Dellinger v. MichalDellinger v. Michal
The record shows that on 17 May 1985 the parties entered into a contract for plaintiff to construct a house on defendants’ land. The contract stated that “[t]he cost of the house will be figured on a cost plus 10% basis with a ceiling of $186,880.00.” Plaintiff began construction around 10 June 1985 and continued construction through 2 March 1987. Several changes and additions were made to the contract after plaintiff began construction. Plaintiff alleged that the costs of construction and his contractor’s fee totalled $237,259.01. Defendants paid plaintiff $154,553.60.
When the contract was executed and plaintiff began construction, plaintiff held a limited general contractor’s license with a limitation of $175,000.00. On 17 July 1985, plaintiff obtained an unlimited license.
Plaintiff seeks to recover in excess of $82,705.41 plus interest and seeks a lien on defendants’ property. In their counterclaim, defendants seek at least $49,329.57 for damages resulting from plaintiffs alleged breach of the construction contract. In a judgment captioned “PARTIAL SUMMARY JUDGMENT” the trial court dismissed plaintiffs claims with prejudice and ordered plaintiffs claim of lien cancelled. Defendants’ counterclaim remains. Plaintiff appeals.
Plaintiffs sole assignment of error is to the signing and entry of judgment. Where the only question presented is whether the trial court erred in granting summary judgment, no other exceptions, or assignments of error are necessary.
Ellis v. Williams,
319
N.C. 413,
In
Brady v. Fulghum,
In this case, plaintiff was licensed up to $175,000.00 when the contract was executed. Two months later, plaintiff secured an unlimited license. Plaintiff began construction during the two-month period. He presented his affidavit that he had passed the unlimited general contractor examination when the contract with defendants was executed and that he had done approximately $2,800.00 worth of work before he was issued his unlimited license.
In Sample v. Morgan, supra, the Court stated:
Clearly the statute contemplates a differing level of expertise for those applying for and receiving a license in the three enumerated categories. In enacting this statute, the legislature reasonably determined that as the cost of a structure increased, there would be additional demands of expertise and responsibilities from the contractor. To permit a general contractor to recover amounts in excess of the allowable limit of his license would vitiate the intended purpose of this statute: to protect the public from incompetent builders. We therefore hold that a general contractor is entitled to recover only up to that amount authorized by his license.
Reversed.