Opinion for the Court filed by Senior Circuit Judge SILBERMAN.
Petitioner Delaware seeks review of two FERC orders by which the Commission conditionally approved an application to site, construct, and operate a liquid natural gas terminal near the mouth of the Delaware River. We dismiss the petition for lack of jurisdiction: Delaware lacks standing because it has not suffered an injury-in-fact.
*576 I
In September 2004, Crown Landing LLC, a wholly-owned subsidiary of BP America Production Company, filed an application with the Commission to site, construct, and operate a liquid natural gas import terminal at the mouth of the Delaware River. Onshore portions of the proposed project were to be located in New Jersey, but a pier designed for the unloading of tanker ships was planned to extend beyond New Jersey waters into that portion of the river which appertains to neighboring Delaware. 1
Section 3 of the Natural Gas Act (“NGA”), 15 U.S.C. § 717b(a) et seq., prohibits the importation of foreign natural gas without prior authorization by the Commission. As amended, 2 the NGA confers upon the Commission the authority to approve or deny applications for the “siting, construction, expansion, or operation of a [liquid natural gas] terminal.” With certain limitations, irrelevant here, approval orders may be issued conditionally as the Commission deems necessary or appropriate.
The NGA specifically provides for the protection of rights granted to the states under the Coastal Zone Management Act of 1972 (“CZMA”), 16 U.S.C. § 1451 et seq., and the Clean Air Act (“CAA”), 42 U.S.C. § 7401 et seq. Although the mechanisms differ, both of these statutes mandate that federal licensing authorities ensure compliance by proposed projects with relevant state-based environmental programs.
The CZMA tasks the states with the development of coastal zone protection programs in exchange for federal funding incentives. Upon approval of such a program by the National Oceanic and Atmospheric Administration, any applicant for a federal license to conduct activities in a coastal zone must certify that the proposed activity complies with the program adopted by the affected state. A copy of this certification must be furnished to the relevant state agency, which must inform the federal government within six months whether or not it concurs with the certification. Ordinarily, no license may be granted absent state approval of this compliance certification. 3 However, if the Secretary of Commerce concludes, whether on his own initiative or upon appeal by the applicant, that the project is consistent with the objectives of the CZMA or otherwise necessary on national security grounds, the state’s pre-approval rights may be preempted and the project may proceed.
The CAA similarly requires each state to adopt a plan to implement, maintain, and enforce national air quality standards within the state. Once the Environmental Protection Agency has approved of a state plan, no department or agency of the federal government is authorized to license any activity that fails to conform with the plan. Federal agencies bear an “affirmative responsibility” to ensure that any proposed project conforms with the applicable state plan prior to approval. Under this statute, there is no provision permitting a federal official to override a state, but, on the other hand, there also does not appear to be any mechanism for the state specifically to disapprove a project.
*577
Crown Landing did not file a CZMA certification with Delaware but did request a status decision from the state (we gather that a status decision is, in effect, a preliminary, yet preemptive, decision). On February 3, 2005, the Delaware Department of Natural Resources and Environmental Control, petitioner here, issued its decision and rejected the project. On appeal, Delaware’s Coastal Zone Industrial Control Board unanimously affirmed that decision. Meanwhile, New Jersey filed an original action before the Supreme Court challenging Delaware’s jurisdiction to regulate the Crown Landing terminal pursuant to its authority under the CZMA. The Supreme Court confirmed that Delaware indeed possesses this authority.
New Jersey v. Delaware,
— U.S. -, -,
Delaware requested agency rehearing on the basis that the Commission had exceeded its statutory authority by approving the application under its NGA powers
before
the requirements of the CZMA and CAA had been satisfied. In Delaware’s view, issuance of an approval order — conditionally or otherwise — is
ultra vires
conduct unless the Commission has first ensured compliance with relevant state environmental programs. Rehearing was denied. Order Denying Rehearing and Issuing Clarification,
Crown Landing LLC,
Docket No. CP04-411-001,
II
As noted, FERC, along with intervenor Crown Landing, challenges Delaware’s standing, asserting that the state lacks an injury-in-fact, because FERC’s order is explicitly conditioned on state approval under the CZMA (and CAA). Indeed, the state has already exercised its CZMA authority to reject the project, which has received the imprimatur of the Supreme Court.
See New Jersey,
Delaware argues that the CZMA unambiguously grants the state priority in the approval process. The statute reads in relevant part: “[n]o license or permit shall be granted by the Federal agency until the state or its designated agency has concurred with the applicant’s certification.” 16 U.S.C. § 1456(c)(3)(A). The CAA contains similar language. 42 U.S.C. § 7506(c)(1). The merits therefore depend upon whether FERC’s conditional approval order constitutes a “license or permit” within the meaning of these statutes.
Of course, in considering standing, we must assume the validity of Delaware’s merits argument,
i.e.,
that FERC violated the statutory scheme by going ahead and issuing a conditional order, because Delaware had a statutory right to go first
(i.e.,
Alphonse ahead of Gaston).
See Warth v. Seldin,
Still, we are unable to see how FERC’s allegedly illegal procedure causes Delaware any injury in light of FERC’s acknowledgment of Delaware’s power to block the project. Delaware is apparently concerned that it will face intense political pressure to acquiesce in FERC’s conditional approval and reverse its own status decision — pressure it would somehow avoid were FERC not to have acted at all. We could hardly recognize this conjectural political dynamic as representing a concrete injury or, indeed, any sort of legally-cognizable injury. Delaware essentially is asking us to prevent it from changing its own mind.
To be sure, Delaware mentioned in its brief and stressed at oral argument that, under the CZMA, Crown Landing could potentially appeal any Delaware denial directly to the Secretary of Commerce. It is argued, therefore, that Delaware is not adequately protected by FERC’s conditions. But as we read FERC’s order, this is not so. The Commission conditioned its approval on Delaware’s approval — which would be unaffected by any subsequent action by the Secretary of Commerce. FERC’s counsel dispelled any doubt on this score by unequivocally assuring us at oral argument that any modification of the Commission’s position — including to recognize an intervention by the Secretary— would require a new order. 5
That leaves Delaware with the argument that it was injured because it has suffered the loss of a statutory procedural right— the right to precede FERC and thereby prevent a FERC proceeding. Delaware’s difficulty is that an alleged procedural injury does not confer standing unless the
*579
procedure affects a concrete substantive interest.
Lujan v. Defenders of Wildlife,
Delaware points to two cases to support its statutory procedural right claim — one is ours and one the Fifth Circuit’s. In Zivotofsky v. Secretary of State, 444 F.3d 614 (D.C.Cir.2006), we recognized that a child born in Jerusalem had standing to insist that his U.S. passport record his birthplace as Israel. But there the plaintiff claimed that the State Department had violated a statutory right to receive this precise passport alteration upon request; he did not assert a procedural injury at all, nor was the alleged harm limited to speculative future psychological effects, as the government argued. Rather, the right to a proper listing of the child’s birthplace was a substantive right conferred by Congress.
At first glance,
Texas v. United States,
In sum, because FERC’s order — as it stands now — cannot possibly authorize Crown Landing’s project absent the approval of Delaware, the state has suffered no injury-in-fact, and thus lacks standing.
For the foregoing reasons, the petition for review is dismissed.
So ordered.
Notes
.The First State’s title to certain submerged lands within a twelve-mile radius of the New Castle courthouse was conclusively determined by the Supreme Court in
New Jersey v. Delaware,
. Energy Policy Act of 2005, Pub.L. No. 109-58, 119 Stat. 594 (2005).
. In the event that the state fails to inform the federal government of its decision within the allotted six month period, the state’s
. Order Granting Authority Under Section 3 of the Natural Gas Act and Issuing Certifícate,
Crown Landing LLC; Texas Eastern Transmission LP,
Docket Nos. CP04-411-000, CP-04-416-000,
. It is not apparent that even if FERC allowed construction to move forward based on a secretarial decision, Delaware would have standing based only on their procedural (Alphonse-Gaston) theory, but, of course, Delaware would then have standing to challenge FERC's order and the Secretary's decision as an interpretation of the substantive statutes (including the APA). In any event, this scenario — which was not raised in Delaware’s opening brief — hardly presents a ripe controversy now.
. Delaware heavily relies on the Supreme Court's statement in
Massachusetts v. EPA
that state petitioners are “entitled to special solicitude in [courts'] standing analysis.”
