DEFENDERS OF WILDLIFE; Center for Biological Diversity; Craig Miller, Petitioners, v. UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, Respondent, National Association of Home Builders; State of Arizona; Arizona Chamber of Commerce, Intervenors. Defenders of Wildlife; Center for Biological Diversity, Plaintiffs-Petitioners, v. Robert B. Flowers, Chief of Engineers and Commander, U.S. Army Corps of Engineers., Defendant-Respondent, Christine Todd Whitman, Administrator U.S. Environmental Protection Agency, Defendant-Respondent, Gale Norton; Steven Williams, Defendants-Respondents, Continental Reserve II, LLC, Defendant-Intervenor/Intervenor, HB Land Development Company; Stephen A. Owens, State of Arizona, ex-rel, Director Arizona Department of Environmental Quality; Grosvenor Holdings; National Association of Home Builders; Home Builders Association of Central Arizona; Southern Arizona Home Builders Association; Saguaro Ranch Investments LLC; Saguaro Ranch Development Corporation, Defendant-Intervenors/Intervenors.
Nos. 03-71439, 03-72894.
United States Court of Appeals, Ninth Circuit.
Filed Aug. 22, 2005.
Argued and Submitted Nov. 1, 2004.
Robert L. Gulley (argued), Thomas L. Sansonetti, Robert L. Gulley, John M. Lipshultz, Andrew Mergen, U.S. Department of Justice, Washington, D.C. (on the brief), for respondents Environmental Protection Agency and U.S. Fish and Wildlife Service.
James T. Skardon, Office of the Arizona Attorney General, Phoenix, AZ, for intervenor State of Arizona.
Russell S. Frye, Collier Shannon Scott, P.L.L.C., Washington, D.C., for intervenors Arizona Chamber of Commerce, et al.
Norman D. James, Esq. (argued), Norman D. James, Thomas R. Wilmoth, Fennemore Craig, Phoenix, AZ, for intervenors National Association of Home Builders, et al.
Before: REINHARDT, THOMPSON, and BERZON, Circuit Judges.
BERZON, Circuit Judge:
Under federal law, a state may take over the Clean Water Act pollution permitting program in its state from the federal Environmental Protection Agency (EPA) if it applies to do so and meets the applicable
The plaintiffs in this case challenge the EPA‘s transfer decision, particularly its reliance on the Biological Opinion‘s proposition regarding the EPA‘s limited authority. This case thus largely boils down to consideration of one fundamental issue: Does the Endangered Species Act authorize—indeed, require—the EPA to consider the impact on endangered and threatened species and their habitat when it decides whether to transfer water pollution permitting authority to state governments? For the reasons explained below, we hold that the EPA did have the authority to consider jeopardy to listed species in making the transfer decision, and erred in determining otherwise. For that reason among others, the EPA‘s decision was arbitrary and capricious. Accordingly, we grant the petition and remand to the EPA.
I. Background
A. The National Pollution Discharge Elimination System (NPDES)
The Clean Water Act (“the Act“), passed in 1972, established the National Pollution Discharge Elimination (“pollution permitting“) System. That System gave the EPA authority to issue permits for the discharge of pollutants into navigable waters. See
The state transfer provisions of
Once the EPA transfers a permitting program to a state government, the EPA Administrator maintains an oversight role to assure that the state follows Clean Water Act standards.
B. The Endangered Species Act
In 1973, one year after the enactment of the Clean Water Act, Congress passed the Endangered Species Act, “the most comprehensive legislation for the preservation of endangered species ever enacted by any nation.” Tenn. Valley Auth. v. Hill, 437 U.S. 153, 180, 98 S.Ct. 2279, 57 L.Ed.2d 117 (1978). The present case focuses on section 7 of the Endangered Species Act,
Section 7(a)(2) imposes substantive and procedural requirements on “each Federal agency” with regard to “any action authorized, funded, or carried out by such agency.”
Endangered Species Act regulations1 describe the consultation and action requirements imposed on agencies. Section 7‘s requirements apply “to all actions in which there is discretionary Federal involvement or control.”
A Biological Opinion must include a “summary of the information on which the opinion is based,” a “detailed discussion of the effects of the action on listed species or critical habitat,” and “[t]he Service‘s opinion on whether the action is likely to jeopardize the continued existence of a listed species or result in the destruction or adverse modification of critical habitat.”
The “effects of the action” include “direct and indirect effects ... together with the effects of other activities that are interrelated or interdependent with that action, that will be added to the environmental baseline[, which] includes the past and present impacts of all Federal, State, or private actions and other human activities in the action area.”
By its terms, section 7(a)(2) applies only to “federal agenc[ies],” not to state governmental bodies. Accordingly, the EPA‘s pollution permitting decisions are subject to section 7(a)(2), but state pollution permitting decisions are not.
Noting that the “EPA now consults with the [FWS and National Marine Fisheries Service] under section 7 of the [Endangered Species Act] on ... approval of State National Pollutant Discharge Elimination (NPDES) permitting programs” but recognizing that after transfer, section 7 will not apply to the state‘s permitting decisions, the EPA signed a Memorandum of Agreement with the FWS governing the two agencies’ involvement with transferred pollution permitting programs. See 66 Fed.Reg. 11,202, 11,202, 11,207 (Feb. 22, 2001). Asserting that the “EPA‘s oversight includes consideration of the impact of permitted discharges on waters and species that depend on those waters,” id. at 11,215, the Memorandum lists several procedures that the EPA and FWS will establish to ensure that they communicate federal endangered species concerns to state water pollution permitting agencies.2 Id. at 11,216. The Memorandum is not, however, binding on states. Id. at 11,206 (“[T]he MOA ... does not impose any requirements on States.“). Rather, the
C. The EPA‘s approval of Arizona‘s pollution permitting transfer application
The State of Arizona (Arizona) applied on January 14, 2002 for transfer of pollution permitting authority regarding Arizona waterways (except those on Indian land). 67 Fed.Reg. 49,916, 49,917 (Aug. 1, 2002). Under that proposal, the Arizona Department of Environmental Quality (ADEQ) was to be responsible for issuing water pollution permits. The EPA‘s regional office in San Francisco determined that the transfer could affect listed species in Arizona and so initiated formal section 7 consultation with FWS. Announcing this decision, the EPA stated that “[s]ection 7(a)(2) of the [Endangered Species Act] places a statutory requirement (separate and distinct from [
During the course of the consultation, FWS field office staff in Arizona expressed serious reservations about the proposed transfer. FWS staff noted that section 7 consultations regarding past pollution permits in Arizona had led to mitigating measures to protect species’ critical habitat, and feared that, without such mandatory consultation, Arizona would issue permits without mitigating measures. As a result, there could be harm to certain listed species and habitat, particularly the southwestern willow flycatcher, Pima pineapple cactus, Huachuca water umbel, cactus ferruginous pygmy owl,4 “and perhaps other species.” The staff concluded “that the transfer of this program from EPA to the State causes the loss of protections to species resulting from the section 7 process, and the impact of this loss must be taken into account in the effects analysis in the biological opinion.” In response, EPA
To resolve this disagreement, staff of the two agencies developed an “Interagency Elevation Document,” summarizing their respective opinions. Pursuant to the Memorandum of Agreement, this document transferred authority over the Biological Opinion to the Director of FWS, the Director of the National Marine Fisheries Service, and the Deputy Assistant Administrator of Water at the EPA. See 66 Fed.Reg. 11,202, 11,209 (Feb. 22, 2001).
After the consultation at the national level between the EPA and FWS, the Field Supervisor of the Arizona Ecological Services Field Office of the FWS issued a Biological Opinion recommending approval of the transfer of permitting authority to Arizona. Noting the loss of section 7 consultation, the Biological Opinion recognized that, after the transfer, no federal agency would have the legal authority to consult with developers concerning the potential impact on listed species of any pollution permits. Such consultation had lead to measures protecting listed species, including the Pima pineapple cactus, razorback sucker, Gila topminnow, southwestern willow flycatcher, and cactus ferruginous pygmy owl. Although Arizona could voluntarily consult with FWS regarding pollution permits, neither the EPA nor FWS could require Arizona to act on behalf of listed species.
After recognizing this impact of the transfer of permitting authority, the Biological Opinion concluded that the loss of any conservation benefit is not caused by EPA‘s decision to approve the State of Arizona‘s program. Rather, the absence of the section 7 process that exists with respect to Federal [Clean Water Act] permits reflects Congress’ decision to grant States the right to administer these programs under state law provided the State‘s program meets the requirements of 402(b) of the Clean Water Act.
The Biological Opinion goes on to conclude:
While reviewing this above referenced approval, the FWS has spent considerable time analyzing direct and indirect effects. In the course of this analysis, our field office staff biologists have expressed concerns that the approval will result in loss of section 7 consultation-related conservation benefits. We have stated our belief that the loss of section 7 conservation benefits is an indirect effect of the authorization. Furthermore, we have stated that this loss of conservation benefits will appreciably reduce the conservation status of the cactus ferruginous pygmyowl and the Pima pineapple cactus. Notwithstanding this, our final opinion is that the loss of section 7-related conservation benefits, which would otherwise be provided by section 7 consultations, is not an indirect effect of the authorization action. In changing from a Federal permitting program to a State permitting program, the permit-related section 7 processes for consultation will no longer apply. Essentially, there will be no substantive change in the permit program, but there will be a reduction in the number of mechanisms available to both of our agencies to protect federally-listed species and critical habitat in Arizona. We believe that the assumption of the program by the State of Arizona will not
cause development, and concur that EPA‘s [Clean Water Act]-mandated approval of the program has only an attenuated causal link to the reduction in Federal [Endangered Species Act] conservation responsibilities.5
As an alternative to this lack-of-causation analysis, the Biological Opinion stated that other federal and state laws would sufficiently protect endangered species, so that transfer of permitting authority would not likely jeopardize such species or their critical habitat. These other laws included section 9 of the Endangered Species Act,
Independently of the Biological Opinion, an official at the Arizona Game and Fish Department6 indicated that his department had “worked cooperatively with ADEQ” when reviewing past water pollution permit applications and “look[ed] forward to continuing this level of cooperation between our agencies.” Noting the EPA-FWS Memorandum of Agreement, the official asserted that “[t]his agreement will serve as a guideline for EPA, FWS, and the State of Arizona to ensure that NPDES permits will not negatively impact endangered and threatened species.” The EPA‘s response to the Game and Fish Department official‘s statement was: “EPA appreciates the commenter‘s support. As with all comments submitted, we have considered these comments in making our final determination on the application.”
FWS staff had earlier suggested the development of a formal memorandum of understanding with ADEQ or the Arizona State Lands Department, but did not mention the Game and Fish Department. No such memorandum of understanding was ever signed, and no official from either ADEQ or the State Lands Department submitted a letter similar to the Game and Fish Department letter.
The EPA approved the permitting authority transfer two days after the FWS issued the Biological Opinion, see 67 Fed.Reg. 79,629 (Dec. 30, 2002), noting its belief that the Biological Opinion “appropriately considered all relevant information regarding the effects of the approval.” The Arizona Department of Environmental Quality (ADEQ) currently operates the program, issuing permits for water pollution. See ADEQ: Permits, at http://www.azdeq.gov/environ/water/permits/index.html (last visited July 5, 2005).
Petitioners, Defenders of Wildlife, the Center for Biological Diversity, and Craig Miller, a resident of Pima County, Arizona (collectively, Defenders) challenge the pol-
Defenders also filed an Endangered Species Act and Administrative Procedure Act suit in district court in Arizona alleging, among other claims, that the Biological Opinion supporting the pollution permitting transfer does not comply with Endangered Species Act standards. The district court held that this court has exclusive jurisdiction over the Biological Opinion challenge pursuant to
II. Jurisdiction & Standing
Before proceeding to the merits, we must satisfy ourselves that we have subject-matter jurisdiction over this case and that petitioners have standing to raise their claims. See B.C. v. Plumas Unified Sch. Dist., 192 F.3d 1260, 1264 (9th Cir. 1999). The Chamber contends this court lacks jurisdiction to hear Defenders’ challenge to the Biological Opinion, and the Home Builders maintain that Defenders do not have standing to bring this action. Neither argument is convincing.
A. Subject-Matter Jurisdiction
“[A]ny interested person” may seek judicial review of the EPA Administrator‘s pollution permitting or state transfer decisions in the circuit court in which the person resides, so long as that circuit is directly affected by the Administrator‘s action.
We disagree. The Supreme Court has noted that biological opinions typically have a “virtually determinative effect” on the ultimate agency action. Bennett v. Spear, 520 U.S. 154, 170, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997); see also id. at 169, 117 S.Ct. 1154 (noting that a Biological Opinion “in reality ... has a powerful coercive effect on the action agency” with the potential to “alter[] the legal regime to which the action agency is subject“). It would be anomalous to review the ultimate agency “determination” while ignoring the reasoning contained in a biological opinion “virtually determinative” of that action.
The actual sequence of events in this instance is consistent with the Supreme Court‘s observations in Bennett regarding the impact of a biological opinion on an agency‘s final decision. The EPA Administrator‘s decisionmaking process before approving Arizona‘s permitting transfer application included section 7 consultation
The EPA, as part of the statutorily mandated consultation process, approved of and relied upon the Biological Opinion when considering Arizona‘s transfer application. Evaluating the Opinion‘s evidentiary and analytic basis is thus integral to reviewing the EPA‘s final decision.7
We conclude that we have jurisdiction to consider the adequacy of both the section 7 consultation and the Biological Opinion that resulted from it while reviewing the EPA‘s final decision.
B. Standing
Petitioners who “allege [1] personal injury [2] fairly traceable to the defendant‘s allegedly unlawful conduct and [3] likely to be redressed by the requested relief” establish Article III standing. Allen v. Wright, 468 U.S. 737, 751, 104 S.Ct. 3315, 82 L.Ed.2d 556 (1984). As Defenders’ members meet this three-part test, Defenders has organizational standing to represent their interests.
Several Defenders’ members reside in Arizona and photograph and observe in Arizona various named, listed species—such as the cactus ferruginous pygmy owl, Huachuca water umbel, and the other species noted in Part I.C, supra and hike and camp in these species’ various habitats. These members do so regularly and plan to continue doing so in the future, because, among other reasons, these activities bring them recreational, aesthetic, and spiritual fulfillment. The members’ activities occur on and near land—such as the upper San Pedro River region, the Sonoran Desert near Saguaro National Park and Tortolita Mountains Park, and the Verde River region—where significant commercial and residential development is taking place, development that depends on water pollution permits. The members assert, consistently with the Biological Opinion, that section 7 consultation has in the past led to mitigation measures by real estate developers in these areas and has thereby protected listed species and their habitat. They further assert that the loss of section 7 consultation would mean that developers of future projects would not engage in such mitigation measures and that listed species, and the members’ interest in their activities involving them, would thereby be harmed.
The Home Builders argue that alleging harm throughout the state of Arizona cannot establish standing, because the state encompasses too large an area to permit a sufficiently specific injury-in-fact allegation. The Defenders’ members who filed declarations, however, mention specific subareas within the state where they engage in activities related to particular listed species and where development is occurring. Our cases require no greater precision. Res. Ltd., Inc. v. Robertson, 35 F.3d 1300, 1303 (9th Cir.1993); see also Kootenai Tribe, 313 F.3d at 1110 (finding standing where party alleged harm to 58.5 million acres of land). Moreover, in light of the statewide impact of the EPA‘s transfer decision, alleging an injury-in-fact covering large areas within the state simply reflects the relatively broad nature of the potential harm.
The alleged injuries are fairly traceable to the EPA‘s pollution permitting transfer decision. As alleged by Defenders, that decision will remove water pollution permitting decisions from the significant protections provided by section 7.
Finally, the alleged injuries would be redressable by a court order vacating or mitigating the EPA‘s transfer decision. The protections accorded by the Endangered Species Act would then come back into operation.
Additionally, section 7(a)(2) of the Endangered Species Act contains both substantive and procedural requirements, and the plaintiffs in this case have alleged violations of both requirements. They thus have alleged, in addition to substantive noncompliance, “procedural” harms, as described in Lujan and subsequent cases—here, lack of adequate consultation between the EPA and the FWS, including reliance on a legally improper Biological Opinion.
Reliance on procedural harms alters a plaintiff‘s burden on the last two prongs of the Article III standing test. See Lujan, 504 U.S. at 572 n. 7, 112 S.Ct. 2130. To establish standing by alleging procedural harm, the members must show only that they have a procedural right that, if exercised, could protect their concrete interests and that those interests fall within the zone of interests protected by the statute at issue. See Pub. Citizen v. Dep‘t of Transp., 316 F.3d 1002, 1015 (9th Cir.2003), rev‘d on other grounds, 541 U.S. 752, 124 S.Ct. 2204, 159 L.Ed.2d 60 (2004); Tyler v. Cuomo, 236 F.3d 1124, 1136 (9th Cir.2000); Churchill County v. Babbitt, 150 F.3d 1072, 1077 (9th Cir.1998), amended by 158 F.3d 491 (9th Cir.1998).
The members have met these procedural harm requirements. They have, first, established a reasonable probability that the
An association has standing to sue on behalf of its members who have individual standing if “the interests at stake are germane to the organization‘s purpose, and neither the claim asserted nor the relief requested requires the participation of individual members in the lawsuit.” Laidlaw, 528 U.S. at 181, 120 S.Ct. 693. The interests at stake—the protection of endangered species—plainly relate to Defenders’ mission. Nor does this lawsuit require the active involvement of individu-
Accordingly, we hold that Defenders has standing to challenge the EPA‘s pollution permitting transfer decision. See Defenders of Wildlife v. Flowers, 414 F.3d 1066 (9th Cir.2005) (holding that Defenders has standing to challenge particular construction permits in Arizona because of “their members’ interest” in species that might live where construction would occur).
III. The Merits
A. Standard of Review
Under the Endangered Species Act, each agency has an obligation to “insure” that any action it takes is “not likely to jeopardize” listed species or their critical habitats. See
trary and capricious review to
An agency decision will survive arbitrary and capricious review if it is rational, based on consideration of the relevant factors and within the scope of the authority delegated to the agency by the statute.... Normally, an agency rule would be arbitrary and capricious if the agency has relied on factors which Congress had not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise.
Motor Vehicle Mfrs. Ass‘n v. State Farm Mutual Auto. Ins. Co., 463 U.S. 29, 42-43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (citations omitted). Agency decisions may not, of course, be inconsistent with the governing statute.
Defenders allege, in particular, that the EPA‘s reliance on the Biological Opinion was arbitrary and capricious, as the Biological Opinion is itself invalid. See Res. Ltd., 35 F.3d at 1304 (holding that an action agency may not arbitrarily and ca-
Applying this test, we first examine the consistency of the EPA‘s reasoning. Next, we examine the Biological Opinion, including its legal conclusion regarding the effects of the transfer decision on listed species and their habitat. We then review the other information relied on by the EPA.
B. Coherent reasoning?
As an initial matter, the EPA‘s approval of Arizona‘s transfer application cannot survive arbitrary and capricious review because the EPA relied during the administrative proceedings on legally contradictory positions regarding its section 7 obligations. Its reasoning was therefore “internally inconsistent and inadequately explained.” Gen. Chem. Corp., 817 F.2d at 857.
The EPA definitively stated several times during the decisionmaking process, including when announcing its final decision, that section 7 requires consultation regarding the effect of a permitting transfer on listed species. The agency so stated when announcing its Memorandum of Agreement with the FWS, see 66 Fed.Reg.
Also, before deciding that consultation was necessary, the EPA first determined that transferring pollution permitting authority to Arizona “may affect” listed species and their critical habitat. See
Despite the lucidity and consistency of its position on the consultation point in the administrative proceedings, in litigation the EPA‘s lawyers have taken varying stances on the same issue. Before the Fifth Circuit, the EPA “suggest[ed]” that section 7 compelled consultation regarding pollution permitting transfers and, when necessary to protect species, allowed conditioning such transfers on formal agreements requiring states to follow section 7 procedures when issuing permits. Am. Forest & Paper Ass‘n v. EPA, 137 F.3d 291, 297 (5th Cir.1998). The Fifth Circuit rejected the latter position and did not address the former. Id. at 298 & n. 6.
The EPA‘s brief in this case states that American Forest “supports a finding that EPA lacks” authority to protect endangered species when considering pollution permitting approvals. The same brief, however, maintains that we need not decide the question because the agency did not rely on this position in its decision in this case. At oral argument, the EPA declined to take a position as to whether it has an obligation under section 7(a)(2) to consult with FWS with regard to permitting transfer decisions—even though, during the decisionmaking process, the agency unequivocally stated several times that it does have such an obligation.
The EPA‘s post-decision equivocation cannot have any impact on our consideration of the validity of the transfer decision. We must review the EPA‘s actions based on the “grounds ... upon which the record discloses that its action was based.” SEC v. Chenery Corp. (Chenery I), 318 U.S. 80, 87, 63 S.Ct. 454, 87 L.Ed. 626 (1943); see also Gifford Pinchot Task Force v. U.S. FWS, 378 F.3d 1059, 1072 n. 9 (9th Cir.2004). The record shows unequivocally that the EPA based the action under review in this case on its belief that section 7 required consultation. We must judge its reasoning taking that position into account.
Doing so, we conclude that the obligation to consult—which, under the regulations, applies only to federal agency actions that “may affect” listed species,
Section 7(a)(2) makes no legal distinction between the trigger for its requirement that agencies consult with FWS and the trigger for its requirement that agencies shape their actions so as not to jeopardize endangered species.10 Instead, in one, integrated provision, the statute provides that agencies “shall, in consultation with and with the assistance of the [FWS], insure that any action authorized, funded, or carried out by such agency ... is not likely to jeopardize the continued existence of any endangered species or threatened species or result in the destruction or adverse modification of [critical] habitat of such species....” An agency‘s obligation to consult is thus in aid of its obligation to shape its own actions so as not to jeopard-
ize listed species, not independent of it. Both the consultation obligation and the obligation to “insure” against jeopardizing listed species are triggered by “any action authorized, funded, or carried out by such agency,” and both apply if such an “action” is under consideration.
This being the case, the two propositions that underlie the EPA‘s action—that (1) it must, under the Endangered Species Act, consult concerning transfers of Clean Water Act permitting authority, but (2) it is not permitted, as a matter of law, to take into account the impact on listed species in making the transfer decision—cannot both be true. Because the agency‘s decisionmaking was based on contradictory views of the same words in the same statutory provision, the ultimate decision was not the result of reasoned decisionmaking.
Additionally, the third prong of the Biological Opinion‘s reasoning—that it is private development, not the EPA‘s transfer decision, that would cause any impact on listed species—suffers from an independent lack of plausibility. Events can, of course, have more than one cause. Events can be caused by several actions in a “but-for” causal chain. If any one of the necessary actions does not take place, the ultimate event does not occur. See, e.g., Olympic Airways v. Husain, 540 U.S. 644, 653, 124 S.Ct. 1221, 157 L.Ed.2d 1146 (2004) (“[T]here are often multiple interrelated factual events that combine to cause any given injury.“). Obviously, without private decisions to construct new developments, there will be no Clean Water Act construction permits and no impact from
For these reasons, the transfer decision cannot stand. We must remand to the agency for a plausible explanation of its decision, based on a single, coherent interpretation of the statute.
C. Statutory power to protect species?
Even viewed in isolation, the first explanation for the EPA‘s no impact conclusion—that the loss of section 7 consultation was not an effect of its transfer decision because the agency had no authority to base its transfer decision on the loss of consultation—fares no better.
Under the statutory regime, the statutory obligation is to “insure” against likely jeopardy of listed species. The two critical factors triggering this obligation are (1) that the “action” be one for which the agency can fairly be ascribed responsibility, namely, an action “authorized, funded or carried out” by the agency; and (2) that there is the requisite nexus to an impact on listed species, namely, a direct or indirect effect “likely to jeopardize the continued existence of any endangered species or
The question in Public Citizen was whether DOT was required under NEPA to develop an environmental impact statement with regard to the pollution caused by the entry of Mexican trucks onto United States highways under the North American Free Trade Agreement. The Court held “that where an agency has no ability to prevent a certain effect due to its limited statutory authority over the relevant actions, the agency cannot be considered a legally relevant ‘cause’ of the effect.” Pub. Citizen, 541 U.S. at 770, 124 S.Ct. 2204 (emphasis added); see also id. at 767, 124 S.Ct. 2204 (analogizing “cause” inquiry for purpose of defining “indirect effects” to proximate cause inquiry in tort law).
Given the similarity in the applicable regulations, we adopt the Public Citizen standard for purposes of determining the likely effects of agency action under section 7(a)(2) of the Endangered Species Act. Accordingly, deciding whether the Biological Opinion followed Endangered Species Act regulations defining “indirect effects” requires us to determine whether the EPA can consider and act upon the loss of section 7 consultation benefits in deciding whether to transfer pollution permitting authority to Arizona. If so, then the EPA‘s transfer decision can be a cause of the loss of section 7 consultation benefits; the loss of those benefits should have been included in the Biological Opinion as an indirect effect of the potential transfer decision; and the loss of those benefits should have been considered and acted upon by the EPA.
2. “Insure that any action ... is not likely to jeopardize the continued existence of any [listed] species”
Authority over the loss of section 7(a)(2) consultation could be grounded in either the Clean Water Act or the Endangered Species Act. The former option is not presented here,11 so we focus on whether the obligation in section 7(a)(2) to “insure” against jeopardizing listed species empowers the EPA to make decisions to preserve listed species and their habitat even if the Clean Water Act does not so specify. If so, then the EPA has the authority—in-deed, because section 7(a)(2) speaks in mandatory terms, the duty—to deny a pollution permitting transfer application that meets Clean Water Act standards but would jeopardize protected species.
The language in section 7(a)(2) providing that each federal agency “shall ... insure that any action authorized, funded or carried out by such agency”12 will not jeopardize listed species or their critical habitat is addressed to each agency, without exception. Our question is: what does it require each agency to do?
The ordinary meaning of “insure” as used in this context requires agencies to take action, as dictionary definitions make clear. To “insure” is “[t]o make (a person) sure (of a thing)” and (“[t]o make certain, to secure, to guarantee (some thing, event, etc.)“).13 VII THE OXFORD ENGLISH
The Supreme Court‘s seminal section 7 case, Tennessee Valley Authority v. Hill, 437 U.S. 153, 180, 98 S.Ct. 2279, 57 L.Ed.2d 117 (1978), confirms this textual interpretation:
One would be hard pressed to find a statutory provision whose terms were any plainer than those in § 7 of the Endangered Species Act. Its very words affirmatively command all federal agencies ‘to insure that actions authorized, funded, or carried out by them do not jeopardize the continued existence’ of an endangered species or ‘result in the destruction or modification of habitat of such species....’ This language admits of no exception.
Id. at 173, 98 S.Ct. 2279 (first alteration added, other alterations in original) (citation omitted).14 An “affirmative command” by a superior authority—here, Congress—ordinarily carries with it both the obligation and the authority to obey that command. For example, despite policy arguments in favor of continuing construction of the dam, the Court in Hill relied on Congress‘s use of “the plainest of words” and section 7‘s equally plain legislative history, id. at 194, 98 S.Ct. 2279, to hold that further construction was in “irreconcilable conflict” with section 7. Id. at 193, 98 S.Ct. 2279; see also id. at 184, 98 S.Ct. 2279 (“The plain intent of Congress in enacting this statute was to halt and reverse the trend toward species extinction, whatever the cost.“).
Hill‘s analysis of the legislative history of the Endangered Species Act confirms that the authority conferred on agencies to protect listed species goes beyond that conferred by agencies’ own governing statutes. Hill noted that earlier endangered species legislation, as well as earlier versions of the bills that became the present Endangered Species Act, included the qualifier “insofar as is practicable and consis-
Another aspect of the statute‘s structure and history, not directly at issue in Hill, bolsters the conclusion that section 7 includes an affirmative grant of authority to attend to protection of listed species within agencies’ authority when they take actions covered by section 7(a)(2). Section 7(a)(1) of the Endangered Species Act directs agencies to “utilize their authorities in furtherance of the purposes of this chapter by carrying out programs for the conservation of [listed] species.” 16 U.S.C.
The House Report indicates that this distinction between the two sections was, as one would expect, deliberate. The Report noted the requirement of present section 7(a)(2) as imposing a “further require[ment]” beyond that of section 7(a)(1).15 See H.R.Rep. No. 93-412, at 14 (1973), reprinted in 1 CONGRESSIONAL RESEARCH SERVICE, A LEGISLATIVE HISTORY OF THE ENDANGERED SPECIES ACT OF 1973, AS AMENDED IN 1976, 1977, 1978, 1979, AND 1980, at 153 (1982)[(hereinafter LEGISLATIVE HISTORY] (emphasis added). The contrasting language of the two sections indicates that the “further requirement” imposed by section 7(a)(2) turns on the distinction between using existing authority to promote conservation of species and conferring an additional, do-no-harm obligation—and reciprocal authority—applicable when the agency‘s own actions could cause harm to endangered species.
That Congress so provided is confirmed by Representative Dingell‘s statement concerning the final bill, relied upon by the Supreme Court as an authoritative statement of section 7‘s intent:16 ” ‘[T]he agencies of Government can no longer plead that they can do nothing about [harm to threatened or endangered species]. They can, and they must. The law is clear. ’ ” Hill, 437 U.S. at 184, 98 S.Ct. 2279 (quoting 119 Cong. Rec. 42913 (1973), emphasis in Hill).17
The limited exemption created by the 1978 amendments and contained in sections 7(g) and (h) has no direct application here, as the EPA did not apply for it. Its terms, however, serve to confirm that the interpretation of the “insure” requirement in Hill remains controlling.
Sections 7(g) and (h) focus on practical concerns, not legal constraints on agency power to protect species. To obtain an exemption, an agency must show that “there are no reasonable and prudent alternatives to the agency action,” the benefits of the action “clearly outweigh the benefits of alternative course of action consistent with conserving the species or its critical habitat, and such action is in the public interest,” and the action has regional or national significance.
That the 1978 amendments reiterated rather than retreated from Hill‘s underlying understanding of the
We conclude that the obligation of each agency to “insure” that its covered actions are not likely to jeopardize listed species is an obligation in addition to those created by the agencies’ own governing statute. The next question we must decide is whether the EPA‘s transfer decision is the kind of agency action to which that obligation applies.
3. Actions “authorized, funded, or carried out” by an agency
As we interpret
The regulatory provision that delineates the actions covered by
Arizona and the Chamber note that the
Second, cases applying
Our
In contrast, we have held that
In sum, we understand our cases applying the “discretionary . . . involvement” regulation to interpret that regulation to be coterminous with the statutory phrase limiting
Like the agencies in Washington Toxics, Pacific Rivers and Houston but not the other
4. Other Circuits
Although Washington Toxics and the cases are fully consistent with our analysis, this case is the first in which we have specifically addressed the question wheth
The First Circuit, writing a year after the Supreme Court decided Hill, noted that the
A decade later, the Eighth Circuit echoed Conservation Law Foundation, writing that “[e]ven though a federal agency may be acting under a different statute, that agency must still comply with the [Endangered Species Act].” Defenders of Wildlife, 882 F.2d at 1299; John W. Steiger, The Consultation Provision of Section 7(a)(2) of the Endangered Species Act and Its Application to Delegable Federal Programs, 21 ECOLOGY L.Q. 243, 274 (1994) (describing as “well established” the proposition that ”
The D.C. Circuit has indicated that the
Platte River did not recognize the obvious differences between
The Fifth Circuit relied on Platte River to hold that
In sum, the better reasoned out-of-circuit authority, as well as our own precedent, supports our conclusion that
5. Summary
We hold that approving Arizona‘s pollution permitting transfer application was an agency action “authorized” by the EPA, thus triggering both
We therefore conclude that, under Public Citizen, the EPA‘s transfer decision will cause whatever harm may flow from the loss of section 7 consultation on the many projects subject to a water pollution permit, and that harm constitutes an indirect effect of the transfer.20 The Biological Opinion, which ignored this effect while recognizing that section 7 consultations concerning pollution permitting permits have saved species’ critical habitat in the past, was therefore deficient. The EPA erred by relying on this fatally deficient Biological Opinion.
Having concluded that the Biological Opinion upon which the EPA relied was flawed in its basic legal premise,21 we now consider whether that Opinion‘s other analyses, or any analysis outside the Biological Opinion that the EPA relied upon, saves the validity of the EPA‘s transfer decision.
1. No “detailed discussion” of effects on all listed species
Consistent with its underlying legal analysis, the Biological Opinion never considered in any detail the likely real-world impact of the transfer decision on listed species in Arizona. The failure to conduct that inquiry fatally infects the Opinion‘s truncated alternative causation analysis.
Defending the Biological Opinion, the Home Builders argue that the “effects of the action“—which the Biological Opinion must consider under
It is understandable that EPA has not embraced the Home Builders’ analysis. According to the Home Builders, the section 7 consultations and EPA-requested mitigation undertaken in the past regarding federal pollution permits were improper, because the EPA took into account as indirect effects the long-run impact of development on terrestrial upland species. This argument is based on a flawed reading of
A Biological Opinion must discuss the effects of an agency action,
The Home Builders also cite cases relating to portions of development projects that “could exist independently of each other.” Wetlands Action Network v. U.S. Army Corps of Eng‘rs, 222 F.3d 1105, 1116 (9th Cir. 2000). Seemingly, the Home Builders argue that, because section 7 does not require consultation or mitigation with regard to a development project truly independent of the one covered by a permit, section 7 also does not cover development projects that are dependent on the permit in question. On the contrary, section 7 covers development projects “interrelated or interdependent with” the discharge permitted by a permit, and therefore covers in many instances the development that will take place if construction-connected stormwater discharge is permitted.
Neither the FWS nor the EPA makes any argument that justifies the Biological Opinion‘s failure to analyze, in detail, the likely effect of such future development projects fostered by pollution permits on specific species. This failure is especially telling in light of the benefits of section 7 consultation regarding water pollution permits. That consultation, as the Biological Opinion noted, has led various developers to alter their development plans, preserving thousands of acres of listed species’ habitat. For example, such mitigation has “maintain[ed] dispersal and movement corridors” for the pygmy owl. FWS staff had noted that the absence of section 7 consultation could harm specific species, yet the Biological Opinion did not spell out those concerns in any detail.
By not considering the transfer‘s specific impact on listed species—at least those as to which specific concerns had been expressed—the Biological Opinion “failed to consider an important aspect” of the transfer decision. Motor Vehicle Mfrs. Ass‘n v. State Farm Mutual Auto. Ins. Co., 463 U.S. 29, 43 (1983).
2. Alternatives to section 7 consultation
The Biological Opinion notes state and federal endangered species protections that exist without section 7 consultation, including: (1) the Memorandum of Agreement between the EPA and FWS, EPA oversight over ADEQ; (2) the
a. Memorandum of Agreement
The Memorandum of Agreement provides the closest substitute for the provisions of section 7. It cannot, however, replace section 7, because it does not grant the federal government any authority to require Arizona to engage in the kind of consultation and mitigation measures EPA had conducted before the transfer.
Under the Memorandum, the EPA will review ADEQ permits and identify those that “may raise issues regarding” listed species. 66 Fed.Reg. 11,202, 11,216 (Feb. 22, 2001). For projects posing a significant threat to listed species, the FWS “will work with the State . . . to reduce the detrimental effects stemming from the permit.” Id. The FWS, however, has no
The Memorandum also provides that the “EPA will use the full extent of its
In sum, the Memorandum calls for the EPA and the FWS to discuss listed species matters with ADEQ, but relies on ADEQ voluntarily to cooperate with those federal agencies. We assume that ADEQ will consider any listed species issues raised in good faith. Nothing in the record, however, indicates that ADEQ even has authority under state law to require permit applicants to protect listed species. Section 7 thus provides protection for species that reliance on purely voluntary action by the state cannot supply.
b. EPA oversight
For similar reasons, EPA oversight under
c. Endangered Species Act anti-take provisions
The
Sections 9 and 10 are important provisions, but they are not substitutes for section 7 coverage. Section 7 covers any federal agency action that could threaten species or their critical habitat. While the anti-take provisions prohibit “[e]liminating a threatened species’ habitat,” Envtl. Prot. Info. Ctr., 255 F.3d at 1075, or “significant . . . modification or degradation where it actually kills or injures wildlife,”
On this record, there is no indication that section 9 is or will be enforced meaningfully enough to provide a sufficient substitute for section 7. The record reflects no instances in which FWS has initiated a section 9 enforcement action with regard to listed species in Arizona. Additionally, FWS staff stated in the Interagency Elevation Document that they did “not believe that section 9 enforcement is an acceptable substitute for section 7 consultation.” This opinion reflected staff concerns, expressed in internal emails, that section 9 is ill-suited to protect species such as the pygmy owl, whose numbers are so low that section 9 enforcement may come too late to prevent extinction. The Biological Opinion contains no indication the FWS will increase section 9 enforcement nor any other analysis alleviating FWS staff concerns. The absence of record evidence of section 9 enforcement is confirmed by our own research, which reveals public notices regarding only two applications for incidental take permits for projects occurring in Arizona since January 1, 2001. See 69 Fed.Reg. 75,556 (Dec. 17, 2004); 69 Fed.Reg. 15,362 (Mar. 25, 2004). Compared to the large number of construction projects in the state, this low number suggests that developers do not feel that section 9 enforcement is sufficiently likely for them to apply for section 10 permits.
d. Arizona state law
The Biological Opinion notes one Arizona law that prohibits the taking of “native plants“—which, the Opinion notes, includes endangered or threatened plants—from any land within the state without following certain procedures. See
The Arizona statute, however, is not an adequate substitute for
In sum, the Biological Opinion fails to provide a reasoned explanation concerning why Arizona‘s native plant law adequately substitutes for section 7, even for plants. As it obviously does not do so for animals,
3. The EPA‘s reliance on the Biological Opinion
The EPA had an independent duty under
When considering challenges to agency actions based on factual objections to the Biological Opinion, however, we have held that an agency can satisfy the arbitrary and capricious standard of review even if it relies on an “admittedly weak” Biological Opinion, if there is no “information the Service did not take into account which challenges the[biological] opinion‘s conclusions.” Id.; see also Stop H-3 Ass‘n v. Dole, 740 F.2d 1442, 1460 (9th Cir. 1984). This holding is based on the notion that action agencies should be able to rely on the expert judgments that underlie most Biological Opinions. See id. (twice noting reasonableness of action agency‘s reliance on “the expert agency“) (emphasis added). Here, however, the Biological Opinion‘s flaws are legal in nature. Discerning them requires no technical or scientific expertise. The EPA should have understood the legal errors of the Biological Opinion‘s analysis. Its failure to do so led to an action based on reasoning “not in accordance with law” and is thus arbitrary and capricious.
Even applying the Pyramid Lake standard, the EPA acted arbitrarily and capriciously. Information not considered by the Biological Opinion that challenges its conclusion includes FWS staff members’ articulated, specific concerns about the impact of the loss of section 7 consultation, supported by information regarding the effect of past section 7 consultations.
The EPA notes that it relied on two pieces of evidence supporting its conclusion beyond that contained in the Biological Opinion and argues that consideration of this evidence provided the reasoned consideration that the arbitrary and capricious standard requires.25
The first such evidence is the EPA‘S own Biological Evaluation. This report focused largely on
The second piece of evidence on which the EPA relies is an “assurance[] from the Arizona Game and Fish Department . . . that Federally-listed species would not suffer” from the lack of section 7 consultations. This document is from an Arizona official of a state department that is not the one that will issue
There is no indication that Arizona would be bound by this letter. The ADEQ, the agency primarily responsible for implementing Arizona‘s pollution permitting authority, has not subscribed to its assurances. Nor does the letter writer explain by what authority Arizona will “ensure that . . . permits will not negatively impact endangered and threatened species,” or indicate that his agency has any authority to do so, let alone authority as broad as the protections mandated by the
In the abstract, voluntary compliance by state agencies willing to follow FWS recommendations to the same extent as would the EPA might substitute for section 7 coverage. The EPA, however, could not so conclude without first analyzing the likelihood that all relevant Arizona agencies can and would live up to the Game and Fish Department‘s promises, as well as considering the effectiveness of federal oversight if Arizona agencies fail to live up to any such promises.
Given its serious faults, the independent evidence on which EPA relies cannot fill in the crucial gaps in the Biological Opinion. Neither the Biological Opinion nor the EPA, consequently, adequately considered indirect effects of the transfer. The EPA thus “entirely failed to consider an important aspect of the problem.” State Farm, 463 U.S. at 43. Because neither the Biological Opinion nor the EPA examined all relevant data, the EPA‘s transfer decision was arbitrary and capricious.
4. Summary
The EPA‘s most serious errors were (1) its failure to understand its own authority under
IV. Remedy
Typically, when an agency violates the
We have carefully considered whether equitable considerations warrant allowing Arizona to maintain its authority over pollution permitting decisions while the EPA “follows the necessary procedures,” beginning with consultations with the FWS based on legal understandings consistent with this opinion. Arizona has undoubtedly expended significant funds to obtain and implement pollution permitting authority and granted a significant number of permits pursuant to this authority.26 We cannot reverse the expenditure of those funds nor the issuance of those permits. We further recognize the administrative difficulties in transferring a program like pollution permitting from Arizona back to the EPA and very possibly back to Arizona again. Based on the desire of Arizona to keep its pollution permitting authority and the record of other states obtaining and maintaining their own pollution permitting authority, even after full consultation regarding the transfer‘s effect on endangered and threatened species, see supra note 3, it seems likely that Arizona will again apply for pollution permitting authority. Finally, we note that all of the actors in this case—Arizona, the EPA, and FWS—operated in a somewhat murky legal environment. Faced with two circuit court cases suggesting that the EPA lacked authority to make pollution permitting transfer decisions based on
Other factors, however, weigh heavily in favor of vacating the EPA‘s approval of Arizona‘s transfer application. As noted above, Arizona annually issues tens of thousands of pollution permits pursuant to the EPA‘s action. See supra note 22. We have concluded that, absent section 7 coverage, we have no strong assurances that these permits will not allow development projects that are likely to jeopardize listed species or adversely modify their habitat. The purpose of the
For the just-stated reasons, we vacate the EPA‘s decision to approve Arizona‘s pollution permitting application. Pursuant to
THOMPSON, Senior Circuit Judge, dissenting:
Because I disagree with the conclusion in Part III of the majority opinion that the EPA had the authority to consider the impact on endangered and threatened species in making its decision to transfer administration of the pollution permitting system to the State of Arizona, I respectfully dissent.
As the majority observes, the requirements of section 7 of the
The majority interprets the “discretionary involvement” language of
Here, the EPA did not have discretion to deny transfer of the pollution permitting program to the State of Arizona; therefore its decision was not “agency action” within the meaning of section 7 of the
Nor, in my view, does the EPA possess the kind of continuing authority to monitor states’ administration of their pollution permitting programs that would render its oversight discretionary. As the majority notes, the EPA‘s limited oversight under
The EPA‘s authority to grant or to deny the State of Arizona‘s application to administer the pollution permitting program was nondiscretionary; I would deny the petition for review.
Notes
(1) The Secretary shall review other programs administered by him and utilize such programs in furtherance of the purposes of this chapter. All other Federal agencies shall, in consultation with and with the assistance of the Secretary, utilize their authorities in furtherance of the purposes of this chapter by carrying out programs for the conservation of endangered species and threatened species listed pursuant to section 1533 of this title.
(2) Each Federal agency shall, in consultation with and with the assistance of the Secretary, insure that any action authorized, funded or carried out by such agency (hereinafter in this section referred to as an “agency action“) is not likely to jeopardize the continued existence of any endangered species or threatened species or result in the destruction or adverse modification of habitat of such species which is determined by the Secretary ... to be critical, unless such agency has been granted an exemption for such action by the Committee pursuant to subsection (h) of this section. In fulfilling the requirements of this paragraph each agency shall use the best scientific and commercial data available.
Further, National Wildlife Federation was not a case concerning a federal action, and therefore did not raise any section 7(a)(2) issue. Moreover National Wildlife Federation merely supports the obvious proposition that a preliminary injunction is an equitable remedy and a court need not grant an injunction “for every violation of law.” 23 F.3d at 1512. Finally, far from abandoning the statutory interpretation in Hill, the Supreme Court has since National Wildlife Federation relied on and quoted Hill in reiterating the conclusion that “Congress[] inten[ded] to provide comprehensive protection for endangered and threatened species.” See Babbitt v. Sweet Home Chapter, 515 U.S. 687, 699, 115 S.Ct. 2407, 132 L.Ed.2d 597 (1995).
The dissent argues that we should nonetheless affirm the EPA‘s action based on
