43 Kan. 684 | Kan. | 1890

The opinion of the court was delivered by

Horton, C. J.:

This was an action in the court below by Deatherage & Ewart, to recover $144.91 for lumber, and to enforce a sub-contractor’s lien for the same. They claim that George A. Woods was the contractor, and Eli Henderson the owner of the building and premises. The lumber was purchased in April, 1885, and used by Henderson in the erection of a building on lots 7 and 8, in block 5, in Harveyville, in this state. The building was completed on the 16th day of May, 1885. A statement for a sub-contractor’s lien was filed on th.e 14th day of July, 1885. A copy of the statement was furnished to Henderson, the owner of the premises, on the 25th of July, 1885. In determining whether Deatherage & Ewart are entitled to a lien, the provisions of the civil code relating to liens of mechanics and others, in force in 1885, control. (Comp. Laws of 1885, art. 27, p. 685.) The trial court rendered judgment against George A. Woods for the sum of $144.91, with interest, but decided that the plaintiffs were not entitled to a lien upon the building and premises owned by Henderson.

This case has been to this court before, and is reported in 37 Kas. 63. The only question involved upon the former hearing was, whether the plaintiffs’ statement for a mechanics’ lien was sufficient. This court held the statement sufficient, and therefore ordered a new trial. Upon the second trial the following questions were submitted to the jury:

“1. Was the lumber, for which plaintiffs claim a lien, sold by them on the general credit of George A. Woods alone, without intending to obtain any security by virtue of a mechanics’ lien, if their claim should not be paid by Woods? A. Yes.
*688“2. Was George A. Woods the agent of plaintiffs for the purpose of collecting the amount due for the lumber? A. Yes.”

It is clearly apparent that the trial court decided against the lien of plaintiffs on account of these findings. But for the findings of the jury, a judgment enforcing the lien of plaintiffs should have been entered upon the findings of fact of the trial judge. The findings, however, of the jury, do not justify any judgment. They are conflicting with each other, and the evidence to sustain them is wholly unsatisfactory. Ewart, one of the plaintiffs, testified that in making all sales, both in Missouri and in Kansas, on bills of this kind, his firm did so with the knowledge that they had the right to a mechanics’ lien, provided the parties were not good.

2' contractor-no waiver. Where materials are furnished and placed in a building, if there be nothing showing a different intention, a jury would be warranted in finding that they were furnished to be used in such building. So if it appear that materials furnished were used in the erection of the building on which a lien is claimed, unless it is shown that they were intended for another purpose, it will be presumed that they had been contracted for to be used in the building. (Power v. McCord, 36 Ill. 214; Martin v. Eversal, 36 id. 222.) Under the statute, the mere fact that the materials were furnished on the credit of Woods, would not be an extinguishment or . ' # , 7 waiver of the plaintiffs’ lien. (Sodini v. Winter, 32 Md. 130.) But it was decided by this court in Weaver v. Sells, 10 Kas. 609, that if a material-man furnished lumber to a person with the understanding that it should be sold again as merchandise, if he should furnish it upon the personal credit of the vendee alone, without intending or expecting to obtain any security by virtue of a mechanics’ lien, it would hardly be claimed that a mechanics’ lien would be created, even though the vendee might afterward use the lumber in erecting a building. The right to the lien must be created at the time or before the material is furnished; it cannot be created afterward. It is the furnishing of the material under *689a contract, with the intention and understanding that it shall be used in erecting the building, that creates the lien. 1. Findings erroneous-judgment. If the plaintiffs furnished the lumber exclusively on the credit of Woods, and without intending to have any lien, then of course Woods was not their agent in selling the lumber to Henderson> nor cou^ he be their agent for the purpose °f collecting from Henderson the amount due plaintiffs for the lumber. In view of the conflicting findings, all that we can do is to reverse the judgment and order a new trial. (Civil Code, § 559.)

Counsel for the defendant claim that as the copy of the lien was not served until after the expiration of sixty days from the completion of the building, plaintiffs have no lien. They say:

“ That the lien must not only be filed within the sixty days, but the copy of the lien must be served within the sixty days; that all things necessary to be done to perfect the lien must be done within the sixty days; that the serving of the copy of the lien is as imperative as the filing; that under the mechanics’-lien law, the party claiming the lien must show he has complied with all the requirements of the statute and within the time fixed; that at the end of sixty days his lien must be completed in all respects, for after that time he can do nothing to perfect his lieu; in other words, that the validity of the lien must be determined at the end of the sixty days, and if anything is left undone at that time, then no valid lien exists.”

We do not concur in these views. Section 631, art. 27, Comp. Laws of 1885, reads:

“Any person who shall furnish any such material or perform such labor under a sub-contract with the contractor, wishing to avail himself of the act, shall file a statement of the amount due him from such contractor, for the labor performed, or the material, fixtures or machinery furnished, and a description of the property upon [to] which the same were done [applied] within sixty days after the completion of the buildings, improvements or repairs, or the furnishing or putting up of fixtures or machinery, or the performing of such labor, in a book kept by the clerk of the district court for that purpose, and furnish a copy thereof to the owner or *690agent of the premises, which book shall be ruled off into separate columns with heads as follows: When filed, name of contractor, name of claimant, amount named, and description of property; and the proper entry shall be made under each of such heads, and the district clerk shall be entitled to a fee of twenty-five cents for making such entries; and if the contractor does not pay such person or sub-contractor for the same, such sub-contractor or person shall have a lien for the amount due, for such labor or material, on such lot or lots, from the same time, and to the same extent, and in the same manner and to the same extent as such original contractor.”

3. mvner of reasoifabie time. Statutes relating to liens for mechanics and material-men should be liberally construed so as to protect, as far as possible, within the terms of the statute, the rights and equities of such persons. If the construction be given as contended for, in many cases the liens of mechanics and material-men could not be perfected. The statute in force in 1885 gave a sub-contractor, furnishing material or performing labor, sixty days after the completion of the building to file his statement for a lien. If such a contractor had all of the sixty days within which to file his statement, it would have been impossible for him, in many cases, to furnish a copy thereof to the owner or agent of the premises, within the sixty days, if his statement was not filed until the last day. A more reasonable construction of the statute would be, to give the sub-contractor a reasonable time, after filing his lien, to furnish a copy thereof to the owner or agent of the premises. What would be a reasonable time, must be determined by the court or jury trying the case under the attending circumstances. But the subcontractor must be diligent in serving his notice after filing his lien. Sections 630, 631, 633 and 636 of the civil code, relating to mechanics’ liens, in force in 1885, were repealed by chapter 168, Laws of 1889, and §632 of the civil code as now in force gives express directions for the mode of the service of a sub-contractor’s notice upon the owner of the premises. (Gen. Stat. of 1889, ¶4735.)

*6914. Agent tiiority exceeded. *690One other matter deserves a word of comment. The court. *691committed error in permitting Henderson to prove that he paid Woods for the lumber by giving credit on an old account due from Woods to him. If it were the intention of the plaintiffs to sell their lumber to Woods upon his personal credit exclusively, and without any lien, then this evidence had nothing to do with the case. If the plaintiffs have, under the statute, a lien for their material, them Henderson had no power to satisfy their claim by giving Woods credit on an old account due from

him, even if Woods was the agent of plaintiffs for the purpose of collecting their bill for the lumber. (Scully v. Dodge, 40 Kas. 395; Organ Co. v. Lasley, 40 id. 521.)

The judgment of the court below will be reversed, and the cause remanded for a new trial.

All the Justices concurring.
© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.