DAYTON CHILDREN‘S HOSPITAL, еt al. v. GARRETT DAY, LLC, et al.
Appellate Case No. 28047
IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY
November 27, 2019
2019-Ohio-4875
Trial Court Case No. 2016-CV-2061 (Civil Appeal from Common Pleas Court)
OPINION
Rendered on the 27th day of November, 2019.
JEFFREY P. MCSHERRY, Atty. Reg. No. 0055993, 201 East Fifth Street, Suite 1110, Cincinnati, Ohio 45202
and
BRYAN M. SMEENK, Atty. Reg. No. 0082393, 100 South Third Street, Columbus, Ohio 43215
Attorneys for Plaintiffs-Appellees/Cross-Appellants
PAUL T. SABA, Atty. Reg. No. 0063723 and JEFFREY M. NYE, Atty. Reg. No. 0082394, 2623 Erie Avenue, Cincinnati, Ohio 45208
Attorneys for Defendants-Appellants/Cross-Appellees
WELBAUM, P.J.
{¶
{¶ 3} We conclude that the trial court did not err in granting summary judgment on both sides’ fraudulent inducement claims. These claims duplicated claims for breach of the parties’ contract and were factually intertwined with the contract claims. In addition, the alleged damages of both sides are the same as those they claimed for breach of contract. Accordingly, the judgment of the trial court will be affirmed.
I. Facts and Course of Proceedings
{¶ 4} Due to the complexity of this case and the many individuals and companies involved, we will briefly describe these principаl actors:
- Garrett, which purchased the former Dayton Electroplate property (“the Property“) at some time in 2012. Garrett is in the business of demolishing and remediating environmentally contaminated properties.
- Michael Heitz, who owns 50% of Garrett and has been in the business of remediating properties since 1998.
- Matt Wagner, who was an employee of KERAMIDA. Garrett employed KERAMIDA in connection with obtaining a grant from the Clean Ohio Assistance Fund (“Clean Ohio“). KERAMIDA also performed environmental assessment work at the Property after the grant was obtained. Wagner was employed at KERAMIDA from 2005 until April 2015, when he took a job with Tetra Tech. Wagner has worked on a number of projects with Garrett.
- Shelley Dickstein, who was the assistant Dayton City Manager during the relevant time, and worked with Garrett, Heitz, and Wagner on the Clean Ohio project.
- Keith Klein, who was a City of Dayton representative supervising the Clean Ohio grant.
- Edd McGatha, who was the facilities director for DCH, which purchased the Property from Garrett.
- Deborah Feldman, who was the Chief Executive Officer of DCH.
- Steve Ireland, who was a realtor representing Garrett in the sale of the Property to DCH.
- MCM Demolition, which obtained a demolition permit in 2012 and demolished two buildings on the Property before Garrett and DCH signed a purchase agreement.
- Michael Cromartie, who was the Chief Building Official for the City of Dayton until April 2015. The Chief Building Official is the department manager of the Division of Building Inspection, and manages the inspection group, which contains inspectors for several disciplines, including electrical, plumbing, structural, and HVAC.
- John Scott, who was the President of Bladecutters, Inc., a company that has been doing demolition work since 2007. Bladecutters removed the
concrete slab on the Property after the original purchase contact between Garrett and DCH was signed in July 2014. At the time, Bladecutters’ primary customer for demolition was the City of Dаyton. - Karen DeMasi, who was employed at CityWide Development (“CityWide“), and represented DCH in the negotiations over the Property. CityWide is a non-profit community economic development corporation. CityWide does comprehensive community development, real estate development, and business lending.
- Scott Adams, who replaced Michael Cromartie as Chief Building Official in April 2015.
- The Montgomery County Port Authority, which is a quasi-governmental agency located in CityWide‘s offices. (According to the Port Authority‘s website, the Port Authority is a “political subdivision that is used as a vehicle to assist in the economic development process. Port Authorities can loan or secure funds, receive grants and buy assets all in order to facilitate incentive drive financing transactions“) (daytonport.com/about.html, accessed on October 26, 2019).
- The Dayton Reserves is a for-profit sub-company of CityWide.
- Michael Kerr, who was the owner of MAKSolve, LLC (“MAKSolve“). DCH retained MAKSolve to conduct environmental studies and to finish the removal of concrete from the Property.
{¶ 5} In April 2016, DCH and the Port Authority filed a seven-count complaint against Garrett, Heitz, and the Chicago Title Insurance Company (“CTC“). These counts included: (1) breach of contract; (2) fraud; (3) negligent misrepresentation; (4) unjust enrichment; (5) promissory estoppel; (6) declaratory judgment as to a mechanic‘s lien; and (7) breach of escrow/declaratory judgment. Garrett and Heitz also filed counterclaims against DCH and the Port Authority, as well as a claim against Feldman, who was added as a counterclaim defendant pursuant to
{¶ 6} The claims of the parties arose from a July 2014 contract that DCH entered into with Garrеtt to purchase the Property. The Property had been abandoned for years and was the scene of many environmental contaminants. Doc. #116, Michael Heitz Affidavit, ¶ 13.
{¶ 7} The Property, which was located near DCH, “was originally developed in the early 1900‘s for the Bernard Focke Slaughter House. By 1950, the slaughter house was replaced with the Dayton Rustproofing Electroplating Works, which operated a plating facility. Several electroplating companies operated on the property until 1996. After closure, both Ohio EPA and US EPA investigated the site and determined that large quantities of hazardous materials and waste were still on the property. In 1997, US EPA issued orders to Dayton Electroplate to stabilize and abate chemical hazards. The company failed to comply. In 2007, US EPA initiated an emergency removal of all waste materials and the plating lines and tanks within the buildings.” Doc. #101, Michael Heitz Deposition, p. 51 and Ex. 8 (Development Agreement), Attachment A, Garrett/Valley Bates Stamp 04132.
{¶ 9} Before Garrett purchased the Property, Garrett‘s environmental lawyer was able to get between $600,000 and $1,000,000 in U.S. EPA liens removed. Garrett‘s lawyer also worked with the Ohio EPA to resolve pending violations of Dayton Electroplate. Heitz Deposition at p. 70. In addition, Garrett had financed a Voluntary Action Program (“VAP“) Phase I Assessment by KERAMIDA, which recommended “proper removal of Universal Waste, an asbestos inspection, and a subsurface investigation to evaluate soil and groundwater conditions” on the Property. Ex. 13, Covenant Not to Sue (“CNS“), Ohio EPA Director‘s Final Findings and Orders (February 29, 2016), p. 4; Doc. #98, Karen DeMasi Deposition 1, p. 58 and Ex. 84.
{¶ 10} In 2012, Garrett and the Montgomery County Land Bank (“Land Bank“) entered into a memorandum of understanding (“MOU“). Pursuant to the MOU, the Land Bank facilitated an expedited tax foreclosure on the Property through the Montgomery County Board of Revision. The Property was then transferred to Garrett in November 2012, in exchange for Garrett‘s promise to demolish the existing structures and fill in the basements. Id. at ¶ 3. In November 2012, KERAMIDA also proposed a Phase II Property Assessment Work Plan. See Ex. 13 at p. 5.
{¶ 11} Garrett contracted with a company named MCM Demolition (“MCM“) to demolish the buildings on the Property. MCM applied for and received a demolition permit for the Property in November 2012. Heitz Deposition at pp. 54 and 142-143, and Ex. 14-A; Doc. #97, Scott Adams Deposition, pp. 24-26. Before the permit
{¶ 12} In January 2013, a press conference was held at the Property as MCM began demolition of the buildings on the property. DCH‘s facilities manager, Edd McGathа, attended the conference. Doc. #106, Edd McGatha Deposition 2, p. 20. McGatha knew at that time that the Property had environmental contamination issues. Id. By July 2014, MCM had taken the buildings down to the concrete slabs. Garrett paid $180,000 to MCM to demolish the existing buildings before eventually signing a purchase contract with DCH. Heitz Deposition at p. 71.
{¶ 13} Previously, in March 2013, the Dayton City Commission authorized the City of Dayton to enter into a development agreement with Heitz to remediate and demolish the Property for future redevelopment. Id. at Ex. 8. Under the development agreement, Heitz was to complete a Phase II environmental assessment of the Property in accordance with the Ohio VAP and the Clean Ohio program, and demolish the Property. Ex. 8 at 04108. Phase I and II assessments indicate how “dirty” a site is and where contaminants are. A covenant not to sue can result from Phase I, Phase II, and remediation activities. Doc. #108, Matt Wagner Deposition, p. 129.
{¶ 14} In June 2013, the Ohio Controlling Board approved a Clean Ohio Fund grant for the project, which had been recommended by JobsOhio and the Ohio Development Services Authority (“ODSA“). See Ex. 8. The effective date of the grant was June 10, 2013, and the grant completion date was December 10, 2014. The grant agreement was between the City of Dayton and the Director of the ODSA. Ex. 8, Garrett/Valley Bates Stamp 04120. The project manager for the grant was Keith Klein, Senior Development Specialist for the City of Dayton. Id. Under the grant agreement, the City of Dayton was the grantee and received a grant amount of $195,654. Id.
{¶ 15} According to the description of the scope of work:
The project is in alignment with the City‘s plan for sustained growth in the DaVinci project area. This area is home to over 200 businesses and represents nearly 10,000 jobs within the City. * * * Redevelopment plans include a new medical office center either servicing the Children‘s Medical Center of Dayton or a doctor‘s group. COAF [Clean Ohio Assistance Fund] assistance will bе used to finance a Phase II Environmental Assessment to determine the environmental suitability of the Project Property and the possible need for any remediation.
The Phase II Environmental Assessment will include the installation of 48 soil borings (up to 10 feet), 12 shallow groundwater monitoring wells (up to 50 feet), one deep bedrock groundwater monitoring well, soil vapor points, as well as a geophysical survey, property survey and reporting. All assessment work will be conducted within the Project Property boundary.
Ex. 8 at 04132.
{¶ 16} The grant did not provide remediation or demolition funds; it only provided funding for a Phase II assessment. However, when the Phase II project was completed in May 2014, the total amount of the grant had not been exhausted. Garrett decided to finish the project and obtain a covenant not to sue or CNS, working in tandem with the City of Dayton, the EPA
{¶ 17} The DaVinci Project is the name of community development work that CityWide was conducting in two greater Dayton neighborhoods: McCook Field and Greater Old North Dayton. A staff team had been working on a comprehensive development plan since 2012. DeMasi Deposition 1 at p. 12. The Electroplate site, which was within the DaVinci area, was a challenge for the City of Dayton. “[T]here had always been a desire to have this site redeveloped. It remained inactive for 20, 30 years and just sat there as an eyesore.” Wagner Deposition at p. 25; McGatha Deposition 2 at pp. 19-20 (describing the property as an eyesore and environmentally contaminated).
{¶ 18} In September 2013, the Dayton City Commission approved the Development Agreement, signed by Dickstein for the Dayton City Manager and Heitz on behalf of Garrett. KERAMIDA, which had prepared the Phase I report, was in charge of preparing the Phase II assessment. KERAMIDA billed the City of Dayton and was paid directly by the City. Wagner Deposition at pp. 23-24 and 98. If costs exceeded the amount of the grant, Heitz was obligated to pay for the costs. Ex. 8. at 04109. The development agreement was to expire on December 31, 2015, unless extended or earlier terminated. Id. at 04110.
{¶ 19} In November 2013, Matt Wagner of KERAMIDA, Heitz, and Steve Ireland (Garrett‘s realtor) met with Edd McGatha and Deborah Feldman of DCH to discuss the Property. McGatha Deposition 2 at pp. 26-27. According to Feldman, this was a very general meeting. Heitz discussed the fact that he owned the Property and was working on remediating it. Doc. #100, Deborah Feldman Deposition, p. 9. Feldman knew there were environmental contamination issues with the Property. Id. She stated that this was a “meet and greet” with just general discussion, as DCH was not “even at the point of talking about purchasing the property.” Id. at p. 10.4
{¶ 20} On December 27, 2013, Ireland sent a letter of intent to Feldman, proposing to sell the Property to DCH for $238,750 plus $10,000 each for four residential parcels. The letter noted that with regard to the Property, Garrett would “remove concrete slab and insure all environmental concerns regarding Phase I and II [were] answered to the satisfaction of the buyer.” Doc. #102, Steve Ireland Deposition, p. 39, and Ex. 61. In mid-January 2014, Feldman informed Ireland via email that DCH had been working closely with Citywide as part of the broader development project, and that she had asked Karen DeMasi to represent DCH in any negotiations related to the purchase of the properties. Id. at p. 40 and Ex. 62.
{¶ 21} Subsequently, on January 21, 2014, DeMasi countered to Garrett with an offer of $175,000. As part of the agreement, DeMasi stated that DCH would send a letter to JobsOhio indicating its desire to take possession of the property and would “encourage the State to award additional grant money to this open project so that the Seller can complete environmental
{¶ 22} In the winter of 2014, Heitz met with John Scott of Bladecutters at the Property and asked for a demolition quote. Doc. #107, John Scott Deposition, p. 29. Subsequently, on May 9, 2014, the KERAMIDA VAP Phase II Assessment was submitted to the Ohio Department of Transportation. DeMasi Deposition 1 at p. 59 and Ex. 85. Keith Klein, who was in economic development at the City of Dayton, was copied with the material and would have shared a copy with CityWide. Ex. 85 at p. 1; DeMasi Deposition 1 at p. 60. The Phase II Assessment included “a geophysical survey of the lot, the installation of soil borings and monitoring wells and analysis of concrete samples for mercury and PCBs” Ex. 13, Ex. 3 attached to Exhibit 13 (December 13, 2015 Ohio EPA Director‘s Executive Summary, p. 5) (“Executive Summary“). As noted, the grant money was not exhausted, and a decision was made to pursue a CNS for the Property.
{¶ 23} According to Wagner (of KERAMIDA), after May 2014, but before the contract to purchase was signed in July 2014, there was a meeting with DCH. Heitz asked Wagner to participate based on the information that was going to be discussed, which was the Phase II assessment findings. At the meeting, they went over the general parameters of the findings and that it looked suitable for the project to go forward. There was discussion of the overall plan, which at that time was green space. Wagner Deposition at p. 44. The use of green space emerged based on what KERAMIDA had found in the soil and groundwater and the likelihood for future use. According to Wagner, DCH indicated that it needed or wanted more green space based on what DCH was doing at the corner of Stanley Avenue and Valley Street (creating an entrance into the hospital area). Green space fit better into DCH‘s plans. Id. at p. 45.
{¶ 24} Again, according to Wagner, McGatha brought up the fact that to make the property look better, it temporarily needed to be covered as green space; during this temporary time, there would have to be grass on the property, but demolition and removal of the concrete would still be necessary at the property. No demolition (other than removing the buildings) had occurred at that time. Wagner stated that “[t]he ultimate desire was that it was going to be developed into a medical office. However, based on discussions that were had, it was very clear that green space was likely the end result of the project.” Id. at pp. 47-48. The discussion was that, based on what they were finding in the soil and groundwater, the property‘s future was going to be green space. Id. at p. 59.5
{¶ 25} Due to his expertise and having talked to his certified professionals and engineers, Wagner wanted the concrete below ground to remain. He stated that
{¶ 26} On June 11, 2014, DeMasi sent an email of “high” importance to Feldman, Dickstein, and McGatha regarding Electroplate. In the email, DeMasi stated that:
I spoke to Steve Ireland today about the Electroplate site and Mike Heitz‘s plans. You will recall that without an end user that guarantees jobs, Mike cannot access Clean Ohio funds for remediation. This means that even if we had a deal with Mike to purchase this site, our use [of] “green space” would not get him funding from the State.
Steve said that Mike has decided to clean up the site using his own funds. He does not believe the site will be marketable unless he does this and he wants the “covenant not to sue” from the EPA which he will receive if he remediates to their standards. Apparently he does not have an end user at this moment that can guarantee jobs at the site.
If Dayton Children‘s wants to purchase, the price remains the same $75K per acre (3.2 acres x $75K = $240k). He will also tear down the adjacent house for $10k. So total cost for everything would be $250k. He would meet all the conditions outlined in his original agreement to him [sic].
We could offer him less money and clean up the site ourselves, but I am not sure we can do it any cheaper. Plus we need to consider the money he already has put in which is substantial. Personally, if the funding is available, I think we should try and get this site. Maybe we can get it for under $250k but I am thinking it will have to be at least $200k.
(Emphasis added.) DeMasi Deposition 1 at p. 90 and Ex. 88, p. 1.7
{¶ 27} DeMasi then reminded the recipients of the email about the investment Garrett had already made in the property. She noted that Garrett‘s estimated private investment to date was $5,000 for an application fee and title work with the Land Bank; $5,000 for a Phase I study; and $200,000 plus in demolition costs. Ex. 88 at p.1. The public investment for the Clean Ohio Grant for the Phase II work was $195,000, with Garrett being responsible for any cost overruns. Ex. 88 at p. 1.8
{¶ 28} Subsequently, in conversations with DCH, DeMasi prepared a June 14, 2014 letter of intent for the purchase of five parcels, including the Property, for $225,000. Among the seller‘s responsibilities with respect to the Property was that Garrett “[r]emove concrete slab.” DeMasi Deposition 1 at pp. 45-47 and Deposition Ex. 81. DeMasi testified that she understood “a slab as being held up by footers, foundations, and all of that.” Id. at p. 47. In addition, DeMasi stated that “There were numerous discussions with the parties
{¶ 29} In June 2014, DeMasi also prepared a request for Clean Ohio Funds to assist Heitz. DeMasi Deposition 1 at pp. 50-52 and Ex. 83. In this Clean Ohio request, DeMasi stated that a purchase agreement had been negotiated between DCH and Garrett and would be executed by August 1, 2014. After discussing DCH‘s economic role in the area and the 2014 announcement of a $140 million expansion of the hospital‘s Dayton campus, including a new 260,000 square foot, еight-story patient care center, DeMasi mentioned that clean-up of the Electroplate site was “vital to the economic interests of Dayton Children‘s Hospital and the revitalization of the community through the DaVinci Project.” Ex. 83 at p. 6. At the time, DeMasi understood that a condition of the grant was that it had to be tied to creating jobs. DeMasi Deposition 1 at p. 50. According to DeMasi, “that was kind of dicey, because there were no real plans.” (Emphasis added.) Id.
{¶ 30} Ireland, who prepared the purchase agreement, indicated that he used the language that had been sent to him by DCH, as reflected in Exhibit 81. Again, these terms included “[r]emove concrete slab.” Ireland Deposition at pp. 87-88. Before the property went under contract, Ireland and Heitz told DeMasi and McGatha that there was a lot more than just concrete slab on the property. There were also foundations and basements. DeMasi Deposition 1 at p. 57. DeMasi stated that she and Heitz had extensive discussions about what the demolition would be. She could not answer why they selected just the concrete slab, and did not just say to remove all concrete from the property. Id. at p. 77.
{¶ 31} On July 10, 2014, Bladecutters submitted a quote to Heitz for removing “concrete slab foundation & asphalt” at the Property. Scott Deposition at p. 30, and Ex. 28, Bladecutters’ Bates Stamp 0001. Together with other items like grading, backfilling with topsoil and seeding, and capping sewers, the total quote was $48,221. Id. However, a contract was not signed before the closing on the Property; instead, a contract that Garrett prepared was signed sometime in the fall of 2014. Scott Deposition at pp. 29-31. In July 2014, Garrett also submitted the new request for Clean Ohio funds. DeMasi believed Garret was going to use the grant to do further remediation on the Property. DeMasi Deposition 1 at p. 53. Apparently, the request was not approved, as there is no further mention of a grant from Clean Ohio.
{¶ 32} On July 23 or 24, 2014, DCH and Garrett signed a contract of purchase regarding the Property only. The Property was a vacant parcel of land, and the purchase
Seller represents that those signing the contract constitute all of the owners of the Property, together with their respective spouses. Seller further represents that with respect to the property (a) Seller shall remove concrete slab (b) insure all environmental concerns regarding Phase I and II are answered to the satisfaction of the buyer (c) Request & obtain a State of Ohio EPA “Covenant Not to Sue” letter prior to close regarding this property (d) De-rock & seed the property (e) that no orders of any public authority are pending (f) no work has been performed or improvements constructed that may result in future assessments, (g) no notices have been received from any public agency with respect to condemnation or appropriation, change in zoning, proposed future assessments, correction of conditions, or other similar matters.
Ex. 11 (Contract to Purchase), “Seller‘s Representations,” p. 2, ¶ 8.10
{¶ 33} The contract further provided that the “closing for delivery of the deed and payment of the balance of the purchase shall be scheduled 10 days after Purchaser receives a State of Ohio EPA ‘Covenant Not to Sue’ from the Seller.” Id. at p. 2, ¶ 11. In addition, the contract stated that it contained all the terms of the parties’ agreement and that there were “no oral conditions, representations, warranties or agreements.” Id. at p. 2, ¶ 12 (“General Provisions“). Furthermore, the contract said that “[u]pon Purchaser‘s examination of the Property as providеd herein, and except as otherwise provided in this Contract, Purchaser is accepting the Property ‘as is’ in its present condition (unless otherwise stated), relying upon such examination as to the condition, character, size, utility and zoning of the Property.” Id.
{¶ 34} An addendum to the contract (also included as part of the contract to purchase) gave DCH “the right to enter onto and into the property for tests, environmental and engineering studies and tests, surveys, planning and other testing and exploratory work necessary to formulate plans for the purchase of the Property * * *.” Ex. 11, Addendum, p. 4, ¶ 2. In the event that DCH made objections after inspection, a cure period was provided for Garrett to take actions necessary to cure the objection, and DCH had the right to cancel the purchase if Garrett were unwilling or unable to cure. Id. at ¶ 4-6.
{¶ 35} Finally, the Addendum provided that:
In addition to the representations and warranties set forth in the Contract to Purchase, Seller also represents and warrants to Purchaser as follows: * * * (c) to the best of Seller‘s knowledge, there is no violation or alleged violation of any legal requirement affecting the Property, including, without limitation, any violation or alleged violation of any zoning, subdivision, fire, safety, health, accessibility, environmental or other codes, laws, ordinances, statutes, regulations, rules or orders of any city, county, state and/or federal authorities with jurisdiction in these matters.
Id. at p. 5, ¶ 10.
{¶ 36} The addendum to the contract also stated that “Seller warrants that all information provided to Purchaser during due diligence is accurate, complete, and
{¶ 37} During the initial inspection period, DCH decided what inspections it wanted done. These included a title exam and a Phase 1 environmental study. DeMasi Deposition 1, at p. 104; McGatha Deposition 2 at p. 16. No one reviewed the records pertaining to demolition permits or inspections, although those were available online, and neither DCH nor its agents checked with the building department for permit status or to see if any violations existed. DeMasi Deposition 1 at pp. 105-106; McGatha at p. 66; Heitz Deposition at pp. 147-148.
{¶ 38} At that time, Section 153.16 of the City of Dayton Unified Building Code (R.C.G.O.) provided that:
Whenever any building or structure is demolished, in whole or in part:
(A) All structural elements and materials shall be completely removed from above and below the surface of the land, unless the building official approves partial removal thereof, based upon his or her determination that complete removal would be:
(1) Physically impractical;
(2) Harmful to a connected or adjacent structure, street, sidewalk, or alley;
(3) Environmentally unsafe, or require extensive environmental
remediation;
- If the complete removal will cause the property to be in violation of another applicable law, code, or regulation; or
- If the costs of complete removal are not economically justified in light of the intended uses of the property after demolition.
{¶ 39} Under the ordinances, the Building Official of the City was required to serve written notices of violations of the code provisions or of permits under the Code “on the person or persons responsible for such violation * * *.”
{¶ 40} MCM had completed all its demolition work (which related to the buildings) before July 2014, when the Contract to Purchase was signed. Heitz Deposition at p. 54. According to City records, a rough inspection of the Property was later rejected on October 6, 2014. Adams Deposition at pp. 25-26 and Ex. 45. There are two kinds of inspections: a rough inspection, where an inspector looks at a hole to make sure everything has been removed; and a final inspection. This latter inspection occurs
{¶ 41} The notes from the October 2014 rough inspection state: “rough rejected, dash, building has been demolished to slab foundation, dash, need to remove footer, foundation, and patch sewer.” Id. at p. 32 and Ex. 46. Both John Scott of Bladecutters and Heitz denied ever knowing about this rough inspection. Bladecutters did not begin its work until around January 2015, and a contractor does not have to be present during inspection, although it is up to a contractor to schedule inspections. Scott Deposition at pp. 35 and 37; Heitz Deposition at pp. 144-146; Adams Deposition at pp. 29 and 31. Failure of a rough inspection is not a violation. Heitz Deposition at p. 145; Adams Deposition at p. 127. No evidence was offered concerning whether anyone from Garrett or MCM was at the site when this rough inspection was done, and there was no evidence of any written notice to MCM or Garrett. Id. at p. 34.12
{¶ 42} The contact that was eventually signed in the fall of 2014 (and prepared by Garrett) required Bladecutters to “remove all concrete and asphalt except for sidewalks from the entirety of the property * * *.” Scott Deposition at pp. 31-32 and Ex. 29 at 0003. According to Scott, this was for demolition and removal of all the materials above and below the ground. Id. at p. 31.
{¶ 43} In early November 2014, DCH objected to certain conditions of the title commitment of CTC, and the parties then signed a First Amendment to the Contract in early December 2014, allowing Garrett until January 15, 2015 to evaluate and cure the defects. If Garrett were not able to do so, DCH could terminate the contract at any time before February 20, 2015, by giving written notice to Garrett. Ex. 11, First Amendment to Contract to Purchase, p. 1.
{¶ 44} In the meantime, a third meeting took place in late November 2014, and the participants were Heitz, Wagner, Ireland, and DeMasi. Wagner Deposition at pp. 63-64, and 68; DeMasi Deposition 1 at p. 70. The main point of discussion was the CNS, which was the reason Wagner was at the meeting. KERAMIDA had performed some additional investigations, so there was further data to talk about. This data was primarily related to the western part of the property, and the fact that some groundwater concerns were associated with it. KERAMIDA had some strategies to achieve a CNS on the Property and how that could still be obtained, but it would not be for the entire parcel. Wagner Deposition at p. 64. The solution KERAMIDA proposed for this concern was to parcel out the area for the CNS, which would still achieve the goal of the grant, which was to obtain a CNS. Id. at p. 67. However, obtaining a CNS fоr the entire property was not attainable because there were elevated levels of hazardous substances on the western part of the property and additional work would be required. Id. at pp. 68-69. This area could be cleaned up, but it was not within the parameters of the grant. Id. at p. 70. Before this meeting, the concrete had not been removed from below the surface. Id. at p. 74.
{¶ 45} According to DeMasi, there was discussion about Garrett completing the demolition and she was assured Garrett
{¶ 46} DeMasi indicated that the other part of the Property (not subject to the CNS) was not unbuildable, but would be limited as to what could be built. A parking lot could probably be built on it. If one wanted to spend the money to remediate it, anything could be built there. Wagner clearly indicated during the meeting that a lot more work would have to happen on the part of the Property that was not going to be subject to the CNS. Id. at p. 73.
{¶ 47} According to Wagner, options were discussed about how to move the project forward, such as scaling back the area covered by a CNS; having DCH enter into a 100-year lease on the contaminated piece; or bringing in two feet of fill to create a separation on the contaminated part as a remedial approach and still trying to allow the property to be further developed. Wagner Deposition at pp. 113-115. Wagner eventually left KERAMIDA in April 2015. However, he was told by his supervisor, Michael May, between this meeting and when he left, that only the concrete slab was going to be removed. Id. at pp. 76-77.
{¶ 48} On November 28, 2014, McGatha of DCH hired MAKSolve to do various tasks, including: (1) rеviewing KERAMIDA‘s Phase I and Phase II Assessments of the Property; (2) providing a professional opinion of the completeness of the work done to date; (3) giving insight, based on DCH‘s goals for the site, “into potential remedial strategies for possible future work and potential funding resources”; and (4) providing a professional opinion “in regard to the reasonableness of a verbal remedial cost estimate provided to Dayton Children‘s Hospital” by Heitz. Michael Kerr Deposition, Doc. #103, pp. 6-7 and Ex. 96. Kerr was unable to answer whether a report was generated because the work was performed by an independent contractor. Id. at p. 8.13
{¶ 49} By December 1, 2014, KERAMIDA had finished an amended Phase II Assessment, which included “results of additional sampling to define further metals and groundwork solvents in the south of the property.” Executive Summary at p. 5. At some point after December 1, 2014, when Phase II was completed, Wagner told the City of Dayton Economic Development Department that it would be best to leave the concrete below grade. Wagner Deposition at p. 141. This would have occurred after Phase II was completed, because Garrett and KERAMIDA would then have had the information. Id. The people present at this meeting were Wagner, Keith Klein, and Klein‘s supervisor, Timothy Downs. Id. at pp. 141-142. During direct discussion with the City of Dayton, when Wagner said it would be best to leave everything at or below ground level, no one from the City said that they could not do that. Id. at pp. 91-92.14
{¶ 50} In December 2014 or January 2015, Bladecutters started demolition work at the Property. Executive Summary at p. 11; Scott Deposition at p. 37.15 In January
{¶ 51} On January 13, 2015, DeMasi sent an email to Ireland, noting that she had noticed heavy equipment at the site. She asked Ireland: “Will they be removing all slabs & footers?” Ireland Deposition at p. 54 and Ex. 68. In addition, DeMasi asked about other items, including the status of the title issues and the CNS, and whether another contract extension was needed. Id. Ireland responded to DeMasi‘s email on January 15, 2015, stating, among other things, that “We are taking the slabs and footers up and have removed the two underground tanks which is required for the NFA [no further action letter] and CNS on the appropriate 1.4 acres of land toward Valley and Stanley.” Ireland Deposition at p. 54; Ex. 68. Ireland testified that he may have misspoken in this email, because the contract only required removal of the slab. Ireland Deposition at p. 69. He further said that he did not intend for this to be misleading, as he was more concerned about whether Garrett was in compliance with the NFA and CNS. Id. at pp. 70-71.
{¶ 52} Ireland also said that “I‘m assuming I carried it [the language] over from her email to me. I just parroted it back to her.” Id. at p. 72. Ireland could not recall if he called Heitz before making the statement about the slabs and the footers. Id. at pp. 54-55.16 Finally, Ireland stated that he had no idea what the City‘s permit requirements were, had not ever dealt with a demolition permit issue with the City of Dayton, and was not aware of a requirement of taking out all materials above and below the ground. Id. at p. 72.
{¶ 53} A few days later, Ireland wrote again to DeMasi and stated that “I met with Mike [Heitz] and he is underwater on the property in terms of his own expenditures. As a result, he is unable to make any concessions on the current price despite the changes to our deliverables. * * * He reminded me he had cleared, demolished and donated a number of properties on Valley to the benefit of the Hospital and he hoped that this could be considered as both good will and some level of consideration as we work through this process with the Ohio EPA.” Ireland Deposition at p. 55. Ireland believed this related to the discovery that Garrett could not furnish a CNS on the entire three-acre parcel. Id. at pp. 55-56.
{¶ 54} On January 26, 2015, Michael May, a “certified professional” from KERAMIDA, submitted a “no further action” (“NFA”) letter to the Director of the Ohio EPA, which described “the investigational and remedial activities undertaken at the Property.” See Ex. 13, Covenant Not to Sue, Director‘s Final Findings and Orders (February 29, 2016), pp. 1-2. May also submitted addenda to the NFA letter on May 28, 2015, August 27, 2015, and December 23, 2015. Id.
{¶ 55} A few days after the NFA was submitted to the EPA, DCH signed a Second Amendment to the Contract. The parties wanted to extend the time period within which Garrett could cure title defects
{¶ 56} On February 6, 2015, DCH sent out an email to DeMasi, Heitz, and Ireland, asking about their availability for a meeting on February 18 or 20, 2015. The meeting participants included McGatha, Feldman, DeMasi, Ireland, and Heitz. Ireland Deposition at p. 57, Ex. 70. Ireland could not recall anything being discussed at the meeting other than the CNS and NFA. Id. at p. 31.
{¶ 57} Wagner recalled attending a fourth meeting with DCH a few months after the November 2014 meeting, which is consistent with the February 2015 meeting. Wagner Deposition at p. 80-81. The meeting was a follow-up to confirm what they were doing. Id. at p. 81. He recalled that the participants in the meeting were himself, Heitz, Ireland, DeMasi, Feldman, and perhaps McGatha. Id. at p. 80.17 According to Wagner, there were discussions about leaving portions of concrete оn the site during the third or fourth meeting with DCH. Id. at p. 114. Wagner further said that “there was [sic] discussions of parking for green space and where that could occur. And if you left the concrete there, that would minimize the amount of work needed to be done.” Id. at pp. 114-115. Wagner was under the impression that it was acceptable to DCH to leave concrete on the site as long as it was covered with dirt. Id. at p. 115. He believed McGatha would have said that. Id. at p. 116. DCH just wanted a clean-looking site that would be esthetically pleasing as a gateway to DCH. Id. Wagner also thought a good strategy was to leave any concrete at grade or below in place to eliminate the direct contact pathway for human contact and the potential migration of contaminants from the dirty side of the Property to the clean side. Id. at p. 117-118.18
{¶ 58} In early February 2015, or about halfway through Bladecutters’ job, John Scott of Bladecutters requested a change to the contract regarding removing the foundations. Scott Deposition at pp. 33-34. At that time, Heitz told Scott that the foundation would not be removed because the Property was going to be parkland. Id. at p. 40. Scott and Heitz also discussed the fact that KERAMIDA would be out doing samples and that Heitz did not want to
{¶ 59} Scott then called the City of Dayton in April 2015 for an inspection of the Property. Scott Adams of the City‘s Division of Building Inspection came out and said there could not be any foundations in the ground. Scott Deposition at p. 50; Adams Deposition, pp. 42-44. Adams did not document this visit in the department‘s records, nor did he send Heitz a written notice about the issue. Id. at pp. 125-127. No notices of violations were ever issued and there were no orders by any public authority affecting the Property. Adams at pp. 103-104.19
{¶ 60} Scott testified that he told Heitz that Adams had said there could not be any concrete buried at the site; Heitz responded that he would take care of it. Scott Deposition at p. 51. Heitz initially said that he could not remember if Scott told him that he had met with the City of Dayton. Heitz Deposition at p. 113. Heitz then said he had never heard from Scott that there were any issues with the demolition work they did or did not do at the Property. Heitz at p. 115.
{¶ 61} About two weeks after Adams visited the site, Adams called Scott to ask why he had not completed the work as he had said he would. At that time, Scott said that Heitz was not going to pay him to remove the footers and foundation. Adams Deposition at p. 47.
{¶ 62} In April or May 2015, DCH engaged MAKSolve to look at the Valley Street property. DCH initially asked MAKSolve to evaluate funding opportunities in Ohio to assist with acquiring the Property. Kerr Deposition at pp. 5-6. Regarding the grant for DCH, Kerr recalled discussion about Ohio Brownfields redevelopment grants and JobsOhio grants. However, none of those funding sources would work because they all required that jobs be created or moved to the site. Id. at p. 15.
{¶ 63} As noted, DCH had until September 1, 2015 under the Second Amendment to cure the defects and obtain the environmental covenants. However, in May or June 2015, Feldman called a meeting with Heitz. According to Feldman, things were not moving along and they had some delays. DCH wanted to get together with Heitz and see what could be done to expedite and resolve the contract so they could close. Feldman Deposition at p. 45. They still did not have a covenant not to sue, and so that was probably the issue that brought them to the table. Id. DCH and Garrett ended up amending the contract a third time based on a number of issues.
{¶ 64} Heitz testified that the parties talked about the whole project in May 2015, including thаt Garrett would take the cement slab off and go down four inches on the foundation, fill it up with soil, and then plant grass on top of it. DCH told him to do that because they hospital did not want to develop the property; it just wanted
{¶ 65} The slab was already gone by May 2, before the Third Amendment to the Contract. Id. at pp. 109-110. According to Heitz, the $25,000 reduction in price was because Garrett was not going to take out the foundations on the buildings as well. To take out the slab was the task for which Garrett had paid Bladecutters $50,000. The slabs were not the most dangerous part to move; taking out the foundations was, because it involved moving the soil. The foundations acted as a barrier to chemicals that had gone into the soil. Id. at pp. 106-109. Heitz also said that Bladecutters had been going to remove everything, including the foundations for $75,000, but had reduced its price by $25,000. Heitz Deposition at pp. 119-120.20
{¶ 66} By the time of the Third Amendment, DCH had decided to accept “as is” the part of the property that did not have a pending CNS and was not “shovel ready.” Feldman Deposition at p. 62. Heitz denied ever telling DCH that the site would be “shovel ready” for DCH‘s purposes. Heitz Deposition at p. 169.
{¶ 67} Because DCH still wanted to purchase the property, DCH and Garrett agreed to reduce the price by $25,000, to $200,000. Feldman Deposition at p. 47. They also added a condition precedent to Garrett‘s obligations that it would consent to DCH‘s assignment of its own contractual obligations to the Port Authority or another entity that DCH identified. Id. at p. 48 and Ex. 11, Third Amendment at p. 1.
{¶ 68} Under the Third Amendment, DCH acknowledged that Garrett intended for the transfer to be a “bargain-sale” for federal tax purposes; DCH also agreed to sign such documents at closing that Garrett would reasonably require, including an “Acknowledgment” IRS form 8283, to substantiate Garrett‘s charitable contribution. Id. at p. 2. The parties further agreed that Garrett‘s obligation to satisfy the environmental conditions only applied to the Remеdiated Property (the CNS part), that if these conditions were not satisfied at closing, they would continue until satisfied in full, and that to secure Garrett‘s obligations, the parties would agree to an escrow agreement substantially like Ex. B, which was attached to the Third Amendment. Id. To secure post-closing obligations, the parties agreed that $40,000 would be placed with CTC in an escrow account and would be retained until Garrett received and delivered the EPA‘s Covenant Not to Sue. Id.
{¶ 69} In addition, the parties agreed that the closing would take place on or before June 15, 2015. Id. at p. 3. The Third Amendment also said that “[i]n all other respects, the Agreement is hereby ratified and affirmed and shall remain in full force and effect.” Ex. 11, Third Amendment at p. 3.
{¶ 70} The Third Amendment was effective May 27, 2015. On June 10, 2015, DCH signed a proposal by MAKSolve to conduct a Phase I Environmental Site Assessment of the Property. Kerr Deposition at p. 19 and Doc. #97. Under the scope of work,
{¶ 71} Further, MAKSolve was to try “to contact the local fire, health, building, zoning, water and sewer departments for information on known or suspected environmental impacts such as fires, spills, releases and violations associated with the property.” Doc. #97, at p. 1. MAKSolve was also to be provided “means of access to the property for purposes of conducting the required site reconnaissance.” Id. at p. 2. Moreover, within 48 hours after this reconnaissance, MAKSolve was to provide a “verbal assessment.” A formal written report was also to be delivered to DCH within 10 days after the reconnaissance. Id.
{¶ 72} On June 12, 2015, DCH and Garrett signed a Fourth Amendment to the Contract, agreeing to extend the closing date tо July 10, 2015. See Ex. 11, Fourth Amendment. Subsequently, in late June 2015, DeMasi asked Ireland if DCH could add fill to the lot before taking possession, because Danis Construction was hauling away fill from another project on DCH property. Ireland Deposition at pp. 60-61. Ireland then sent Heitz an email, stating that “I realize we are very close to close and I also told her we have already been punished by the City of Dayton for backfilling the site and covering where the concrete pad once stood. I also let her know you were not happy about that and she [should] also check with the city.” (Emphasis added.) Ireland Deposition at p. 60 and Ex. 72. Ireland testified that he believed “we” was a reference to Garrett. Ireland did not know what the actual punishment was. He believed Garrett may have been criticized because it had removed the concrete pad, backfilled it, and covered it with dirt, but apparently no one had inspected its removal. He received information from Heitz that the City was apparently not happy with that. Id. at pp. 62-63.
{¶ 73} Although Garrett had given permission for filling the lot, DeMasi told Ireland on July 7, 2015, that DCH did not dump dirt on the site before closing because it was applying for grants. Id. at pp. 64-65 and Ex. 73, pp. 1-2. DeMasi stated that the hospital expected Garrett to de-rock, grade, and seed the entire site because it needed to look good in the interim. Id. Ireland notified Heitz of this, and also copied Heitz‘s son, Cory, with his email, because Heitz was on a bicycle at the time, somewhere in Canada. Id. at p. 6.
{¶ 74} On July 8, 2015, DCH and the Dayton Reserves signed an assignment and assumption agreement, pursuant to which DCH assigned its interest in the Contract to Purchase to Dayton Reserves, LLC (“Reserves”), which was a for-profit corporation previously set up to help CityWide with holding property for various reasons. Doc. #126, Affidavit of Karen DeMasi, ¶ 5. The agreement was in final form and both parties signed the agreement; the only thing missing was the notarization of the signatures of the Reserves’ officers. Doc. #132 (Corrected Ex. 95); DeMasi Deposition 1 at pp. 139-140.
{¶ 75} Subsequently, on July 10, 2015, DCH and Garrett signed a Fifth Amendment to the Contract. Ex. 11, Fifth Amendment. Heitz‘s son, Cory, was a member of Garrett and signed on Garrett‘s behalf. Heitz Deposition at pp. 84-85. This agreement was for an extension of the closing date to July 23, 2015. Id. at Ex. 11. At some point, DeMasi had realized that the Reserves could not give Garrett a charitable bargain sale because the Reserves
{¶ 76} Under the development agreement, the Project would be deemed completed on the earliest occurrence of one of three conditions (The Completion Date). One of these conditions was when the CNS was obtained. Ex. 37 at p. 4. The Port Authority was then required to transfer all its interest to DCH no later than 30 days after the Completion Date. The CNS was obtained on February 29, 2016. McGatha Deposition 1 at pp. 42-47; Ex. 37 at p. 4; and Ex. 13. However, the Port Authority did not transfer its interest before the complaint in this case was filed. In fact, the transfer did not occur until July 27, 2017. See Doc. #127, Second Affidavit of Edd McGatha.
{¶ 77} The closing on the Contract to Purchase took place on July 24, 2015. DeMasi Affidavit at ¶ 10; McGatha Affidavit at ¶ 9. Because all the closing conditions had not been satisfied, CTC, Garrett and the Port Authority entered into an Escrow Agreement. McGatha Deposition 1 at pp. 129 and 131-132, and Ex. 12. Again, CTC, as escrow agent, was to retain $40,000 of the purchase price until Garrett satisfied the closing conditions that had not been met. Ex. 12 at p. 1. With all other deductions and credits, the amount of cash due to Garrett at settlement was $137,499.35. Id. at Ex. 12, Ex. B to Escrow Agreement (Closing Statement), p. 2. The conditions that had not been met were listed in Exhibit A, attached to the Escrow Agreement, and were as follows:
1. Complete remediation and clean-up of environmental conditions listed in the Phase I and Phase II environmental site assessments completed by the Seller for the Remediated Property and obtain a “Covenant Not to Sue” letter from the Ohio EPA as to the Remediated Property; and
2. De-rock, grade, and seed the Property.
Ex. A to Escrow Agreement; see also Feldman Deposition at p. 61; Heitz Deposition at p. 135.
{¶ 78} A few days after the closing, DeMasi contacted Ireland to ask when the de-rocking and grading of the Property would occur. Ireland Deposition at p. 65 and Ex. 74. DeMasi also emailed Cory Heitz, about this on July 31, 2015, but there is no indication of what the responses were to DeMasi‘s inquiry. Id. at p. 66 and Ex. 75. On August 12, 2015, DeMasi sent an email to Ireland, indicating that she had spoken to Scott Adams at the City of Dayton, and that there was nothing unusual about the City‘s request regarding the demolition at Electroplate. Id. at p. 67 and Ex. 76. DeMasi further stated that:
* * * It is routine to call for an inspection before the demolition site is filled in. It is a mystery why Bladecutters (who Garrett Day hired to complete the demo) did not follow this simple routine procedure.
Bottom line is there is not going to be a sign off on the demolition until someone digs up the site and proves the foundation was removed and the sewer lines were capped. * * * Without the sign off from the City, future use of the site is totally compromised. I had to relay this news to Dayton Children‘s and not surprisingly they are very unhappy.
{¶ 79} On September 10, 2015, Ireland sent an email to DeMasi, indicating they would have clarity on the de-rocking and reseeding soon. DeMasi Deposition 2 at p. 153 and Ex. 126. DeMasi then wrote the following email to Ireland on September 10, 2015:
* * * Since our discussion about de-rocking, I have done some investigation.
Here is what I know to be true about the Electroplate site:
1. On October 6, 2014 Garrett-Day/Mike Heitz was informed by the City that they did not pass their rough demolition inspection.21 The reason given was that the footers and foundations were still in the ground and the sewer lines were not properly capped. (Note: this was nine months before we closed)
2. The City Building Inspector asked Bladecutters to meet then [sic] at the site a few weeks ago. Bladecutters dug up a few holes which showed that the footers in fact were still there. Using ground penetrating radar I have confirmed that there is still a lot of stuff in the ground. I won‘t have the final report until next Wednesday that gives me total details on how much.22
3. Mike Heitz met with the City‘s Chief Building Inspector while he was in town this weekend and claims that the former building inspector, Mike Cromartie gave him a variance which allowed him to leave the stuff in the ground. However, the City has no copy of the variance. This is odd, because if a variance had been granted why not produce it in October when the Building Inspector inquired about the demolition? In addition, in the rare case when a variance is granted, it has to be signed off by an assistant city manager, in this case Shelley Dickstein.23 Since Shelley sits on the DaVinci investment board and is well aware of our work to acquire
Electroplate, I think she would have told me if a variance had been granted.
4. Mike Heitz also met with Mayor Whaley to tell her that Dayton Children‘s was fine with him leaving footers, foundations, etc., in the ground. Just so you are clear, they are not.
Ex. 126 at pp. 1-2.
{¶ 80} On October 8, 2015, Dickstein sent a letter to Heitz about several projects, including the Property. Adams Deposition at p. 58 and Ex. 43. The letter was prompted by Garrett‘s failure to complete
{¶ 81} Heitz‘s position was that he did not need to do anything further about Dickstein‘s issues because he no longer owned the Property and there were no violations on the Property when the closing occurred. In addition, Garrett was denied access to the Property. Heitz Deposition at pp. 113, 139-140, and 177. At some point in the fall of 2015, DCH had denied Heitz access to the Property. McGatha Deposition 1 at pp. 133-135.
{¶ 82} In early November 2015, MAKSolve gave DCH an estimate for completing demolition and closing the demolition permit. The amount of the proposal was $184,150. Kerr Deposition at p. 48 and Ex. 101. The hospital made the decision to do additional demolition based on the MAKSolve surveys. McGatha Deposition 1 at pp. 140-141. In response to a question about whether anyone asked for an exception to removal of all the concrete, McGatha stated that no one did anything to evaluate that possibility or went to the City to ask if DCH had to complete the demolition. Id. at pp. 141-142.
{¶ 83} Subsequently, on January 12, 2016, Garrett filed a mechanic‘s lien in the amount of $40,000 against the Property. Heitz Deposition at p. 154 and Ex. 17. Then, on February 29, 2016, the Ohio EPA issued the CNS for 1.4 acres of the Property. The CNS limited the Property to commercial or industrial land use. It also released Garrett and the Port Authority (and their successors or assigns) from all civil liability from the State to perform additional investigational and remedial activities. See Ex. 13 and Covenant Not to Sue, Director‘s Final Findings and Orders (February 29, 2016) at pp. 2 and 4, and Ex. 1 attached to the Director‘s Final Findings. The CNS was to “remain in effect for as long as the Property continues to comply with the applicable standards upon which the Covenant is based * * * ” Id. at p. 5. The EPA also retained oversight and access to the Property at reasonable times. Id. at p. 6. According to Heitz, the Ohio EPA had inspected the monitoring wells at the Property a week before the CNS was issued. Heitz Deposition at pp. 92-94.
{¶ 84} On March 10, 2016, MAKSolve applied for a demolition permit for the Property, and a permit was issued on March 29, 2016. Adams Deposition at pp. 36-67 and Ex. 48. The City of Dayton gave final approval of the demolition in late August 2016. Adams at p. 12, Ex. 43, Bates Stamp DAYTON006. According to MAKSolve, the cost of the demolition was $323,848.03. Doc. #113, Kerr Affidavit, ¶ 6 and Ex. 2 to the affidavit p. 3.
{¶ 85} Garrett did not receive the signed 8283 charitable contribution form from the Port Authority by April 15, 2016. Feldman did not know why the Port Authority refused to sign this form (which was dated May 4, 2016) before the tax deadline. Feldman Deposition at p. 80 and Ex. 18.
{¶ 86} As noted, DCH and the Port Authority filed a complaint against Garrett, Heitz, and CTC on April 20, 2016 for breach of contract, fraud, and other claims. At the time, the Port Authority had not assigned its claims and rights under the contract to DCH. Doc. #127, Second McGatha Affidavit. In May 2016, CTC filed
{¶ 87} In June 2016, Defendants filed an answer, a counterclaim against Plaintiffs, a counterclaim against Feldman, and a third-party complaint for foreclosure. Feldman was added as a counterclaim defendant. The counterclaim contained the following claims: (1) breach of contract against DCH; (2) breach of escrow agreement against DCH and the Port Authority; (3) tortious interference of contract and business against DCH; (4) fraud against DCH and Feldman; and (5) foreclosure of the mechanic‘s lien against the Port Authority.
{¶ 88} In August 2016, Plaintiffs replied to the counterclaim. On the same day, thеy also filed a motion to dismiss the counterclaim or to render judgment on the pleadings on counts four and five of the counterclaim. After Defendants responded and also filed their own motion for judgment on the pleadings as to DCH‘s claim in count one and to both DCH‘s and the Port Authority‘s claims in counts two, three, four, and five, the trial court overruled both motions.24 However, in April 2017, the Port Authority dismissed the following claims against Garrett, without prejudice: fraud, negligent misrepresentation, unjust enrichment, and promissory estoppel. See Doc. #86.
{¶ 89} Subsequently, both sides filed motions for summary judgment in July 2018. After considering the issues and the material submitted, the trial court sustained DCH‘s and Feldman‘s motion for summary judgment as to Defendants’ fraud claim (count four of the counterclaim). The court also sustained Defendants’ summary judgment motion as to the fraud and negligent misrepresentation claims in Plaintiffs’ complaint (counts two and three). In all other respects, the summary judgment motions were denied. The trial court included a
{¶ 90} We concluded that the judgment was a final appealable order, but limited our consideration to the parts of the decision that were final and appealable under
II. Summary Judgment on DCH‘s Fraudulent Inducement Claim
{¶ 91} Plaintiffs’ cross-assignment of error states that:
The Trial Court Erred by Granting Summary Judgment to Garrett Day and Heitz on Children‘s Fraudulent Inducement Claim.
{¶ 92} Under this cross-assignment of error, DCH argues only that the trial court erred in granting summary judgment on grounds other than those raised by Defendants. See Plaintiffs’ First Response Brief, pp. 19-20 and Reply Brief of Plaintiffs, pp. 7-8.25 DCH does not assert error regarding the summary judgment granted to Defendants on DCH‘s negligent misrepresentation claim.
{¶ 93} In its decision, the trial court noted that DCH did not file for summary judgment on its fraud claim. Doc. #172, p. 10. In beginning its analysis of Defendant‘s motion for summary judgment on that claim, the trial court described the basis of DCH‘s fraud claim, as follows:
DCH averred that prior to entering into the contract, Defendants falsely represented that they would remove all “concrete slab” at the property. Compl. at ¶¶ 34-35. DCH asserted that Defendants falsely represented that it [sic] had removed all of the concrete-related materials, and they also “failed to disclose that they had not complied with the City of Dayton permit requirements for demolition and removal of concrete at the Property * * * .” Id. at ¶¶ 35-36. DCH further asserted that Defendants had a duty to disclose “the concrete-related materials and permit and other legal issues * * * ” Id. at ¶ 40.
Doc. 172 at pp. 10-11.
{¶ 94} The trial court also observed that Defendants did file for summary judgment on the fraud claim of DCH. Id. at p. 11. The court then summarized various arguments that Defendants made, including that “DCH failed to cite to any representation or concealment that exists independent of the contract.” Id., citing Defendant‘s Summary Judgment Motion at p. 8. After considering the arguments, the trial court concluded that summary judgment should be granted to Defendants for these reasons: (1) DCH‘s fraud claim duplicated its breach of contract claim and was not viable; (2) DCH failed to show that Defendants “owed a duty separate and apart from their contractual duties“; and (3) DCH did not allege any extra-contractual damages. Id. at pp. 13-14.
{¶ 95} In reviewing decisions granting summary judgment, we apply a de novo standard, “which means that we apply the same standards as the trial court.” GNFH, Inc. v. W. Am. Ins. Co., 172 Ohio App.3d 127, 2007-Ohio-2722, 873 N.E.2d 345, ¶ 16 (2d Dist.). “Summary judgment is aрpropriate if (1) no genuine issue of any material fact remains, (2) the moving party is entitled to judgment as a matter of law, and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and construing the evidence most strongly in favor of the nonmoving party, that conclusion is adverse to the party against whom the motion for summary judgment is made.” State ex rel. Duncan v. Mentor City Council, 105 Ohio St.3d 372, 2005-Ohio-2163, 826 N.E.2d 832, ¶ 9, citing Temple v. Wean United, Inc., 50 Ohio St.2d 317, 327, 364 N.E.2d 267 (1977).
{¶ 96} Under established law, parties seeking summary judgment must
{¶ 97} However, as the court stressed in Mitseff, this “does not mean the non-moving party bears no burden. Requiring that the moving party provide specific reasons and evidence gives rise to a reciprocal burden of specificity for the non-moving party.
{¶ 98} After reviewing the record and the trial court‘s decision, we find no error. Contrary to DCH‘s claim, Defendants adequately raised the issues upon which the trial court granted summary judgment. In their motion for summary judgment, Defendants initially raised seven points, including matters such as the fact that the contract was an “as is” contrаct and Defendants had no duty to disclose latent defects; and the fact that there was no duty to remove or disclose any information about underlying materials because the contract called for removal of only the concrete slab. Doc. #115, Joint Motion for Summary Judgment, p. 7. However, Defendants went on to note, as the trial court indicated, that “[n]either DCH or the Port [Authority] can cite to a representation or concealment related to a non-contractual obligation as the basis for a fraud claim.” Id. at p. 8.
{¶ 99} In addition, when discussing the fraud claims against Heitz individually, Defendants stated that “[a]ny alleged fraudulent statements made by Heitz prior to forming the Contract are precluded by the fully integrated Contract itself, and such claims fail as a matter of law.” Id. Defendants also discussed these issues, citing to pertinent authority. Id. at pp. 8-9.
{¶ 100} Thus, DCH was not surprised about the basis for summary judgment and had an adequate chance to respond. In fact, in Plaintiffs’ memorandum in opposition to Defendants’ motion for summary judgment, Plaintiffs spent a substantial amount of time discussing the fraud claims asserted by both sides. See Doc. #130, Plaintiffs’ Memorandum in Opposition to Defendants’ Motion for Summary Judgment, pp. 36-44. In particular, Plaintiffs discussed the fact that a fraud claim cannot exist when an explicit written contract exists; they also argued that Defendants’ fraud claim was precluded by the integration clause in the contract. Id. at pp. 38-39.
{¶ 101} Accordingly, we find no merit in Plaintiff‘s assertion that the basis for summary judgment was not adequately raised, and that they did not have an opportunity to adequately respond.
{¶ 102} Assuming that DCH had also challenged the merits of the summary
{¶ 103} Although evidence of negotiations and agreements outside the execution of a written contract are normally excluded due to the parol evidence rule, this rule “does not prohibit a party from introducing parol or extrinsic evidence for the purpose of proving fraudulent inducement.” Galmish v. Cicchini, 90 Ohio St.3d 22, 27-28, 734 N.E.2d 782 (2000). “A claim of fraud in the inducement arises when a party is induced to enter into an agreement through fraud or misrepresentation. * * * In order to prove fraud in the inducement, a plaintiff must prove that the defendant made a knowing, material misrepresentation with the intent of inducing the plaintiff‘s reliance, and that the plaintiff relied upon that misrepresentation to her detriment.” ABM Farms, Inc. v. Woods, 81 Ohio St.3d 498, 502, 692 N.E.2d 574 (1998). Generally, “fraud cannot be predicated upon promises or representations relating to future actions or conduct.” Tibbs v. Natl. Homes Constr. Corp., 52 Ohio App.2d 281, 286, 369 N.E.2d 1218 (1st Dist.1977).
{¶ 104} “Fraudulent inducement must be proven by clear and convincing evidence.” Simon Property Group, L.P. v. Kill, 3d Dist. Allen No. 1-09-30, 2010-Ohio-1492, ¶ 17, citing Mid-America Tire, Inc. v. PTZ Trading Ltd., 95 Ohio St.3d 367, 2002-Ohio-2427, 768 N.E.2d 619, ¶ 62. The Supreme Court of Ohio has also stressed that ” ‘a fraudulent inducement case is not made out simply by alleging that a statement or agreement made prior to the contract is different from that which now appears in the written contract. Quite to the contrary, attempts to prove such contradictory assertions [are] exactly what the Parol Evidence Rule was designed tо prohibit.’ ” (Citation omitted.) Galmish, 90 Ohio St.3d at 29, 734 N.E.2d 782.
{¶ 105} In its decision, the trial court did not reject evidence or the claims based on the parol evidence rule. Instead, the court concluded that DCH‘s claim for fraud duplicated its contract claim and was not viable. Doc. #172 at p. 13. We agree.
{¶ 107} The court of appeals further observed that “[a] tort claim based upon the same actions as those upon which a claim of contract breach is based will exist independently of the contract action only if the breaching party also breaches a duty owed separately from that created by the contract, that is, a duty owed even if no contract existed.” Id., citing Battista v. Lebanon Trotting Assn., 538 F.2d 111, 117 (6th Cir.1976). Our district has agreed with this position. See Argrov Box Co. v. Illini Four Co., 2d Dist. Montgomery No. CA-6947, 1981 WL 2827, *4 (June 15, 1981); Kane v. Mazer Corp., 2d Dist. Montgomery No. 11614, 1990 WL 74021, *1-2 (May 29, 1990); Duncan v. Fifth Third Bank, 2d Dist. Greene No. 2018-CA-50, 2019-Ohio-3198, ¶ 22. In the case before us, DCH has not pointed to an independent duty that Garrett owed even if the contract did not exist.
{¶ 108} Notably, a breaching party‘s motive is irrelevant in a contract action. Textron at 151, citing Wolfe at 710. Accord Twin Maples Veterinary Hosp. v. Cincinnati Ins. Co., 159 Ohio App.3d 590, 2005-Ohio-430, 824 N.E.2d 1027, ¶ 24 (2d Dist.). Thus, in Textron, the court found that the “[t]he additional allegation of an intentional failure to obtain Textron‘s consent to the upgrade by claiming concealment does not change the contractual nature of Textron‘s claim.” (Emphasis sic.) Textron at 151.
{¶ 109} In the case before us, even though the parties renegotiated several times, the obligation to “[r]emove concrete slab” remained constant.27 The Third Amendment (like the other amendments) specifically noted that in all respects other than the agreed changes, the Contract to Purchase “is hereby ratified and affirmed and shall remain in full force and effect.” Ex. 11, Third Amendment at p. 3. As in Textron, the fraud claim and alleged breach both relate to the contract, i.e., that Garrett did not remove all the concrete as required and did not comply with the City‘s demolition ordinances, which the contract may also have required (although in an unspecific and indirect manner). The trial court made specific mention of the fact that the claims were identical, by comparing the misrepresentations cited in DCH‘s motion for summary judgment and the allegations of DCH‘s contract claim. Doc. #172 at p. 13. Having done so, the court concluded that the claims were factually intertwined and could not be separated. Id.
{¶ 110} Furthermore, the fraud claim was also not viable because Garrett had
{¶ 111} As an additional ground, the trial court rejected the tort claim because DCH failed to claim damages independent of those that arose from the breach of contract. Doc. #172 at p. 14, citing Kott v. Gleneagles Professional Builders & Remodelers, Inc., 197 Ohio App.3d 699, 2012-Ohio-287, 968 N.E.2d 593, ¶ 15 (6th Dist.) and Med. Billing, Inc. v. Med. Mgmt. Sciences, Inc., 212 F.3d 332, 338 (6th Cir.2000). Again, we agree with the trial court. Our review of the record failed to disclose any damages that DCH claimed, other than those attributed to the removal of the remaining concrete by MAKSolve. DCH has not disputed this point.
{¶ 112} Based on the preceding discussion, Plaintiffs’ sole cross-assignment of error is overruled.
IV. Defendants’ Claim for Fraudulent Inducement
{¶ 113} Defendants’ sole assignment of error states that:
The Trial Court Erred in Granting Summary Judgment to DCH and Feldman on Garrett and Heitz‘s Fraudulent Inducement Claim.
{¶ 114} In count four of the counterclaim, Defendants alleged that they had been damaged by DCH‘s false representations in an amount in excess of $25,000. This claim is based on allegations that during negotiations for the Third Amendment, DCH and Feldman falsely represented that if Garrett agreed to reduce its purchase price to $200,000, DCH would execute all documents that Garrett reasonably needed to treat part of the sale proceeds as a charitable donation for tax purposes. Garrett also alleged that DCH and Feldman discussed holding part of the sales proceeds in escrow and that they would not deny Garrett access to the Property. According to the counterclaim, DCH prevented Garrett from accessing the Property after the closing. Doc. #29, pp. 20-22 and 24. Forms for the charitable donation were also not signed in time for the 2015 tax year.
{¶ 115} As with DCH‘s fraud claim, the trial court concluded that Defendants’ fraud claims were duplicative of their claims for breach of the contract and breach of the escrow agreement, and were factually intertwined with the contract claims. The court further held that Defendants’ claimed damages were the same as those alleged for breach of contract.
{¶ 116} According to Defendants, the trial court misapplied the merger and parol evidence rules because fraud cannot be merged into a contract when the alleged fraudulent inducement is consistent with the written terms of the contract. As noted, the trial court did not rely on the parol evidence rule.
{¶ 117} Defendants further argue that a promise pertaining to future conduct can be the basis for fraudulent inducement if the promisor did not intend to keep its promise when the promise was made. In this vein, Defendants contend that the trial court erred by failing to examine and discuss any evidence indicating whether DCH and Feldman intended to keep their promises when the Third Amendment was signed. Following this discussion, Defendants point to evidence they believe shows
{¶ 118} In its decision, the trial court stated as follows:
The Court further agrees with Plaintiffs and Ms. Feldman that the allegation in paragraph four of Defendants’ Counterclaim, i.e., that Ms. Feldman and DCH represented that DCH would not deny Garrett Day access to the property to complete the escrow tasks, is a promise relating to future conduct that cannot serve as a basis for fraudulent inducement unless it is demonstrated that DCH and/or Ms. Feldman had no intention of keeping its promise at the time the promise was made.
(Emphasis sic.) Doc. #172 at p. 30.
{¶ 119} This was not the only basis for the court‘s decision, however. As noted, the court had several reasons for granting summary judgment in favor of DCH on this claim. Furthermore, in rejecting the fraudulent inducement claims of both DCH and Defendants, the trial court cited case law regarding the lack of viability of tort claims where the tort and contract claims are intertwined. See Doc. #172 at pp. 13 and 31, citing Thornton v. Cangialosi, S.D.Ohio No. 2:09-CV-585, 2010 WL 2162905, *3 (May 26, 2010). Not only is Thornton instructive in that respect, but the federal court (applying Ohio law) also discussed the exception that Defendants have raised. Specifically, the court stated that:
As a general rule, a fraud claim “cannot be predicated upon promises or representations relating to future actions or conduct.” Tibbs v. National Homes Constr. Corp., 52 Ohio App.2d 281, 286, 369 N.E.2d 1218, 1222 (Ohio Ct.App.1977). However, an exception exists “where an individual makes a promise concerning a future action, occurrence, or conduct and, at the time he makes it, has no intention of keeping the promise.” Williams v. Edwards, 129 Ohio App.3d 116, 124, 717 N.E.2d 368, 374 (Ohio Ct.App.1998).
Id. at *3.
{¶ 120} The court noted that the plaintiffs in that case had alleged that the defendant made certain misrepresentations when the contract was signed that they had relied on (such as his promise to buy back their stock and that he had sufficient net worth to do so), but had no intention of keeping those promises when the contract wаs signed. Id. However, the court concluded that this was “not the relevant question.” Id. Instead, “[t]he question [was] whether such a claim is viable in light of the concurrent breach of contract claim.” Id. The court then commented that:
As noted above, an independent tort claim is viable only if Plaintiffs can show that Cangialosi owed a duty separate and distinct from his contractual duties. As the Supreme Court of Ohio noted in ABM Farms, a claim of fraudulent inducement typically involves “a misrepresentation of facts outside the contract or other wrongful conduct [inducing] a party to enter into the contract. Examples include a party to a release misrepresenting the economic value of the released claim, or one party employing coercion or duress to cause the other party to sign an agreement.” 81 Ohio St.3d at 503, 692 N.E.2d at 578 (emphasis added). In other words, the claim involves some collateral misrepresentation designed to induce the plaintiff to enter into the contract. See also Wall v. Planet Ford, Inc., 159 Ohio App.3d 840, 850-51, 825 N.E.2d 686, 694 (Ohio Ct.App.2005) (giving an example of a termite inspector falsely representing that a house is infested with termites in order
to induce the homeowner to enter into a pest control contract).
Id. at *3
{¶ 121} After making these remarks, the federal court noted that the plaintiffs had failed to show that the defendant made any misrepresentations that were collateral to the contract. Because they failed to do so, the court stated that the defendant‘s lack of intention to keep promises at the contract‘s outset could not save their fraudulent inducement claim. Id. at *4.
{¶ 122} The situation here is similar. All the alleged statements of Feldman or DCH did not relate to collateral misrepresentations; they related to contractual duties. With regard to de-rocking and reseeding, the Port Authority (to whom DCH had assigned its rights and duties) agreed to “take any and all actions reasonably necessary to causе the satisfaction of the Closing Conditions in a timely manner * * * “. See Ex. 12 at p. 2, ¶ 3. And, concerning the signing of the tax form, that was nothing more than a contractual promise made in the Third Amendment. See Ex. 11, Third Amendment at p. 2, ¶ 2.
{¶ 123} The same observations are obviously true with respect to DCH‘s claim against Defendants (which we have already addressed). The actions that DCH points to as fraudulent inducement are not collateral to the Contract to Purchase.
{¶ 124} Having reviewed the record, there is simply no evidence that Defendants’ claims are anything other than ones for breach of the Contract to Purchase and the Escrow Agreement. As we previously observed, a tort claim is not viable in the absence of an independent duty outside the contract or where the tort damages are the same as would lie for breach of contract. The case before us simply involves a situation where two parties contracted, and due to various factors, including poor communication and poor phrasing, their expectations were not met.
{¶ 125} In view of the above discussion, the trial court did not err in granting summary judgment to DCH on the fraudulent inducement claims asserted by Defendants. Accordingly, Defendants’ sole assignment of error is overruled.
{¶ 126} As a final matter, we note that in a footnote, Defendants complain that they never received a copy of our December 12, 2018 decision limiting the briefs to the claims on which summary judgment was granted, nor did they receive a copy of our August 16, 2018 show cause order requiring the parties to answer whether the trial court‘s order was so limited. See Defendants’ Brief, p. 2, fn. 1. According to Defendants, the clerk is required under
{¶ 127} This issue relates to events that occurred a year ago, and our review of the docket indicates that Defendants were in no way prejudiced, as they did respond to our show cause order and did appeal to the Supreme Court of Ohio. More importantly, if Defendants are concerned with the clerk‘s implementation of the rule, they should address that with the clerk.
{¶ 128} Finally, under well-established authority, parties are responsible for checking the docket and keeping themselves informed of the progress of their cases. E.g., Pearl v. J&W Roofing & Gen. Contracting, 2d Dist. Montgomery No. 16045, 1997 WL 86415, *1 (Feb. 28, 1997); Bank of Am., N.A. v. Shultz, 2d Dist. Clark No. 2012-CA-70, 2013-Ohio-2567, ¶ 14, fn. 4. As a result, we decline Defendants’ request.
V. Conclusion
{¶ 129} Defendants’ sole assignment of error and Plaintiffs’ sole cross-assignment of error having been overruled, the judgment of the trial court is affirmed.
HALL, J. and TUCKER, J., concur.
Copies sent to:
Jeffrey P. McSherry
Bryan M. Smeenk
Paul T. Saba
Jeffrey M. Nye
Hon. Mary E. Montgomery
