Opinion
The principal issue in this appeal is whether a court may authorize a purchaser of goods and services that is dissatisfied with the seller’s performance to terminate its contract with the seller, without compliance with the contract’s unequivocal termination provision, by invoking the doctrine of frustration of purpose. Under the circumstances of this case, in which the validity of the termination provision has not been challenged, we reverse the judgment of the trial court excusing performance by the purchaser.
On January 19,2011, the plaintiff, DDS Wireless International, Inc., filed a complaint alleging that the defendant, Nutmeg Leasing, Inc., was in breach of contract, having unilaterally repudiated the parties’ service agreement prior to its expiration. The defendant admitted to terminating the service agreement but denied its liability, asserting three special defenses: (1) the plaintiff materially had breached the contract; (2) the purpose of the contract had been frustrated; and (3)
The record reveals certain undisputed facts relevant to this appeal. In 1997, the defendant purchased from the plaintiff a mobile digital dispatch system for use in its operation of a fleet of taxi cabs. The system, composed of computer equipment operating from a central dispatcher location and terminals installed into individual taxi cabs, was designed to facilitate communication between the dispatcher and taxi drivers. At the time of the purchase, the defendant also entered into a service agreement with the plaintiff. That contract provided that the plaintiff would conduct any necessary maintenance of the system for a set period of time. The service agreement, which is the subject of this appeal, required that the defendant make quarterly payments in exchange for the plaintiff’s maintenance of the dispatch system.
On June 30, 2006, the parties renewed the service agreement for a period of five years through June 29, 2011. The contract included a termination provision giving either party the opportunity to end the relationship under certain circumstances. The provision provided that “[i]f either party fails to perform its obligations under this Agreement and such failure continues for a period of 30 days after written notice from the other party, the other party shall have the right to terminate this Agreement.”
At trial, William Scalzi, a principal of the defendant, testified regarding the propensity of the dispatch system and its components to malfunction, a situation that allegedly created significant problems with the operation of the defendant’s taxi business. Although this testimony appears to be a basis for the trial court’s ultimate conclusion that the purpose of the contract was frustrated, the record contains no specific findings as to the cause or extent of the malfunctions, the impact of the malfunctions on the defendant’s finances, the responsibility of each party for the malfunctions, or any other findings relevant to a determination of a frustration of purpose. We note that neither party sought articulation from the trial court in order to clarify its ruling.
On appeal, the plaintiff claims that the court improperly determined that the purpose of the contract was
We begin by setting forth the applicable standard of review. “Where . . . there is clear and definitive contract language, the scope and meaning of that language is not a question of fact but a question of law.” (Internal
At trial, the court found that the defendant “anticipated a working system, and the system didn’t work up to par” and that, despite the “best efforts by [the plaintiff] to repair and do the best [it] could . . . [the system] just didn’t work. It didn’t—it failed.” The court concluded that “there’s been a failure of the purpose of the contract,” but did not articulate what that purpose was or why the defendant was justified in terminating the contract prematurely. Accordingly, we are not persuaded that the court’s conclusion that a frustration of purpose excused the defendant from complying with the requirements of the termination provision is supported by the facts that appear in the record.
“[I]n private disputes, a court must enforce the contract as drafted by the parties and may not relieve a contracting party from anticipated or actual difficulties undertaken pursuant to the contract, unless the contract is voidable on grounds such as mistake, fraud or unconscionability.” Holly Hill Holdings v. Lowman,
The doctrine of frustration of purpose was first recognized in the tum-of-the-century English case of Krell v.
In light of the foregoing, we conclude that the trial court improperly relied on the doctrine of frustration of purpose in excusing the defendant from the nonperformance of its obligations pursuant to the service agreement. As this was the sole basis for the court’s decision, we do not address any alternative theory that might have excused the defendant’s nonperformance, if alleged and proved.
The judgment is reversed and the case is remanded for a new trial.
In this opinion the other judges concurred.
Notes
“It is well established that [a]n articulation is appropriate where the trial court’s decision contains some ambiguity or deficiency reasonably susceptible of clarification. . . . [P]roper utilization of the motion for articulation serves to dispel any . . . ambiguity by clarifying the factual and legal basis upon which the trial court rendered its decision, thereby sharpening the issues on appeal.” (Internal quotation marks omitted.) Priest v. Edmonds,
The plaintiff also argues that the defendant may not be excused from performance under the contract on the basis of the plaintiffs alleged material breach because the defendant did not plead such a defense or, alternatively, because the plaintiff was not afforded an opportunity to correct the problem with the terminals as required by the terms of the contract. As we have previously explained, the trial court ruled on the basis of the doctrine of frustration of purpose, not on a finding of material breach. Although the defendant argued material breach at trial, the court declined to address the issue.
“When an issue is raised in the trial court but the court declines to address it, an appellate court may consider it if the facts are undisputed and the issue is purely a question of law. . . . When it is unclear from the record whether the trial court based its decision on factual or legal conclusions any decision made by [this court] respecting [the plaintiffs claims] would be entirely speculative.” (Citation omitted; internal quotation marks omitted.) Stone-Krete Construction, Inc. v. Eder,
A party claiming that a supervening event or contingency has frustrated, and thus excused, a promised performance must demonstrate that: (1) the event substantially frustrated his principal purpose; (2) the nonoccurrence of the supervening event was a basic assumption on which the contract was made; (3) the frustration resulted without the fault of the party seeking to be excused; and (4) the party has not assumed a greater obligation than the law imposes. 2 E. Farnsworth, Contracts (3d Ed. 2004) § 9.7, pp. 652-53; see also 2 Restatement (Second), Contracts § 265 (1981).
The relevant provision provides: “If either party fails to perform its obligations under this Agreement and such failure continues for a period of 30 days after written notice from the other party, the other party shall have the right to terminate this Agreement.”
For example, we do not consider whether the plaintiff, in furnishing the defendant with allegedly faulty terminals, breached the implied warranties of merchantability or fitness for a particular purpose. See General Statutes §§ 42a~2-314 and 42a-2-315; Schenck v. Pelkey,