17 Kan. 263 | Kan. | 1876
The opinion of the court was delivered by
This was an action by Goldie to foreclose a mechanic’s lien. M. W. Delahay was the' owner, J. P. Taggart the contractor, and Goldie claimed as sub-contractor. The latter made Taggart, M. W. Delahay, and Louisiana/ Delahay, parties defendant. He recovered a personal judgment against Taggart, and a portion of this amount was ad
I. The only allegation in the petition against Mrs. Delahay is in these words: “And said plaintiff further says, that the said Louisiana Delahay and the said J. P. Taggart claim ari interest in this controversy adverse to the plaintiff, that the extent of such interest, if any, to this plaintiff is unknown, and that they be compelled to set up their interest, if any.” She filed no answer. Upon this a decree was entered barring her of all interest in the premises. This was erroneous. Short v. Nooner, 16 Kas. 220.
II. The statement for the lien was verified, not by the claimant, but by an agent. Counsel contend that, inasmuch as verification by an agent is not in terms authorized by the lien.law, and as the lien law is in derogation of the common law, no such verification is sufficient. If the statute had prescribed by whom the verification should be made, it might well be contended that such provision was exclusive. But the statute simply requires the filing of a statement, “verified by affidavit.” Laws 1872, p.296, §3. It would be adding to the statute to hold that only the claimant’s affidavit was sufficient. In all the instances cited by counsel in which express authority is given to agents and attorneys to make affidavits, the principals are likewise expressly named. The omission here is certainly significant. In Ohio, under a statute which provided that the claimant should file a statement “after making oath thereto,” a verification by an agent was held sufficient. Williams v. Webb, 2 Disney, 430; Dorman v. Crozier, 14 Kas. 224.
III. Again, it is claimed that as Goldie was a lumber dealer, who had no contract with Delahay, but simply sold
IV. Finally, it is claimed that as nothing was shown to be due and unpaid by Delahay to Taggart at the time of the filing of the lien, no recovery could be had against the premises. But the contract between Delahay and Taggart provided for the payment of many times the sum now claimed by Goldie; and, as heretofore decided under the lien law of 1872, the lien of the sub-contractor is limited only by the amount contracted to be paid the contractor; and all payments made to the contractor prior to the expiration of sixty days after the completion of the building are at the risk of the owner. Shellabarger v. Thayer, 15 Kas. 619; Shellabarger
The judgment of the district court as to M. W. Delahay will be affirmed; as to Louisiana Delahay it will be reversed, and the case remanded with instructions to render judgment in her favor for costs. The costs of this court will be divided between Goldie and M. W. Delahay.