202 A.D. 390 | N.Y. App. Div. | 1922
Lead Opinion
The third, sixth and seventh causes of action alleged in the complaint are the only ones involved on this appeal. The “ seventh ” is for damages alleged to have been sustained from the defendant’s breach of the contract occasioned by the delay on the part of the engineer of the Public Service Commission in furnishing the plaintiff with certain steel drawings as required by the contract for long
The “ third ” and “ sixth ” causes of action are for the construction of what is called “ By-passing.” By that term is meant the temporary cutting out or non-user of the gas mains under the street and the laying of substituted temporary overhead gas pipes until all danger attendant upon the use of the original pipes is passed.
The plaintiff, respondent, claims that it is entitled to be recompensed for the expense involved in constructing the “ by-passing.” The jury found in favor of the plaintiff on both claims, i. e., the sum of $153,553 for the item of delay and $31,263 for “ by-passing,” to which the court afterwards directed the clerk to add interest.
The first question that confronts us is whether the defendant is liable for the delays in furnishing the steel drawings to the plaintiff on the part of the engineer of the Public Service Commission. There were three general sets of plans or drawings provided for by the contract. The first set of plans are known as contract drawings, which are delivered to bidders for the contract at the charge of five dollars for a set. The second set of plans are known as construction or amplifying drawings showing the location, elevation of the structure and its appurtenances and the various details connected therewith and are required to be furnished from time to time by the engineer of the Public Service Commission. The third set of plans are made from the amplifying drawings and are known as shop drawings giving minute details of the steel construction. These last-named drawings are made in the first instance by the contractor and are submitted to the engineer of the Public Service Commission for his approval.
The theory of the plaintiff’s claim is that if it had been furnished with the amplifying plans at the time operations were started in January, 1913, the performance of the contract would have been completed by September, 1914.
The rule ordinarily applicable to the construction of contracts between private individuals and private corporations is that where the language of the agreement manifests a clear intention that the parties shall do certain acts, an action for damages for non-performance thereof will lie. It is upon this proposition that the plaintiff rests its claim, relying upon the case of Mansfield v. N. Y. C. & H. R. R. R. Co. (102 N. Y. 205) and which Mr. Justice Merrell cites in his dissenting opinion. But it must be manifest that where a contract between the parties does not clearly indicate that one of them will be responsible for certain acts complained of, the rule is not applicable.
It has been repeatedly held that the Rapid Transit Railroad Commissioners, as they were formerly termed, or the Public Service Commissioners of the First District, as their successors at the time in question were called, and who have been since superseded by the Transit Commissioners, are not agents in a general sense of the city of New York, nor are any of their employees to be regarded as such agents. The Public Service Commission is a State body, independent of the municipal government. (People ex rel. New York Dock Co. v. Delaney, 192 App. Div. 734, 739.)
In actions for injuries brought on the theory of negligence it has frequently been held that the negligence of the Commissioners or their agents is not imputable to the city. (O’Brien v. City of New York, 182 App. Div. 810, 813.) The Massachusetts Supreme Court has also so held. (Mahoney v. Boston, 171 Mass. 427; Murphy v. Hugh Nawn Contracting Co., 223 id. 404; McGovern v. Boston, 229 id. 394.)
In the last-mentioned case (McGovern v. Boston, supra) the plaintiffs had made a contract with the city of Boston through the Boston Transit Commission, a body created by law,
In the instant case the theory of the complaint is that the acts of the Commission or its chief engineer were careless, in that they delayed in giving certain plans to the plaintiffs. In other words, the real basis of the claim is the negligence of the engineer or his subordinates.
The contract in suit specifically provided as to detail drawings as follows: “ Section No. 36. The Engineer [referring to the engineer of the Public Service Commission] will prepare and furnish to the contractor, from time to time as required, drawings and plans amplifying such details of the contract drawings as may be necessary; and drawings and plans necessary to show the adjustment and reconstruction of all surface and sub-surface structures wherever the reconstruction of the same is necessitated by the construction of the railroad. These plans must be strictly followed, unless local conditions should develop, during the construction, suggesting changes, when, with the approval of the engineer, such changes may be permitted.”
Under article 24 it is provided that the engineer “ shall determine all questions in relation to the works and the construction thereof and shall in all cases determine ■ every question which may arise relative to fulfillment of this contract on the part of the contractor. His determination and estimate shall be final and conclusive upon the contractor, and in case any question shall arise between the parties hereto, touching this contract, such determination and estimate shall be a condition precedent to the right of the contractor to, receive any money under this contract.”
It thus appears that the parties by express agreement have recognized that the engineer occupies a position over which the defendant has no control and that both the defendant and the plaintiff would in many instances be absolutely bound by the decision which the engineer may make, assuming, of course, that it is not made as the result of fraud or of bad faith. It is difficult to understand upon what theory the city may be held liable for the acts of the engineer in delaying the delivery of plans to plaintiff who knew or was presumed to know the provision of the statute and the con
It would seem to follow that it must have been understood by the parties that for any negligence or delay occasioned by the engineer in respect of a matter under his jurisdiction and over which the city had no control whatever, the city could not be held responsible. Moreover, the contract contains a provision which requires the construction work to be performed thereunder to be completed within a certain time and also provisions to the effect that if the contractor is delayed by causes over which he has no control he would be entitled to additional time for completing the work, to the extent to which he has thus been delayed.
Even if wre assume that the city might under certain circumstances be liable, it should at least then be made to appear that the defendant was duly notified of the delay to which the plaintiff was put, to afford an opportunity to the city to remedy the troubles complained of, if it was within its ability or power so to do.
Article 43 of the contract reads as follows:
“ Contractor’s claims for damage. Statement of damage to be filed with the engineer. Article XLXII. If the contractor shall claim compensation for any damage sustained by reason of the acts of the Commission, or its agents, he shall, within ten days after sustaining such damage, make a written statement of the nature of the damage sustained to the engineer. On or before the 15th day of the month succeeding that in which any such damage shall have been sustained, the contractor shall file with the engineer an itemized statement of the details and amount of such damage, and, unless such statement shall be made as thus required, his claim for compensation may be forfeited and invalidated, and he shall not be entitled to payment on account of any such damage.”
It seems to me that this was a precautionary provision which was designed to prevent such a claim as the one here asserted. Assuming, however, that a liability against the city under this clause could be predicated under the acts of the engineer of the Commission, then we must treat this clause as meaning that there would be a strict compliance thereof by filing the statement as therein required, and a failure so to do is fatal to a recovery. But assuming that the city is liable for damages, it is clear that it is incumbent upon the plaintiff to establish damages which directly resulted from the acts complained of. In this case it appears that the plaintiff had subcontracted the work. There was no evidence to show that the plaintiff had either voluntarily adjusted any claim flowing from the delay by the subcontractor asserted against it, or that any judgment for damages resulting from the delay com
The rule has been stated in Dunn v. Uvalde Asphalt Paving Co. (175 N. Y. 214, 218) as follows: “ The contract of indemnity implied by law, in favor of one who is legally liable for the negligence of another, covers loss or damage, and not mere liability. (Sedgwick on Damages,
I think the measure of damages is also criticizable for other reasons. Thé court permitted expert testimony to be given to show how long it would take to complete the work under ideal conditions. While it may be true that the engineer of the Public Service Commission had a right to give defendant certain latitude in the manner of continuing and progressing the work, nevertheless, the engineer of the Public Service Commission was really the only one who could determine how the work should be performed, so that what may be regarded by others as an ideal condition cannot control the rights of the parties.
The theory of damages allowed by the court was based upon the difference between the contract price and the cost of doing the work in the most approved manner as evidenced by the testimony of alleged experts as to what in their opinion would be the most economical and most expeditious way of doing the work.
The contract did not provide when the drawings were to be furnished by the engineer. The engineer had the absolute power to determine in what manner the work was to be done. In the absence of proof that the actions of the engineer were corrupt or malicious, they should not be subject to review by the court. If outside testimony should be permitted to be given that the work could be prosecuted more expeditiously than by the method adopted by the Commission’s engineer, the value of a public contract would be nil.
The rule of damages applicable to a case like this was discussed in the case of Uvalde Asphalt Paving Co. v. City of New York (196
Here was an item which could definitely have been proven if any records thereof were kept. The same witness testified that he could not give any record or any date as to the exact amount of expense involved in making the various shifts in plant, the reason for that being that no records were kept.
Another item of damage was for $24,667, the extra cost of timber due to the acts of the engineer of the Commission. The witness was asked how he arrived at the extra cost of the timber
“ By-passing gas mains. Section No. 52. Wherever the excavations are decked, all gas pipes whose services cannot temporarily be dispensed with shall be by-passed, if directed by the engineer; temporary pipes to take their place being laid either upon or below the street or sidewalk surfaces. These temporary by-passing pipes will be paid for at the prices stipulated in Schedule Item 99-A.” (Italics mine.)
Section 59 of the specifications reads as follows:
“ Maintenance, support, etc. Section No. 59. The contractor shall at all times, by suitable bridging or other supports, maintain and support in,an entirely safe condition for the usual service and to the reasonable satisfaction of the owners, all surface, sub-surface and overhead structures and appurtenances encountered or affected during the prosecution of his work. Also, in order that access may be had in emergencies to gates or valves on water or gas mains and to electric manholes, where such gates or valves and manholes are decked over, trap doors of a suitable size shall be provided in the decking. All surface, sub-surface and overhead structures and appurtenances, and all surfaces of whatever character along*399 the line of the work shall be protected from injury, but should any injury occur the contractor shall fully restore such surface, sub-surface or overhead structures and appurtenances or surfaces to as good a condition as existed before the injury was done. All the above, including also all changes of surface, sub-surface or overhead structures and appurtenances made by the contractor for his own convenience in executing his work, shall be done at the contractor’s own expense and included in the prices stipulated in the schedule for excavation except as otherwise herein specifically provided.”
The following articles of the contract or parts thereof are also apposite:
“ Engineer’s determination to be final and conclusive upon contractor. Article XXIV. To prevent disputes and litigations, the engineer shall in all cases determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract; shall determine all questions in relation to the works and the construction thereof, and shall in all cases determine every question which may arise relative to the fulfillment of this contract on the part of the contractor. His determination and estimate shall be final and conclusive upon the contractor, and in case any question shall arise between the parties hereto, touching this contract, such determination and estimate shall be a condition precedent to the right of the contractor to receive any money under this contract.
“ Engineer to explain. Article XXY. The engineer shall make all necessary explanations as to the meaning and intention of the specifications, shall give all orders and directions contemplated therein or thereby and in every case in which a difficult or unforeseen condition shall arise in the performance of the work required by this contract.”
A reading of these paragraphs, I think, warrants the conclusion that the engineer has the sole power for deciding as to whether there should be “ by-passing ” or not, and that where the engineer decides that there was to be no “ by-passing ” of gas mains, the contractor would nevertheless have the right if he thought the situation warranted it to do such “ by-passing,” but in such a case the expense for that work is not chargeable upon the city.
Unless it can be shown that the “ by-passing ” was done upon the direction of the chief engineer there can be no recovery upon that item. Testimony given under the objection of the defendant’s counsel for the purpose of showing that the work of “ by-passing ” was necessary was, to my mind, entirely incompetent. Such testimony tended to present the question as to whether or not the
The letters of subordinates of the chief engineer that were admitted in evidence should have been excluded unless it could have been shown that they were sent with the approval of the chief engineer and that it was thereby intended to direct the “ by-passing ” to be done by the contractor for which it would be entitled to reimbursement on the part of the city.
The judgment and orders should be reversed and a new trial granted, with costs to appellant to abide the event.
Clarke, P. J., and Smith, J., concur; Latjghlin, J., concurs in result; Merrell, J., dissents.
See Mass Acts of 1894, chap. 548, § 23 et seg.— [Rep.
See Mass. Acts of 1911, chap. 741, § 17.— [Rep.
See 8th ed.— [Rep.
Dissenting Opinion
The plaintiff, Degnon Contracting Company, is a foreign corporation, duly organized under and by virtue of the laws of the State of New Jersey, duly authorized to transact business in the State of New York. On or about October 2, 1912, the plaintiff entered into a contract with the defendant, The City of New York, acting through and by the Public Service Commission of the First District, pursuant to the Rapid Transit Act (so called), to construct sections Nos. 1 and 2, route No. 11-B, Fourth Avenue subway, in the borough of Brooklyn.
It is admitted by the defendant, and was expressly alleged in its answer, that the plaintiff duly entered into said “ contract, in writing, with the City of New York, defendant, acting by the Public Service Commission.” It is well, at the outset, to bear in mind that it is the contract of the city of New York with which we have to deal.
Section No. 1 of the subway, the construction of which was embraced in the contract, extended from a point 25 feet south of Fortieth street to a point 110 feet south of Sixty-first street in the borough of Brooklyn; and section No. 2 extended from the last-mentioned point to a point 310 feet south of the center line of Eighty-ninth street in said borough of Brooklyn. Subsequently, section No. 2 was changed so that the southern terminus thereof was located at the south end of the Eighty-sixth street station. Separate contracts were entered into between the plaintiff and said Public Service Commission as to said two contiguous sections. For the purposes of its convenience in carrying on said construction work, the plaintiff subdivided its entire contract into two parts
“ Time is of the essence of this contract. The contractor shall begin actual work within sixty (60) days after the delivery of this contract. The entire work covered by this contract shall be completed in all respects within twenty-four (24) months from the date of the delivery of this contract.”
Each contract contained provisions reducing the price which the contractor was to receive for the work in case of its delay in completion beyond the twenty-four months, and according the city drastic powers in the event of such delay. It was further provided by article 16 of the contract that
“ The contractor shall complete the entire work in accordance with the specifications and contract drawings, and according to the other provisions of this contract and within the times specified in this contract, in the most workmanlike manner and with- the highest regard to the safety of life and property and according to the lines, levels and directions given by the engineer, for the prices herein agreed upon.”
This action was brought to recover of the defendant, The City of New York, damages claimed to have been sustained by the plaintiff in seven different respects/ and in its complaint the plaintiff sets forth and alleges seven separate and distinct causes of action. Those numbered first, second, fourth and fifth were eliminated by stipulation before or at the trial, and a part of the third and sixth causes of action, relating to the reconstruction of electric ducts and grading of sidewalks in both sections, were dismissed by the court upon the trial, and the plaintiff has not appealed therefrom. The issues raised by the pleadings as to so much of the third cause of action and the sixth cause of action set forth in plaintiff’s complaint as related to the by-passing of gas mains in said sections 1 and 2, and plaintiff’s right to recover therefor, were submitted to the jury, and the jury returned a verdict in plaintiff’s favor for the sum of $31,263, to which, by order of the court, there was added interest in the sum of $6,502.70. Plaintiff’s seventh cause of action was to recover damages alleged to have been caused by the delay of the defendant in furnishing certain construction drawings or “ steel drawings,” as they were called, which the defendant was obliged to furnish under the
Upon this appeal the defendant urges several grounds upon which it seeks a reversal of the judgment so entered against it. As to the plaintiff’s recovery for delay in furnishing the required plans and specifications for the steel drawings, the defendant contends that such delay or other negligence was that of subordinates of the Public Service Commission charged with furnishing construction or amplifying drawings to the contractor, for which negligence and delay the city is not responsible.
It is also claimed by the appellant that, inasmuch as the actual construction work was sublet by the plaintiff to a subcontractor upon a percentage basis, whatever damages were suffered by reason of delay or otherwise could be claimed only by the subcontractor, and that the plaintiff has not actually suffered as the result of such delay.
It is also the contention of the appellant that the contract provided a remedy to the contractor in case the work was delayed by way of an extension of time to complete it, and that, therefore, damages may not be recovered for such delay.
The appellant also contends that, by requesting and accepting extensions of time to complete the work, the contractor waived any claim for delay attributable to the defendant.
With reference to the plaintiff’s claim, the appellant urges that under the provisions of the contract the contractor was derelict in presenting its claim for damages.
The appellant also contends that the court improperly submitted plaintiff’s claim for damages by reason of alleged delays by the defendant in furnishing the necessary drawings, and also in fur
The appellant also contends that the verdict of the jury upon the delay claim was against the weight of the evidence.
Error is also claimed by the appellant in the manner in which the issues on the claims for by-passing were submitted to the jury, and also that the court erroneously allowed interest upon the amount of the by-passing claim for which the plaintiff recovered a verdict.
The extra allowance of costs to the plaintiff is also assailed by the appellant.
Taking up these' various contentions of the appellant, it seems to me, first, that the plaintiff established a sufficient basis for its claim against the city for damages arising from the delay of the engineer of the Public Service Commission in furnishing the required construction and steel drawings. Plaintiff’s claim for such delay arises with reference to section 2 of the work. The plaintiff makes no claim for damages for delay in furnishing plans and drawings with relation to section 1. The plaintiff claims that the city failed to keep its contract with the plaintiff to furnish the plaintiff with steel drawings in accordance with the terms of the contract, and in continuing such breach of contract for such an unreasonable period as to result in great damage to the plaintiff in carrying on its construction work. Furthermore, the plaintiff contends that, when the defendant did furnish the required construction drawings necessarily used in procuring the fabrication of the steel work, the same were supplied at straggling and irregular intervals and in scattered, disconnected portions of the section. The plaintiff claims that such delay and such disconnected manner in which the plans were furnished resulted in greatly increased expense in the construction of the subway, and interfered with . plaintiff’s orderly plans for excavating and building the subway structure. The plaintiff planned, with the approval of the Public Service Commission, to start its work on section 2 at the southerly or Eighty-sixth street end, and to work north to the northerly terminus of said section at Sixty-sixth street. It is the claim of the plaintiff that the subway could be built in this manner at a minimum cost, and it does not require an expert to appreciate the force of such claim. The construction involved several different steps. First, the excavation had to be made, which was accomplished by means of a steam shovel, which excavated part of the required depth of the trench; the second step of the excavation was by means of hoists and derricks. After the excavations were
The contract also provided: “ Generally the contractor will be permitted to conduct his work in the most expeditious manner possible, having due regard for the safety of persons and property and facilities for traffic, and under such instructions as the engineer may give from time to time.”
In order that the work might be completed within the contract period of twenty-four months, it is entirely evident that the most perfect system and the utmost speed was required in prosecuting the work. The contract further provided: “ All the work shall be prosecuted in the manner, according to local conditions, best calculated to promote rapidity in construction, to secure safety to life and property and to reduce to the minimum any interference with abutting property and the public travel.”
On October twenty-sixth the engineer of the Public Service Commission, who was in charge of the work in behalf of the city, gave the plaintiff written directions to proceed with its work of the construction of section No. 2.
In the subway construction work three general sets of plans or drawings were required, all of which were passed upon by the engineer’s office of the Public Service Commission. The first plans were known as the contract drawings from which the contractors made their bids. These were furnished at five dollars a set. After the contract was let to the successful bidder, a second set of plans, known as construction drawings, were to be furnished by the engineer of the Public Service Commission, and were known as amplified construction drawings. With the consent of the Public Service Commission, the structural steel work was sublet by the plaintiff to the American Bridge Company for fabrication. When the amplified construction drawings were furnished by the engineer of the Public Service Commission, they were turned over by the plaintiff to the American Bridge Company, which, in turn, prepared shop drawings of the fabricated steel work. Under the contract and practice of the parties, these drawings were in turn submitted to the engineer of the Public Service Commission, who passed upon the same, and modified, rejected or approved them. When finally approved by the engineer, they were returned to the American Bridge Company, who at once took up the fabrication of the steel work. The evidence shows that about seven months was required, after the final steel drawings were in shape, for the
Again, on January 22, 1913, plaintiff’s secretary wrote the chief engineer of the Public Service Commission, calling attention to the difficulty in obtaining steel, and urging that the general drawings for steel work be furnished the contractor at as early a date as possible. On February 4, 1913, plaintiff’s secretary again wrote the engineer, stating that work on the two sections had been commenced, both at Sixty-fifth street and at Eighty-sixth street, and that it was the contractor’s plan to prosecute each section northerly, and asking to have the drawings for the work prepared in the same consecutive order, and thus facilitate the delivery of steel in the order desired. On February 8, 1913, the chief engineer of the Public Service Commission wrote the plaintiff, replying to its letters of January eighteenth, January twenty-second and February fourth, and expressing an understanding of the
The first steel drawings that were actually furnished by the engineer of the Public Service Commission for the first or southerly section of the work were not received until June 20, 1913. In the meantime plaintiff’s engineer in charge of the work had called upon the designing department of the defendant and talked with Mr. Guertz, who was then in charge of the designing of the steel drawings, and told him that the contractor was anxious to get all the drawings as soon as he could, and asked him how long he thought it would take to get them out. Briggs testified, referring to Guertz: “ He said the steel drawings for sections 1 and 2 would not be completed within two months; but he thought they would be completed within three months. He said six men were constantly at work and they would not be withdrawn.”
Briggs testified that he then told him that the contractor would be glad to send money to facilitate the completion of the steel drawings, and offered to hire and pay for men and put them to work under the direction of the office of the said Public Service Commission designer. This offer was not accepted by the Public Service Commission. Guertz testified upon the trial, with reference to the contractor’s request for prompt plans: “ Why, I was not particularly interested from the contractor’s side except that those drawings were to be furnished within a reasonable time, as near as I could determine myself, unless other conditions arose, such as the contractor’s request that he be furnished drawings at a certain time and in that respect the chief engineer to a certain extent, in my opinion, has always the prerogative of indicating how fast or how slow work may proceed under certain conditions. I do not wish to be understood that the chief engineer limits the contract or has limited it, but I believe he holds the prerogative of determining when, where and how work shall be done.”
Interrogated with reference to the necessity of extra help in preparing the plans, Guertz was asked: “ Q. You said that it was not necessary to put on any extra force because the work for the construction had not been begun? A. I said there was sufficient men available. Q. For what? A. To take up the work of making the detail drawings, construction drawings. Q. Sufficient men available who would take thirteen months; that is what you mean? A. Why, in certain propositions it might take thirty years to work out a problem. That is no criterion.”
The appellant’s main contention is that even though plaintiff’s prosecution of the work was interfered with and hindered and delayed by the manner in which said construction drawings were furnished, nevertheless, the city should not be held liable therefor. I am unable to appreciate the force of the appellant’s position in this respect. It is conceded in the appellant’s brief that the Public Service Commission “ is charged by law and by the contract in this case with the preparation and checking of plans for the construction of subways, and that in certain matters set forth in the contract and in the statute the engineer and his subordinates are specifically made the agents of the city for doing certain things mentioned therein. * * * ”
The contract itself was made by the Public Service Commission, in accordance with the provisions of the Rapid Transit Act. The Public Service Commission was the agent of the defendant, and the defendant contracted and agreed to furnish as required the necessary drawings. It failed in this, or, at least, it furnished them with such tardiness and in such a manner as to justify the finding of the jury, that the defendant’s default damaged the plaintiff.
The city, having contracted with the plaintiff that the engineer
The appellant seeks to avoid liability upon the ground that the Public Service Commission is a State department and is no part of the internal management of the city; that the engineer of the Public Service Commission is not a city official nor the general agent of the city for whose wrongful acts the city can be held liable. Nevertheless, the contract was made by the Public Service Commission, pursuant to law, in behalf of the city, and the city is bound by its terms. The contract provided that the amplified construction drawings would be furnished by a certain individual, namely, the engineer of the Public Service Commission. It was primarily the duty of the city, for which the construction work under the contract was to be performed, to furnish these drawings. By law and by the terms of the contract, the performance of that duty devolved upon the engineer of the Public Service Commission. The plaintiff had absolutely no control over the city nor over the engineer required to furnish the necessary drawings. It had the right to expect, however, that the party who was lawfully selected for that purpose should act with reasonable promptness and so as not to interfere with the plaintiff’s prosecution of the work. The city did not fulfill its obligation to the plaintiff in this respect. The engineer was named in the contract as the arbiter of the final construction plans, and when the engineer defaulted his default was the city’s default. It seems to me an absurd proposition that the city could avoid responsibility for the acts of the engineer of the Public Service Commission when it contracted that the engineer would act in a particular way. The action is purely for a breach of the provision of the contract entered into by the city with the plaintiff that a certain
The strongest evidence of the fact that the city became liable for the acts of the engineer of the Public Service Commission is to be drawn from the provisions of article 43 of the contract. That article provides that: “ If the Contractor shall claim compensation for any damage sustained by reason of the acts of the Commission, or its agents, he shall, within ten days after the sustaining of such damage, make a written statement of the nature of the damage sustained to the Engineer. * * * ” Here we find an admission of responsibility on the part of the city for the acts of the Public Service Commission, or its agents, and that, if timely presentation thereof is made, the contractor may assert his claim for compensation against the defendant city. It seems to me futile for the city, in view of said provision of the contract, to claim that it is not responsible for the conduct of the engineer.
The appellant cites several cases holding that the city cannot be held liable for the torts of those not connected with it or its internal management. I think none of these authorities are controlling against the plaintiff’s claim herein. The plaintiff’s claim is not based upon the tortious act of a third party, for which the city, of course, could not be held liable, but is asserted under the contract and by reason of the city’s breach thereof, in failing, as required, to furnish plaintiff with the amplified plans prepared by the engineer of the Public Service Commission. If the city can be held liable to the plaintiff for the payment of the contract price which the plaintiff was to receive for the work, it can just as surely be held to the performance of any other provision of the contract, and, in case of a breach thereof, is liable to plaintiff under the contract for any damage resulting from such breach. It may be that the engineer of the Public Service Commission
As to the award of the jury as damages for by-passing, I think the evidence fully supports the verdict. The contract, I think, unquestionably provided that by-passing was one of the steps which might necessarily be taken in the prosecution of the work, and provided proper compensation to the contractor therefor. The term “ by-passing ” is descriptive of the operation of furnishing temporary conduits for gas mains so as to avoid the necessity of cutting off the gas supply to users, pending the construction of the subway. So much of plaintiff’s claim as concerned section 1 of the work is set out in plaintiff’s third cause of action, and the by-passing claimed with reference to section 2 is alleged in the sixth cause of action. The circumstances under which by-passing became necessary were as follows: In constructing the subway the street under which it ran was excavated from the surface from curb to curb to a depth of about thirty feet. The width of the excavation from curb to curb was substantially sixty feet. After the excavation was made and while the work of installing the subway structure was in progress, the contractor was obliged to maintain a roadway for travel at the street surface on both sides of Fourth avenue, each roadway being, as hereinbefore stated, about sixteen feet in width and having a two-inch plank surface. This left an opening in the center twenty-eight feet in width. Under this temporary plank roadway, for a distance on each of the two sections, there ran a twenty-inch high-pressure cast-iron gas main and also under the decking there was a sixteen-inch cast-iron gas main. By means of these mains the residents of the locality were served with gas. The pipes constituting these mains were not screwed together, but were held together by means of molten lead. The gas companies notified the contractor that it was necessary to by-pass these mains during the progress of the work, as the mains were at places left suspended in the air, and the nature of the unions of the sections of the pipe was such that they might easily become disjointed, and the gas escape. In by-passing, the gas mains were temporarily killed and temporary overhead pipes were laid through which the gas was' conveyed during the time when the work was being prosecuted and until service through the original pipes could be safely resumed. The proof shows clearly
* It is the contention of the appellant upon this appeal that said by-passing was unnecessary and was not directed to be done by the engineer in charge. The appellant relies in this respect upon section No. 52 of the contract, which provides that wherever the excavations are decked, all gas pipes whose service cannot temporarily be dispensed with shall be by-passed, if directed by the engineer, temporary pipes to take their place being laid either upon or below the street or sidewalk surfaces. The engineer refused to direct the by-passing of said gas mains. Nevertheless, by article 10 of the contract it is provided that in order to construct the railroad it would be necessary to protect, support and maintain during construction all water mains, gas pipes, electric subways and other surface, subsurface and overhead structures, together with their necessary connections, as the same might be met with along the route, and to move, alter, readjust or rebuild water mains, gas pipes, etc. Said article 10 of the contract further provided as follows: “ All such work of every description, including under-pinning wherever necessary, of all buildings or structures of whatsoever nature, monuments, and surface and sub-surface railroads affected by or interfered with during the construction of the railroad, is a part of the work which is included in this contract and which the contractor agrees to perform for the price herein agreed upon.”
The contract particularly provided that the contractor should complete the entire work in the most workmanlike manner, and with the highest regard to the safety of life and property. The officials of the Kings County Lighting Company, owning and maintaining said conduits, wrote the plaintiff that the mains in question must be by-passed, calling attention to the danger to life and property in case this were hot done. Repeatedly letters to the same effect were written by the officials of the lighting company to the'contractor. The plaintiff’s chief engineer sought tq place the responsibility for directing the same upon the engineer
It would seem from the above-quoted portion of the engineer’s letter that he understood that a duty was upon the contractor to do whatever was necessary in the premises. The subsequent correspondence between the engineers shows conclusively that the Public Service Commission understood that said by-passing was to be accomplished, although the engineer did not expressly direct the same to be done. The contract itself, in article 11, in its schedule of unit prices, provided that the contractor should receive: For twelve-inch by-passing pipe, the sum of three dollars per lineal foot. It would seem, therefore, that the furnishing of this by-passing pipe for which the jury have allowed the contractor was a part of the work contemplated by the parties and necessarily done in the execution of the contract. While one section of the contract would seem to indicate that the by-passing was to be directed by the engineer, such section does not relieve the contractor from responsibility for by-passing the conduits when actually required. When the engineer refused to direct the by-passing of the gas pipes, the contractor was left to his own resources, and was called upon to determine ^whether he should leave the mains unprotected and in danger of being broken with resulting loss of life and property, or should adopt the other course, which prudence suggested. Unquestionably, from the correspondence the contractor was convinced that the by-passing was necessary. If the company’s cast-iron mains became disconnected air would
I think the allowance of interest upon this claim was entirely proper. The defendant was aware of the amount of pipe necessarily used in effecting such by-passing. Indeed, the figures upon which the jury based its verdict were furnished by the defendant’s engineers. The contract itself provided the unit price for the twelve-inch' pipe used in such by-passing. It was, therefore, at all times entirely within the power of the defendant to compute the amount due the contractor for such by-passing, and this being so, the plaintiff was entitled to interest upon its claim therefor. (Degnon-McLean Co. v. City Trust Co., 99 App. Div. 195; affd., 184 N. Y. 544; Sloan v. Baird, 162 id. 327; Sweeny v. City of New York, 173 id. 414.) In Sweeny v. City of New York (supra) the referee awarded interest upon the plaintiff’s claim. The Appellate Division disallowed the same (69 App. Div. 80), and the Court of Appeals reversed the Appellate Division and reinstated the interest.
I do not think there is any force in the appellant’s contention that the plaintiff cannot recover by reason of the fact that it sublet the construction of the subway to the firm of Carpenter & Boxley. As a matter of fact, the plaintiff employed Carpenter & Boxley to perform the work upon an agreement that Carpenter
The appellant also claims that the plaintiff’s recovery is barred by its failure to present its claims for damages in conformity with article 43 of the contract. The article mentioned requires the contractor, if it claims compensation for any damage sustained “ by reason of the acts of the Commission or its agents,” within ten days after sustaining such damage, to make a written statement of the nature thereof to the engineer, and that on or before the fifteenth of the month succeeding that in which any such damage shall have been sustained the contractor shall file with the engineer an itemized statement thereof, or otherwise forfeit its claim. The article expressly refers to damages sustained “ by reason of the acts of the Commission or its agents.” Strictly, the damages claimed by the plaintiff herein are not by reason of the acts of the Commission or its agents, but are by reason of the said engineer’s failure to act. Moreover, the damages involved in the delay claim were of a continuing nature, and unascertainable until the work was completed sometime in January, 1916. On January 12, 1916, the defendant was advised of the claim, and on January 31, 1916, an itemized statement thereof was rendered. It would have been a practical impossibility for the plaintiff to have stated the items of its damage each month it was delayed in the performance of its contract. Just what damage the plaintiff sustained by reason of the delay would be impossible of ascertainment
There is no basis whatever for the defendant’s claim that, the contract having provided a remedy to the contractor, in case the work was delayed, in the shape of an extension of time to complete the work, it was, therefore, not entitled to damages for delays.
I do not think there is any force in the appellant’s position that the request for and acceptance of extensions by the contractor to complete the work worked any waiver of damages by reason of delay. If the defendant violated its contract by the delay complained of, it could not complain that additional time was required for the performance of the work, and in asking such extension the contractor did not waive his right to damages resulting from the defendant’s wrongful acts.
The manner in which the court submitted the case to the jury, I think, was eminently fair. But a single exception was taken by the city to the charge of the court. Counsel for the plaintiff asked the court to charge as follows: “ I ask your Honor to chargé if in order to fairly and reasonably fulfill its obligations to the contractor with respect to the furnishing of steel drawings, it was necessary for the city to have proceeded with and advance the preparation of such steel drawings before the time for the signing of the contract, then it was the duty of the city so to do.”
To this request the court acceded, and counsel for the defense excepted. Manifestly, there was no error in such instruction. The contractor was allowed but twenty-four months to complete this gigantic work. Time was specified as of the essence of the contract. The city knew that only under the most favorable conditions could the contractor hope to complete the heavy task within the allotted time. The construction plans, from which the shop plans for the steel work were to be prepared, were to be furnished by the engineer of the Public Service Commission. The contractor took no part in their initiation. No reason is apparent why such construction plans could not have been prepared in advance. The Public Service Commission was as well aware of what plans were necessary before the contract was let as after. Knowing, as the engineer testified, that the preparation of such plans would require many months, reasonable prudence would have required advance work thereon, It is conceivable that the full1
In. submitting the question of delay to the jury the charge of the court was eminently fair. The court charged:
“ Whether or not the delay of the" engineer of the Public Service Commission to furnish the plans required to the plaintiff was due to the contractor’s manner and method of prosecuting the work is also a question which the jury must determine on the facts, and if the jury should find that the delay was due to the contractor’s method rather than the failure to receive the plans in sequence, then the plaintiff is not entitled to damages for delay in the performance of this contract.
“ Assuming that you find that the delay was due to the City’s omission to furnish the plans in sequence, that alone would not make out or establish the plaintiff’s claim for damages. It must also establish to your satisfaction by the preponderance of evidence that it was the delay of the City or its officials that actually caused the delay and that the damage was suffered only because of the delay and arose directly and proximately out of the City’s delay, to the contractor’s pecuniary damage, and, even when you so find you will have to go still further and determine what the amount of damage was and is.”
Such charge, it seems to me, was entirely correct, and within the rule laid down in Uvalde Asphalt Paving Co. v. City of New York (196 App. Div. 740).
The judgment and orders appealed from should be affirmed, with costs.
Judgment and orders reversed and a new trial ordered, with costs to' appellant to abide event. Settle order on notice.