limitation for collecting debts owed to educational and charitable organizations. The current limitation is three years for an оral contract and five years for a written contract. There does not appear to be any justifiable reason why debts to these organizations should be treated any differently than debts to other entities. This statute of limitation should be eliminated.
A Review of the Commonwealth’s Management and Collection of Accounts Receivable, at II — 11 (Virginia Department of Planning and Budget, March 1988).
Thereafter, the Virginia legislature adopted comprehensive legislation to improve collection of debts by the state.
See
Ch. 544, 1988 Va.Acts 678. Part of this legislation eliminated the second sentence of
We are persuaded, despite the dictum in
Burns,
that if the Supreme Court of Virginia were now to interpret
III. Statute of Repose
Limitation on certain actions for damages arising out of defective or unsafe condition of improvements to real property. — No action to recover for any injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defеctive and unsafe condition of an improvement to real property, nor any action for contribution or indemnity for damages sustained as a result of such injury, shall be brought against any person performing or furnishing the design, planning, surveying, supervision of construction, or construction of such improvement to real property more than five years after the performance or furnishing of such services and construction. ...
Blake substantially completed building the Alexandria facility in April 1982 and the facility was “placed in use for its intended purpose” in November 1982. Consequently, the district court held that WMATA’s action, filed in November 1989, was barred by the five year statute of repose.
In support of the district court’s holding, Hampton argues that sovereign immunity does not protect WMATA from applicаtion of
unlike a “pure” statute of limitations that merely bars the maintenance of a remedy, the statute of repose bars theremedy and extinguishes the underlying cause of action. The exemption from suit accorded those named in the statute is a substantive right protected by the due process clause of the Constitution of Virginia, Article I, Section 11.
Owens-Corning Fiberglas,
Unfortunately for Hampton, however, it gains no solace from
Owens-Corning Fiberglas
because
WMATA asserts three causes of action in its counterclaim. Count I is for breach of contract; Count II is for negligence; and Count III is for breach of warranties. Despite Hampton’s argument that the claims “sound” in tort because they arise out of alleged negligence, we are persuaded by controlling Virginia precedent that this is a contract action. In
Oleyar v. Kerr,
The following distinction, between actions for tort or contract is made by the English Court of Appeals: “The distinction is this: If the cause of complaint be for an act of omission or non-feasance which, without proof of a contract to do what was left undone, would not give rise to any cause of action (because no duty apart from contract to do what is complained of exists) then the action is foundеd upon contract, and not upon tort. If, on the other hand, the relation of the plaintiff and the defendants be such that a duty arises from that relationship, irrespective of contract, to take due care, and the defendants are negligent, then the action is one of tort.”
Oleyar,
The judgment of the district court is, therefore, reversed and remanded to the district court for action consistent with the views expressed in this opinion.
REVERSED AND REMANDED.
Notes
. At the time of the contract, Envirodynе Engineers, Inc., was then doing business as Westen-hoff & Novick, Inc.
.WMATA argued that the dispute must be resolved through the administrative process provided for in the “Dispute Clause" of the parties’ contract. The Dispute Clause states in pertinent part:
(a) Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. The decision of the Contracting Officer shall be final and conclusive unless, within thirty (30) days from the date of receipt of such copy, the Contractor mails or otherwise furnishes to the Contracting Officer a written appeal addressed to [WMATA’s] Board of Directors. The decision of the Board of Directors or its duly authorized representatives for the determination of such appeals shall be final and conclusive unless determined by a court of competent jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidencе.
However, in
WMATA v. Buchart-Horn, Inc.,
. This initial release was voided in March 1979 and amended drawings were readvertised for bid in May 1979.
. The claimed costs resulting from the alleged design errors were presented in general categories:
Design deficiencies detected after construction $ 331,577
Design deficiencies detected prior to construction 457,599
Total $1,071,397
. This section apparently codifies the common law rule that a statute of limitations does not run against the sovereign.
See Commonwealth v. Owens Coming Fiberglas Corp.,
. Persuasively, the Commonwealth of Virginia submitted a brief amicus curiae, stressing that WMATA was an agency and instrumentality of the Commonwealth of Virginia.
.
See District of Columbia v. Owens-Corning Fiberglas Corp.,
. Article 7 states in full:
RESPONSIBILITY FOR WORK
(a)Notwithstanding any review, approval, acceptance or payment by the Authority, the Contractor shall be responsible for the professional and technical accuracy of all designs, drawings, specifications and other work or materials furnished under this contract, and shаll without additional cost or fee correct or revise any errors or deficiencies in its performance.
(b) The Contractor shall likewise be liable to the Authority for all costs to it of any kind caused by or resulting from the Contractor’s negligent performance of this contract.
(c) The rights and remedies of the Authority provided in this clause are in addition to any other rights or remedies provided by law or under this contract.