OPINION
{1 Plaintiff DCH Holdings, LLC (Buyer) appeals the district court's decision to consider parol evidence in interpreting an integrated contract that Buyer entered into with Defendant Loren Nielsen (Seller). We affirm.
BACKGROUND
€ 2 In May 2005, Buyer and Seller entered into a contract for the sale of real property located in Sandy, Utah. The contract set October 15, 2005, as a final closing date and provided that Seller would deliver physical possession of the property and convey "good and marketable title" upon closing, after Buyer tendered the agreed-upon purchase price. The contract also included an explicit integration clause reading, "This Contract together with its addenda ... constitutes the entire Contract between the parties...."
T3 At the time of contract, the subject property was part of a larger parcel that had not yet been subdivided or replatted. Under
1 4 Seller did not hear from Buyer in the months following execution of the contract and believed that Buyer had abandoned the plans to purchase and develop the property. On the day before the final closing date, Buyer sent Seller a facsimile notifying him of its intent to tender the purchase price and close on the sale of the property that day. 2 Immediately after the parties signed the contract, Buyer had begun taking steps to obtain plat approval. As of the final closing date, however, the property had not yet been subdivided or platted. When Seller delivered neither possession nor title, Buyer brought suit for breach of contract.
15 Both parties filed cross-motions for summary judgment. Judge Timothy R. Hanson denied both parties' motions, concluding that the contract was silent on assigning responsibility for obtaining plat approval and that, absent an express statutory delegation of such duties, the parties needed to specify that term in their contract. Judge Hanson further concluded that the contract's ambiguity on an essential term would require the introduction of parol evidence to assess the parties' intent. 3
T6 Following Judge Hanson's retirement, Judge Kate A. Toomey conducted the ensuing bench trial. Based on extrinsic evidence of the parties' intent, Judge Toomey ruled that the parties had agreed that Buyer would obtain plat approval. Judge Toomey therefore concluded that Seller had not breached the contract. Judge Toomey also awarded Seller attorney fees based on a contractual provision providing that "[iIn the event of any litigation ... to enforce this Contract, the prevailing party shall be entitled to ... reasonable attorney fees." Buyer appeals.
ISSUE AND STANDARD OF REVIEW
T7 Buyer claims that the district court erred by considering parol evidence to interpret the parties' integrated contract. Seller counters that the district court was correct in considering parol evidence because the parties' integrated contract was ambiguous. "[Bloth the issues pertaining to ambiguity and admittance of parol evidence present questions of law which we review under a correctness standard, granting no particular deference to the trial court" Bennett v. Huish,
18 The parol evidence rule operates "to exclude [extrinsic] evidence of contemporaneous conversations, representations, or statements offered for the purpose of varying or adding to the terms of an integrated contract." Tangren Family Trust v. Tangren,
9 The contract here contains a clear integration clause. See generally Tangren,
T10 A contract is "ambiguous if it is capable of more than one reasonable interpretation because of uncertain meanings of terms, missing terms, or other facial deficien-cles." Daines,
{11 "[Wlhen determining whether a contract is ambiguous, any relevant evidence must be considered." Id. ¶ 26. But parol evidence may not be used "to obscure otherwise plain contractual terms," for determining what a contract means "begins and ends with the language of the contract." Id. ¶¶ 31, 30. Therefore, all interpretations inferred from extrinsic evidence must be " 'reasonably supported by the language of the contract?" Id. ¶ 26 (quoting Ward v. Intermountain Farmers Ass'n,
1112 Transferring the subject property here, without obtaining plat approval, would violate Utah law. From the face of the parties' contract, it is apparent that they were aware of the mandatory platting requirement because the contract explicitly provides for partial payment and closing upon preliminary and final plat approval. Yet the contract does not assign responsibili
CONCLUSION
13 The contract is ambiguous because it did not specify who was responsible for obtaining plat approval. The district court therefore properly considered parol evidence to ascertain the parties' intent.
{14 Accordingly, we affirm and remand for the purpose of calculating Seller's attorney fees reasonably incurred on appeal. See Management Servs. Corp. v. Development Assocs.,
15 WE CONCUR: GREGORY K. ORME and CAROLYN B. MeHUGH, Judges.
Notes
. The transfer "of any land located in a subdivision ... before a plat of the subdivision has been approved and recorded" is in violation of Utah law. Utah Code Ann. § 10-9a-611(1)(a) (Supp. 2005); id. § 10-9a-803(2) (stating that violation of section 10-9a-611(1)(a) may be punishable as a class C misdemeanor or by imposing other civil penalties); see generally id. § 10-9a-103(35)(a)-(b) (" 'Subdivision' means any land that is divided ... or proposed to be divided into two or more ... parcels ... for the purpose ... [of] sale ... [and] includes{[ ] the division ... of land ... [by] plat ...."); id. § 10-9a-103(25) (" 'Plat' means a map or other graphical representation of lands being laid out and prepared in accordance with [this section].'"). The process for obtaining plat approval of subdivided property is provided by Utah Code section 10-9a-603. See id. § 10-9a-603.
. Buyer's attempt at closing on the contract came just days after plans were announced to build a soccer stadium adjacent to the subject property.
. Judge Hanson's decision to allow parol evidence was premised upon the recognition that had the parties failed to reach a meeting of the minds in assigning responsibility for obtaining plat approval, the contract could potentially be unenforceable due to a defect in formation-specifically, failure to agree on an essential term. See Nielsen v. Gold's Gym,
. Integrated contracts with missing terms are considered only partially integrated. See Stanger v. Sentinel Sec. Life Ins. Co.,