Noel Delahaye, Appellant-Respondent, v Saint Anns School et al., Respondents-Appellants, et al., Defendant.
Supreme Court, Appellate Division, Second Department, New York
May 8, 2007
836 N.Y.S.2d 233 | 40 A.D.3d 679
Ordered that the order is modified, on the law, by deleting the provision thereof denying that branch of the cross motion of the defendants GJF Construction Corp., doing business as Builders Group, incorrectly sued herein as Builders Group (Park Row), Inc., and Builders Group, LLC, which was for summary judg
The plaintiff allegedly was injured when he fell off a ladder while performing drywall taping work on the second floor lobby of a building under renovation which was owned by the defendant Saint Anns School (hereinafter St. Anns). He was attempting to smooth over an area surrounding a sprinkler head located close to the ceiling. The plaintiff subsequently commenced this action against St. Anns, the construction manager hired by St. Anns for the project, GJF Construction Corp., doing business as Builders Group, incorrectly sued herein as Builders Group (Park Row), Inc., and Builders Group, LLC (hereinafter collectively Builders Group), and the contractor hired to perform certain work relating to the interior, Best Choice of New York (hereinafter Best Choice). The plaintiff seeks to recover damages for his personal injuries, alleging violations of
The Supreme Court denied the plaintiff‘s motion for summary judgment on the issue of liability on his cause of action pursuant to
The Supreme Court properly denied the plaintiff‘s motion for summary judgment on the issue of liability on his cause of action pursuant to
In order to prevail on a
The Supreme Court properly granted that branch of the cross motion of Builders Group which was for summary judgment dismissing the complaint insofar as asserted against it. “A party is deemed to be an agent of an owner or general contractor under the Labor Law when it has supervisory control and authority over the work being done where a plaintiff is injured” (Linkowski v City of New York, 33 AD3d 971, 974-975 [2006]; see Walls v Turner Constr. Co., 4 NY3d 861, 863-864 [2005]; Russin v Louis N. Picciano & Son, 54 NY2d 311, 317-318 [1981]; Miano v Skyline New Homes Corp., supra; Chimborazo v WCL Assoc., Inc., supra). To impose such liability, the defendant must have the authority to control the activity bringing about the injury so as to enable it to avoid or correct the unsafe condition (see Linkowski v City of New York, supra; Damiani v Federated Dept. Stores, Inc., 23 AD3d 329, 331-332 [2005]). It is not a defendant‘s title that is determinative, but the amount of control or supervision exercised (see generally Aranda v Park E. Constr., 4 AD3d 315, 316 [2004]).
In opposition to Builders Group‘s prima facie showing of entitlement to judgment as a matter of law, the plaintiff and St. Anns failed to raise a triable issue of fact as to whether Builders Group was a general contractor or St. Anns‘s statutory agent for purposes of the Labor Law (see
Likewise, since no evidence was submitted to demonstrate that St. Anns had any control or supervisory role over the work of the plaintiff, so as to enable it to prevent or correct any unsafe conditions, or that St. Anns provided the allegedly defective ladder or had notice of any defects, there are no triable issues of fact as to St. Anns‘s liability under the
To obtain common-law indemnification from Builders Group, St. Anns was required to establish that Builders Group was either negligent, or supervised or controlled the plaintiff‘s work (see Linkowski v City of New York, supra; Singh v Congregation Bais Avrohom K‘Krula, 300 AD2d 567, 569 [2002]). Since St. Anns failed to present such evidence, the Supreme Court properly granted that branch of the cross motion of Builders Group which was for summary judgment dismissing St. Anns‘s cross claim for common-law indemnification. However, the Supreme Court erred in denying that branch of the cross motion of Builders Group which was for summary judgment dismissing St. Anns‘s cross claim for contractual indemnification. The original agreement between St. Anns and Builders Group did not contain an indemnification provision, and St. Anns failed to raise a triable issue of fact as to whether Builders Group subsequently agreed to indemnify St. Anns. The only evidence offered by St. Anns in support of its claim was a conclusory assertion that there was a meeting of the minds on this issue and an unsigned indemnification agreement which had been forwarded to Builders Group after the work had commenced.
“While leave to amend a bill of particulars is ordinarily to be freely granted in the absence of prejudice and surprise, when leave to amend is sought on the eve of trial, judicial discretion should be exercised in a ‘discreet, circumspect, prudent and cautious manner‘” (Fuentes v City of New York, 3 AD3d 549,
The Supreme Court providently exercised its discretion in denying the plaintiff‘s cross motion for leave to amend his bill of particulars, which, if granted, would have been the plaintiff‘s third amendment of his bill of particulars. The cross motion was made after the plaintiff filed a note of issue and certificate of readiness and moved for summary judgment. The plaintiff‘s proffered reason for his delay is disingenuous in view of the fact that the plaintiff was in possession of the necessary information at the time he made his initial motion. In any event, the amendment was prejudicial to the defendants and lacked merit. The plaintiff sought to assert a violation of
Builders Group‘s remaining contention is without merit.
Schmidt, J.P., Santucci, Florio and Balkin, JJ., concur.
