58 N.Y.S. 277 | N.Y. App. Div. | 1899
This action has been twice tried. On the first trial the referee held that the defendant was not required by the contract to pay on the tenth day of each month ninety per cent of the value of all materials furnished and labor performed during the preceding month, but was bound to pay only ninety per cent of the value of such work as had been fully completed and of materials used in completed work. The referee also held that the 'provision in defendant’s proposals, “ The vitrified pipe line is mostly and the tunnels are entirely to be in soft shale rock,” was not binding on the defendant. On an appeal to the General Term it was held that, these constructions of the contract were erroneous, and a new trial was granted. (77 Hun, 124.)
The contract provided : “ The party of the first part (the defendant) agrees that their executive committee will cause an estimate to be made before the tenth day of each month of the value of the labor and materials on all work completed up to the first day of the same month, and will on said 10tli day of each" month pay to the party of the second part (the plaintiff), as a partial payment, 90 per cent of the contract price of such completed work.”
In July, 1889, the plaintiff began the construction of the principal or “ Kent Reservoir,” and shortly afterwards was stopped by the-owner of the fee of the land upon which the reservoir was to be constructed because the village had not acquired title to the land, and for more than a month labor was suspended upon that part of the-work because the title had not been acquired, which was solely th& defendant’s fault.
The referee also found, upon evidence which is ample to sustain the-finding, that the vitrified pipe line was not mostly and the tunnels-entirely in soft shale rock, but, on the contrary, that these excavations were in solid rock, which caused additional expense and delayed the prosecution of the work, for which the. plaintiff was entitled to extra compensation. These were the failures on the part of the defendant' which the referee specifically found. Tliedefendant did not furnish detailed working plans, definitely describing how the several parts of the work were to be performed, and. the referee was of the opinion' that as the contract did not speciii
The learned referee held that, by reason of the defendant’s failure to pay monthly ninety per cent of the value of the work done and materials furnished during each preceding month, and by its delay in acquiring title to the land for the Kent reservoir, and because the ■excavations for the vitrified pipe line and the tunnels were in hard instead of in shale rock, the plaintiff was excused for not completing his contract bv the 1st of December, 1889. Aside from the failure to complete the work within the time contracted, the referee found that the plaintiff had failed to lay several hundred feet of the pipe lines six feet below the surface, and that by reason thereof the ■defendant was damaged to the extent of $2,000, which sum the referee deducted from the amounts found due the plaintiff for work ■done and materials furnished.
It is not urged in behalf of the defendant that the referee erred in the admission or rejection of evidence, and I am of the opinion that the defendant has failed to demonstrate that the referee has. erred to the prejudice of the defendant, and that this appeal cannot be sustained.
But a single question is urged in support of the plaintiff’s appeal, which is that the referee erred in not allowing him interest on all or some of the items making up the sum recovered. The case does not show that the defendant has collected the plaintiff’s certified check for §2,000, deposited by the plaintiff as security for his performance of the contract, and in the absence of such evidence the plaintiff is not entitled to interest on that item. The other items making up. the recovery were unliquidated. Neither the quantities of the work performed nor the quantities of materials furnished, for which the prices were agreed on, had been ascertained, nor could they be readily ascertained by the defendant, and the amount when ascertained was subject to a reduction for damages sustained by the defendant for improper performance by plaintiff of some of the work, and the amounts due for extra work, for which prices were not agreed on, were clearly unascertainable without taking evidence. The claims recovered by the plaintiff were unliquidated. (Mansfield v. N. Y. C. & H. R. R. R. Co., 114 N. Y. 331; Gray v. Central R. R. Co. of N. J., 89 Hun, 477; affd., 157 N. Y. 483.)
I think no error was committed in refusing to allow the plaintiff interest on the several items included in his recovery.
The judgment is affirmed, without costs to either party, as both have appealed and neither has succeeded.
All concurred.
Judgment affirmed, without costs to either party.