28 Mo. App. 540 | Mo. Ct. App. | 1888
If the question were res nova in this jurisdiction, I should hold that, where a party executes a bond, as did this plaintiff, contemporaneously
There is, however, something more in the answer of defendant than the allegation of the execution of the bond by plaintiff as surety. There is an express plea of damnificatum. It is alleged that the contractor had not kept his contract; that he abandoned it before its completion, to defendants’ damage; that he had not protected it against mechanics’ liens, whereby defendant had paid out more than the contract price, to-wit, $156.29 ; for unfinished work, seventy-five dollars ; delay in finishing said work, seven hundred and fifty dollars, and the like. If these facts were true, there existed in favor of the defendant, at the time of filing his answer, a cause of action against the plaintiff on his bond, although it may be said it was merely a bond of indemnity, because the defendant had suffered loss and damage, against which the plaintiff had undertaken to indemnify him. Jones v. Childs, 8 Nev. 121; Belloni v. Freeborn, 63 N. Y. 384; Tankersly v. Anderson, 4 Des. 43; Carman v. Noble, 9 Pa. St. 371.
The Hartman case holds that the very moment the plaintiff brought this action, even without a judgment, he became liable on his bond for the amount. In Trustees v. Heis & Co. (44 Md. 455), the action was brought on the equity side of the court to enforce a mechanic’s lien; the practice there requiring such actions to be brought on the chancery side of the court. The plaintiff had given to defendant, owner of the-property, a bond of indemnity, as here. The court said it would be grossly inequitable to allow the claimant, the obligor, to proceed to the enforcement of his lien, and the possible sale of the church property, in the-very face of his bond that no such lien should exist. In that case there does not appear to have been any other breach of the contract than the suffering of the lien in question to be placed upon the property. So the court,.
The instructions given by the court, although subject to some verbal criticism, perhaps, and might have gone further and been made to apply to the damages already sustained by the defendant as a measure of recoupment or counter-claim, yet, the jury, under the instructions, did find the fact to be that the defendant had wholly performed the contract on his part, by paying out the whole contract price for the work done and materials furnished for the building, and that this claim is for an excess over and above the contract. Why, then, should the plaintiff recover, when the very sum thus asked for was a breach of his bond, and which he must return to the defendant, for so it is “nominated in the bond.”
The judgment was for the right party, and, the other judges concurring, it is affirmed.