Lead Opinion
McKEAGUE, J., delivered the opinion of the court, in which COLE, J., joined. MAYS, D.J. (pp. 359-63), delivered a separate dissenting opinion.
OPINION
This case poses the question whether a district court has jurisdiction to confirm an arbitration panel’s interim award denying class arbitration. The district court, following guidance provided by this court in a closely related earlier ruling in the same case, determined that the requisite ripeness is lacking and dismissed the motion to confirm for lack of jurisdiction. Because we agree that appellant has failed to demonstrate that it is subject to cognizable hardship if immediate judicial review of the interim award is denied, we affirm.
I. BACKGROUND
Plaintiff-appellant Dealer Computer Services, Inc. (“DCS”) provides computer hardware and software support to automobile dealers. It developed an electronic parts catalog system known as a Computerized Publication Display (“CPD”) that enabled car dealers to display then current automobile parts, prices, descriptive data and parts visualizations. Defendant-appellee Dub Herring Ford, a Mississippi corporation, and sixty-three other originally named Ford dealers are a group of dealerships that were parties to written contracts with DCS for the provision of CPD systems and services. They are also putative class representatives of a class of some 2,470 similarly situated Ford dealerships across the country allegedly aggrieved by DOS’s breaches of the CPD contracts. All of the CPD contracts contained an arbitration provision requiring that any contract-related controversy be submitted to arbitration under the Commercial Arbitration Rules of the American
In November 2006, the arbitration panel issued its Clause Construction Award, concluding that the applicable CPD contracts permit the present arbitration to proceed as a class arbitration. DCS moved the district court to vacate the clause construction award. The district court denied the motion on May 29, 2007. R. 23, Order; Dealer Computer Services, Inc. v. Dub Herring Ford,
Next, in proceedings conducted from August to October 2008, the arbitration panel considered evidence and arguments regarding class certification. In December 2008, the arbitration panel issued its 37-page Partial Final Class Determination Award, denying class certification. DCS moved the district court to re-open the case and confirm the class determination award. Taking its lead from our earlier opinion on DCS’s motion to vacate the interim clause construction award, the district court applied the prescribed three-factor ripeness test. The court determined that the arbitration panel’s denial of class certification did not pose a likelihood of harm to DCS and that denial of immediate judicial review of the interlocutory award would pose no hardship to DCS. R. 43, Order; Dealer Computer Services, Inc. v. Dub Herring Ford,
II. APPELLATE JURISDICTION
Although Dub Herring Ford has not moved to dismiss the appeal for lack of appellate jurisdiction, it has questioned DCS’s asserted reliance on the collateral order exception to the final judgment rule of 28 U.S.C. § 1291 as a basis for this court’s appellate jurisdiction. Indeed, the district court’s dismissal order, essentially refusing to finally determine the propriety of the arbitration panel’s class determination award, does not appear to meet the requirements of the collateral order exception. See In re Dow Corning Corp.,
In response, however, DCS has correctly noted that appeal is properly taken under 9 U.S.C. § 16(a)(1)(D), expressly allowing appeals from orders confirming or denying confirmation of arbitration awards and partial awards. See Bull HN Information Systems, Inc. v. Hutson,
III. ANALYSIS
A. Governing Standards
The district court’s determination that it lacked jurisdiction for lack of ripeness is subject to de novo review. DCS-I,
The ripeness doctrine “focuses on the timing of the action.” ... “[It] is more than a mere procedural question; it is determinative of jurisdiction. If a claim is unripe, federal courts lack subject matter jurisdiction and the complaint must be dismissed.” ... Ripeness “draw[s] both from Article III limitations on judicial power and from prudential reasons for refusing to exercise jurisdiction.” ... Enforcing ripeness requirements discourages “premature adjudication” of legal questions and judicial entanglement in abstract controversies .... Thus, the doctrine serves as a bar to judicial review whenever a court determines a claim is filed prematurely.
The key factors to consider when assessing the ripeness of a dispute are: (1) the likelihood that the harm alleged by a party will ever come to pass; (2) the hardship to the parties if judicial relief is denied at this stage in the proceedings; and (3) whether the factual record is sufficiently developed to produce a fair adjudication of the merits.
Id. at 560-61 (citations omitted). See also Stolt-Nielsen S.A. v. AnimalFeeds Int’l Corp., — U.S. -,
The ripeness inquiry is triggered by the fact that the instant interlocutory arbitration award, like the one at issue in our earlier ruling, is not a final arbitration award. A final award deciding the merits of the dealers’ breach of contract claims would clearly be subject to confirmation under the Federal Arbitration Act, 9 U.S.C. § 9.
B. Finality of Class Arbitration Determination
DCS concedes that the class determination award is an interim award, but argues that it is nonetheless subject to judicial review because it resolves a “separate, discrete, independent, severable issue” and therefore has sufficient “finality.” See Island Creek Coal Sales Co. v. City of Gainesville, FL,
Here, in contrast, the interim class arbitration determination, albeit a significant procedural step in the arbitration proceedings, has no impact on the parties’ substantive rights or the merits of any claim. The denial of class arbitration proceedings arguably disposes of a discrete, independent, severable issue, but it is a procedural issue — hardly the sort of final decision that warrants immediate judicial review in disruption of ongoing arbitration proceedings. Island Creek is thus distinguishable.
This very distinction is among the reasons why, in litigation (as opposed to arbitration), class certification decisions by the district courts were traditionally not deemed to have the requisite finality to warrant immediate appellate review. See
Hence, insofar as case law applying Rule 23(f) is relevant, by analogy, to assessment of the district court’s jurisdiction to confirm the arbitration panel’s denial of class arbitration in this case, it does not counsel in favor of a per se rule of appealability because the denial is sufficiently “final.” Rather, it counsels in favor of requiring consideration of the very sort of ripeness factors that the district court did consider in accordance with our recent direction in DCS-I,
DCS insists the DCS-I ruling expressly contemplated the immediate reviewability of the arbitration panel’s class arbitration determination. DCS relies on the following language from our opinion:
The stay procedures set forth in [AAA Commercial Arbitration Supplementary] Rule 5(d) enable a party to contest an unfavorable decision on class certification in court before commencement of class arbitration and resolution of the merits by the arbitration panel. Thus, if the arbitrators in this case ultimately decide to certify Dealers’ class, which is no certainty, Rule 5(d) would nonetheless provide DCS ample opportunity to obtain judicial review of any arguments it may have against class arbitration, including those challenging the soundness of the arbitration panel’s prior Clause Construction Award. Given this prospective opportunity for judicial review, it does not appear DCS will suffer any material hardship if review is withheld at this preliminary stage of arbitration.
Id. at 562-63 (bold-emphasis added).
DCS construes this language more broadly than warranted. DCS reads the language as reflecting our determination that the motion to vacate the clause construction award was not ripe because DCS would necessarily — i.e., irrespective of outcome — have another opportunity to obtain interlocutory judicial review of the class determination award. As indicated by the highlighted language, however, the contemplated judicial review of the class determination award is clearly contingent on the eventuality of an unfavorable award. Indeed, whether the arbitration panel ultimately decided to certify the class or not, the decision would be interlocutory. An interlocutory award, we made clear, is ripe for judicial review only if the three ripeness factors — i.e., likelihood of harm, hardship, and factual development — are met.
It is because of the importance of the hardship element to the ripeness assessment that this favorable/unfavorable distinction is not merely one of semantics. And it is the hardship requirement that undermines DCS’s argument that because motions to confirm and to vacate are two sides of the same coin, both forms of judicial review should be mutually available. Yes, if Dub Herring Ford and the other dealers had moved the district court to vacate the class determination award under 9 U.S.C. § 10, they may very well have been able to establish the requisite hardship (e.g., in the form of the “death-knell” factor) to justify the exercise of jurisdiction notwithstanding the non-final nature of the award. In that case, yes, the district court would presumably be able to exercise supplemental jurisdiction over “the flip side of the coin,” DCS’s anticipated reciprocal motion to confirm the award. Yet, because the dealers have not moved to vacate the award, DCS, as the winning party, is handicapped in its efforts to obtain judicial review. Pursuant to DCS-I, which has newly been confirmed in material part by the Supreme Court in SiolfNielsen, DCS must meet the requirements of ripeness to trigger federal court jurisdiction.
This result, requiring either a final award or a sufficiently ripe interlocutory award, is consistent with the “national policy favoring arbitration.” Hall Street, 552 U.S. at 588,
C. Ripeness of DCS’s Motion to Confirm
1. Correctness of the Ripeness Standard Applied
The district court granted Dub Herring Ford’s motion to dismiss DCS’s motion to
(1) the likelihood that the harm alleged by the party will ever come to pass; (2) the hardship to the parties if judicial relief is denied at this stage of the proceedings; and (3) whether the factual record is sufficiently developed to produce a fair adjudication of the merits.
R. 43, Order, p. 3-4 (quoting DCS-I,
The district court’s analysis is faithful to the direction provided in DCS-I, where we observed, in holding that DCS’s motion to vacate the clause construction award was unripe, that the “absence of hardship for DCS at this juncture renders DCS’s motion to vacate the sort of premature adjudication the ripeness doctrine seeks to avoid.” DCS-I,
DCS contends the district court should not have applied this ripeness test, noting that other circuits apply a less rigid standard and that the Supreme Court itself has applied a two-part ripeness test, sans the likelihood-of-harm factor. The three-factor test set forth in DCS-I is essentially the law of the case and DCS has not presented any persuasive reason to abandon it in favor of any other circuit’s standard. We acknowledge, however, that the Supreme Court, in Stolt-Nielsen, applied a two-factor ripeness test in a context practically identical to the situation faced in DCS-I. Is the two-factor test materially different? If it were applied here, would it produce a different result?
In StolL-Nielsen, the Court reversed a Second Circuit decision. The Second Circuit had ordered that the district court’s order vacating an arbitration panel’s clause construction award be vacated. The Supreme Court ultimately held that the arbitration panel exceeded its powers by imposing class arbitration on parties whose contractual arbitration agreement was silent on the issue. Stolt-Nielsen,
This test is nominally different from the three-factor standard we employed in DCS-I, but in practical effect, the distinction is one without a difference. In StoltrNielsen, the Court focused on the hardship element. The Court observed that “[t]he arbitration panel’s award means that petitioners must now submit to class determination proceedings before arbitrators who, if petitioners are correct, have no authority
The facts and procedural posture of the case presented in Stolt-Nielsen are materially indistinguishable from those presented in DCS-I. Yet, what Stolt-Nielsen found to be ripe, we found not to be ripe. In this respect (i.e., the merits of the ripeness determination), the two decisions may be deemed in conflict.
2. Correctness of the Ripeness Determination
In challenging the correctness of the district court’s ripeness determination, DCS asserts a different form of harm or hardship than the district court considered. The district court held that the potential harm to DCS involved in defending against class arbitration would never occur and that therefore, DCS had failed to demonstrate that withholding judicial review would pose any hardship. On appeal, DCS acknowledges that it won the class determination battle and is no longer threatened, in this case, by the specter of class arbitration expenses and liability. Adopting a new approach, DCS now contends that the hardship posed by denial of immediate confirmation of the class determination award resides in the (a) postponement of judicial confirmation until after the arbitration panel renders its final award(s); and (b) the denial of repose and certainty of preclusive effect that would accompany a confirmed award.
DCS did not assert this argument in the district court. The issue is therefore forfeited. See In re Hood,
DCS’s new arguments are only weakly supported. First, DCS argues that its opportunity to obtain judicial review and confirmation of the class determination award may be entirely foreclosed if the one-year
Absent immediate confirmation of the class determination award, DCS further contends, the award lacks the preclusive effect DCS needs to protect it from other claimants’ potential efforts to obtain class arbitration of similar breach of contract claims in other arbitration proceedings. In particular, DCS refers to another pending putative class arbitration proceeding involving similar claims and commenced just four months after the instant arbitration, Fox Valley Ford, et al. v. DCS, in which the claimants are represented by the same counsel as the claimants in this case. DCS contends that counsel for the Fox Valley Ford claimants have made clear their intentions to pursue class arbitration proceedings in that case if the class determination award in this case is not confirmed.
In response, Dub Herring Ford contends that Fox Valley Ford involves dissimilar breach of contract claims. Yet, in any event, we remain unpersuaded that such “collateral hardship” (i.e., potentially incurring expenses in another case) is cognizable in evaluating the ripeness of DOS’s motion for confirmation of an interim arbitration award in this case. In evaluating ripeness, the Supreme Court has recognized that the disadvantages of premature review ordinarily outweigh the burden created by the additional costs of — even repetitive — litigation. See Ohio Forestry Ass’n, Inc. v. Sierra Club,
Further, even if such collateral consequences could be considered “hardship,” DOS’s showing of the likelihood of this harm coming to pass is sketchy and hardly compelling. We note that the Fox Valley Ford case does appear to be on a parallel track. When the arbitration panel issued a clause construction award permitting the Fox Valley Ford claimants to pursue class arbitration, DOS’s motion to vacate the award was assigned to and denied by the same district judge who denied both DOS’s motion to vacate and motion to confirm in this case. See Dealer Computer Services v. Fox Valley Ford,
In short, the new appellate arguments made by DCS in attempting to carry its burden of showing ripeness — if they are considered at all — are no better than the old arguments the district court rejected. The district court’s order dismissing the motion to confirm for lack of ripeness must therefore be upheld.
IV. CONCLUSION
Despite DCS’s protestations that confirmation should be a simple procedure that would ultimately enhance efficiency in managing and resolving the dealers’ arbitration claims, this very judicial review experience, still pending eighteen months after the arbitration panel’s interim class determination award was issued, and having seemingly accomplished nothing but delay, starkly demonstrates why the courts should be vigilant to safeguard arbitration proceedings from unwarranted judicial interference. For all the foregoing reasons, the district court’s order of dismissal is AFFIRMED.
Notes
. The Federal Arbitration Act itself is not jurisdictional. Hall Street Associates, L.L.C. v. Mattel, Inc.,
. Although ripeness was not expressly addressed in Island Creek, if it had been, the three ripeness factors set forth in Dealer Computer Services,
. In Stolt-Nielsen, the Court reached a conclusion on ripeness that appears to be at odds with our ripeness ruling in DCS-I. Stolt-Nielsen,
. Considering that the Stolt-Nielsen Court implicitly considered likelihood of harm, along with fitness and hardship, as we did in DCS-I, how are we to understand its different "ripeness" determination? The answer may lie in the nature of the hardship identified by each court and the likelihood that that hardship would come to pass. In each case, interestingly, the parties had not expressly argued hardship, so the court had to presume the "asserted” hardship. See Stolt-Nielsen,
In contrast, we presumed in DCS-I that DCS "sought to avoid the 'harm' of increased time, expense, complexity, and potential liability often associated with the defense against a class proceeding.” DCS-I,
Thus, the difference in the two courts’ ripeness determinations may be attributable not to application of two materially different ripeness standards, but to application of two substantially similar ripeness standards to similar but not identical types of hardship whose imminence or likelihood of occurrence was materially different. In light of this analysis, Stolt-Nielsen does not necessarily undermine the district court's ripeness ruling in this case. Also, in light of this analysis, it becomes apparent that Stolt-Nielsen is not necessarily at odds with our ripeness ruling in DCS-I, but may be distinguishable on the basis of the nature and imminence of the presumed hardship.
In assessing the significance of Stolt-Nielsen 's teaching on ripeness, moreover, it is important to recognize that the majority's entire discussion of ripeness is confined to one footnote. Stolt-Nielsen,
Dissenting Opinion
dissenting.
Dealer Computer Services, Inc. (“DCS”) appeals from the district court’s dismissal of its Motion to Confirm the arbitrators’ award finding that Dub Herring Ford and the proposed class of automobile dealers whom it represents (collectively, the “Dealers”) should not be allowed to go forward with their arbitration as a class arbitration. The district court found that DCS’ action was not ripe, basing its conclusion on a prior published opinion of this court in this case. See Dealer Computer Servs., Inc. v. Dub Herring Ford,
I.
DCS sells computer software systems to automobile dealerships around the country. These systems allow Dealers to display currently available automobile parts and prices to their customers. The Dealers allege that DCS breached its contracts with them by failing to negotiate an extension of its agreement with Ford Motor Company allowing Dealers to continue to view Ford parts and their prices on DCS’ system. Dealers filed a series of arbitration actions against DCS and sought to proceed as a class arbitration. The arbitrators ruled initially that the arbitration agreement found in all of DCS’ form contracts with Dealers permitted the arbitrators to hear a class arbitration. DCS sued in federal district court to vacate the arbitrators’ decision as exceeding their powers under the arbitration agreement and as in “manifest disregard of the law.” DCS I,
When the case returned, the arbitrators held, in a “Partial Final Class Determination Award,” that the Dealers could not proceed with their claims as a class. DCS then returned to federal district court, seeking to confirm the arbitrators’ class determination. See 9 U.S.C. § 9 (providing that federal district courts may enter orders confirming arbitration awards). The district court, following the ripeness analysis employed by this court in the parties’ prior appeal, dismissed DCS’ Motion as unripe. See Dealer Computer Servs., Inc. v. Dub Herring Ford Lincoln Mercury, Inc., No. 07-10263,
II.
A.
In Stolt-Nielsen, a corporation that regularly ships liquids via tanker vessels commenced an arbitration proceeding against Stolt-Nielsen, alleging that StollANielsen had conspired to violate the antitrust laws through price fixing.
Importantly for this case, the Court also responded to the dissent’s primary argument that Stolt-Nielsen’s Motion to Vacate was premature because it was unripe. See id. at 1777 (Ginsburg, J., dissenting). The majority held that the claim was ripe because, if Stolt-Nielsen could not presently seek review, it “must now submit to class determination proceedings before arbitrators who ... have no authority to require class arbitration.” Id. at 1767 n.2 (majority opinion). The Court also viewed it as certain that, had Stolt-Nielsen refused to abide by the arbitrators’ decision, it would be subject to a motion to compel under 9 U.S.C. § 4 to force it to arbitrate the class claims. Id. Responding to the dissent’s argument that the Court would allow parties to challenge merely procedural decisions by arbitrators, the majority reasoned that a shift from bilateral arbitration to class arbitration wrought “fundamental changes.” Id. at 1776. Under the rules of the American Arbitration Association, participants in class arbitrations no longer enjoy “the presumption of privacy and confidentiality” that applies to bilateral arbitrations. Id. at 1776 (citing AAA Class Rule 9(a)). Class arbitrations “no longer resolve[ ] a single dispute between the parties to a single agreement, but instead resolvef ] many disputes between hundreds or perhaps even thousands of parties.” Id. Thus, parties must have the ability to seek court review of arbitrators’ construction of a class clause in an arbitration agreement. Id.
StolL-Nielsen arrived at the Supreme Court in the same procedural posture as DCS in its prior appeal to this court. As in Stolt-Nielsen, DCS had filed a Motion
B.
Without the support of this court’s prior holding, it is difficult to argue that a procedurally later development is unripe for consideration when the Supreme Court has held that an earlier procedural ruling is ripe for confirmation or vacatur. The arbitrators’ decision rejecting class arbitration disposes of “a separate, discrete, independent, severable issue.” See Island Creek Coal Sales Co. v. City of Gainesville,
Second, the concession that a motion to vacate the present award by the Dealers would be ripe effectively concedes that this court has jurisdiction over the present Motion. The provisions of the FAA are not severable. See 9 U.S.C. §§ 9-10 (statutory provisions conferring authority on the federal courts to confirm or vacate an arbitral award). Had the Supreme Court refused to vacate the arbitrators’ decision in Stolt-Nielsen, that refusal would have had the same effect as confirming it. The language of the FAA makes this clear. A federal court “must grant [an order confirming an arbitral award] unless the award is vacated, modified, or corrected.” 9 U.S.C. § 9 (emphasis added). Where there is jurisdiction to vacate an award, there is of necessity jurisdiction to confirm it. No authority — other than argument by analogy to this court’s prior, abrogated decision — supports severing the FAA’s remedies. The Dealers concede that, if this court concludes a motion to vacate by them would be ripe, DCS’ current Motion to Confirm must also be ripe. Audio recording: Oral Argument at 21:30-22:11 (Aug. 4, 2010) (on file with the clerk of the court) [hereinafter “Oral Argument”].
The potential for an aggrieved party to vacate the award explains why failure to confirm would harm DCS. See 9 U.S.C. § 9 (noting that the only two requirements
Third, the Dealers appear to base much of their argument on the idea that allowing piecemeal adjudication would serve to undermine the “national policy favoring arbitration.” Hall St. Assocs., LLC v. Mattel, Inc.,
III.
This court denied DCS a decision on its prior Motion to Vacate. See DCS I,
. Both challenged awards were termed “Partial Final” awards. See Stolt-Nielsen,
. Nor would it be correct to characterize the Supreme Court's holding that it had jurisdiction as summary or dismissive. “[Fjederal courts have a duty to consider their subject matter jurisdiction in regard to every case and may raise the issue sua sponte.” Answers
. To the extent that one can find any "discretion” in a court's jurisdiction, this court should exercise it in favor of DCS because this court denied DCS a hearing on the merits about the validity of the class arbitration clause. Compare Stolt-Nielsen,
