Lead Opinion
SUBSTITUTE MAJORITY OPINION
The majority and dissenting opinions issued on January 11, 2011 are withdrawn, and the panel issues the following substitute majority and dissenting opinions.
In this subrogation action, Lexington Insurance Co. sued Daybreak Express, Inc. in connection with property damage that occurred during the interstate shipment of
The trial court found that (1) Lexington proved all elements of a Carmack Amendment claim under 49 U.S.C. § 14706 (2006); (2) the claim was not time-barred under the applicable New Jersey statute of limitations; and (3) Lexington sustained damages of $85,800. The trial court signed a final judgment awarding damages and attorney’s fees, and Daybreak appealed. We reverse and render a take-nothing judgment in favor of Daybreak because Lexington’s Carmack Amendment claim is barred by limitations under Texas law.
BACKGROUND
Burr hired J. Supor & Sons Trucking & Rigging Co. to transport Burr’s equipment from New Jersey to Texas. Supor issued a bill of lading for the shipment, which it referred to Daybreak, a New Jersey trucking company. Supor’s personnel loaded the equipment onto Daybreak’s truck, and Daybreak transported the equipment to Daybreak’s New Jersey terminal. Daybreak transferred the bill of lading to its sister company, which then transferred it to T. Orr Trucking, Inc. Orr transported the equipment to Texas. The equipment arrived in Texas on August 15, 2002 in a damaged condition.
Burr presented a written claim for damages to Daybreak on September 11, 2002. Daybreak hired an independent adjuster from Cunningham Lindsey to investigate Burr’s claim. The adjuster submitted a report to Daybreak reflecting that the adjuster and Burr had agreed to value Burr’s claim at $166,655. Burr contended that this valuation was a settlement agreement. Daybreak contacted Burr on February 6, 2008 and informed Burr that Daybreak would pay only $5,420 for the claim.
Burr also filed a damage claim with Supor. Supor paid Burr $5,000 on November 13, 2003 to meet its insurance policy deductible. Supor’s insurer, Lexington, paid Buit $87,500 to settle the claim on November 18,2003.
Lexington filed a subrogation suit against Daybreak in Texas state court on January 6, 2005. In its original petition, Lexington asserted only a single state law breach of contract claim based on the alleged settlement agreement between Burr and Daybreak. The original petition recited that Daybreak delivered a shipment to Burr in Texas on August 15, 2002; that a bill of lading had been issued by Supor and consigned to Daybreak; and that “[ujpon arrival in Houston, it was discovered the equipment had been damaged in transit.” Lexington alleged that “it issued a policy of cargo insurance to J. Supor and Sons Trucking and Rigging Co., which provided coverage to Burr for its cargo the subject of this lawsuit.” Lexington further alleged, “When Daybreak breached its settlement agreement with Burr, Burr submitted the claim to Plaintiff, and Plaintiff subsequently reimbursed the loss suffered by Burr under its policy of insurance.” Lexington asserted that it “became subro-gated to the rights of Burr in both contract and equity.” Lexington additionally asserted that “it is subrogated to the causes of action of Burr both in contract and tort, and may prosecute the claim of Burr against Daybreak.”
Daybreak removed the case to federal court, arguing that Lexington’s claim “is a civil action pending in the State Court against a common carrier to recover damages for alleged delay, loss, or injury to a shipment arising under the Interstate Commerce Act.” See 49 U.S.C. § 14706. Lexington filed a motion to remand and contended that federal question jurisdiction under 28 U.S.C. §§ 1331 and 1441(b) did not encompass the single state law breach of contract action pleaded in its
United States District Judge Sim Lake concluded that “Lexington does not seek to impose liability on Daybreak for damages arising from the interstate transport of property.” Id. at 541. “Instead, Lexington seeks to enforce an agreement it alleges Daybreak entered into in order to settle claims for damages to a shipment of electrical equipment.” Id. “Resolution of this contract claim does not turn on the rights and responsibilities of Daybreak as a carrier in interstate commerce.” Id. The federal district court also observed as follows: “Lexington seeks to recover in contract not for loss or damage to the electrical equipment, but rather for breach of Daybreak’s alleged promise to settle those claims for the specified sum.” Id. at 541 n. 8. Accordingly, the federal district court remanded this case on June 24, 2005.
More than two years after Daybreak rejected the valuation of Burr’s claim, Lexington added claims for breach of contract, indemnity, contribution, and unjust enrichment arising from the payment it made to Burr on Supor’s behalf. Lexington pleaded for the first time on May 4, 2007 that Daybreak is liable for damages under the Carmack Amendment.
Following a bench trial, the trial court concluded that the “New Jersey statute of limitations is applicable and therefore [Lexington’s] claim is not time barred.” The trial court found that the equipment was “delivered to the initial carrier in good condition” and was “damaged before delivery” to its final destination, which entitles Lexington to damages under its Carmack Amendment claim.
ANALYSIS
I. Applicable Limitations Period
Daybreak contends on appeal that Lexington’s claim is barred by limitations. As subrogee, Lexington stepped into Burr’s shoes and is subject to any limitations defense that would apply to Burr. See, e.g., Guillot v. Hix,
A carrier’s liability for damage to an interstate shipment is a matter of federal law. Mo. Pac. R.R. Co., 377 U.S. at
A carrier providing transportation or service ... shall issue a receipt or bill of lading for property it receives for transportation under this part. That carrier and any other carrier that delivers the property and is providing transportation or service ... are liable to the person entitled to recover under the receipt or bill of lading. The liability imposed under this paragraph is for the actual loss or injury to the property caused by (A) the receiving carrier, (B) the delivering carrier, or (C) another carrier over whose line or route the property is transported....
49 U.S.C. § 14706(a). A state court has subject matter jurisdiction to adjudicate a claim under the Carmack Amendment. See id. § 14706(d)(3).
Parties frequently establish the time period for filing suit under the Carmack Amendment by agreement. See generally Shao v. Link Cargo (Taiwan) Ltd.,
Daybreak asserts that the Carmack Amendment itself establishes a two-year statute of limitations. See 49 U.S.C. § 14706(e). Alternatively, Daybreak argues that a “catch-all” four-year limitation period applies. See 28 U.S.C. § 1658(a) (2006). Daybreak contends that Lexington’s suit is untimely under either statute of limitations because the Carmack Amendment claim Lexington first pleaded on May 4, 2007 (1) was not brought within two or four years of Daybreak’s disallowance of the written claim for damages on February 6, 2003; and (2) does not relate back to Lexington’s claim for breach of settlement agreement filed on January 6, 2005.
We reject Daybreak’s contention that federal law provides the applicable limitations period in the absence of an agreed limitations period. Daybreak relies on subsection (e), which states that “[a] carrier may not provide by rule, contract, or otherwise ... a period of less than 2 years for bringing a civil action against it under this section.” 49 U.S.C. § 14706(e). But this section does not establish a limitations period; instead, it provides only that carriers cannot establish by contract a limitations period of less than two years. See La. & W.R. Co. v. Gardiner,
The four-year “catch-all” limitations period imposed by 28 U.S.C. § 1658 does not apply because (1) the four-year limitations period applies to claims made possible by post-1990 legislative enactments; and (2) Carmack Amendment claims against motor carriers have been authorized since 1935. See Jones v. R.R. Donnelley & Sons Co.,
When the governing federal statute does not provide a limitations period, we “borrow” the most closely analogous state limitations period. See Graham Cnty. Soil & Water Conservation Dist. v. U.S. ex rel. Wilson,
The first candidate is the New Jersey statute of limitations, which provides that an “action at law for ... any tortious injury to ... personal property ... or for recovery upon ... liability, express or implied” must be brought not later than six years after the day the cause of action accrues. N.J. Stat. Ann. § 2A:14-1 (West 2000). The second candidate is the Texas statute of limitations, which provides that “a person must bring suit for ... injury to ... the property of another ... not later than two years after the day the cause of action accrues.” Tex. Civ. Prac. & Rem. Code Ann. § 16.003(a) (Vernon 2002). This circumstance adds a conflict of law component to the process of determining the applicable statute of limitations.
The case was tried to the bench on October 18, 2007. After both sides rested and while closing argument was being presented, the trial court questioned Lexington’s counsel about whether the statute of limitations is substantive or procedural for conflict of law purposes. The trial court stated, “In conflicts law you have to decide whose law you’re applying and then you have to analyze procedure versus substance.” In response to the trial court’s questioning, Lexington’s counsel argued that the statute of limitations is substantive law for conflict of law purposes in this case and that New Jersey law should apply-
Lexington reiterated this argument in Plaintiffs Post-Trial Brief filed on October 29, 2007. Lexington further argued that “any amended claims asserted in this lawsuit relate[ ] ... back to the original date of filing of suit of January 5, 2005.... ” Daybreak also filed post-trial briefing on October 29, 2007, in which it contended that (1) Lexington’s claim is barred under a two-year or a four-year limitations period; (2) “[t]he claims based in federal law arise from wholly separate facts and circumstances than the state law breach of contract claim;” and (3) “Judge Sim Lake made a clear distinction between the federal claims for property damage and the state law claims for breach of contract.” Lexington filed a reply on November 1, 2007; among other things, Lexington argued that its Carmack Amendment claim would relate back to its original petition filed in 2005 “[i]f a Texas statute of limitations applies.... ” Lexington also argued that “Judge Lake merely held that Plaintiff was only asserting a breach of contract claim at the time, not that the contract claim was ‘wholly based on a new, distinct, or different transaction or occurrence’” (original emphasis).
As it did in the trial court, Lexington argues on appeal that the New Jersey statute of limitations is substantive law that should apply under the “most significant relationship” test used in Texas, the forum state, to decide conflict of law questions. See Hughes Wood Prods., Inc. v. Wagner,
Determining which state’s statute of limitations governs is a question of law for the court to decide de novo. See, e.g., Hughes Wood,
Texas law generally treats statutes of limitations as procedural in nature. See California v. Copus,
Accordingly, the Texas two-year limitations period applies here because it is a procedural rule of the forum state. See Tex. Civ. Prac. & Rem.Code Ann. § 16.003; see also Arkoma Basin,
The analysis thus far has focused on the length of the statute of limitations. The next step is to address accrual.
When it becomes necessary to borrow a state limitations period for a federal cause of action, only that portion necessary to fill the gap left by Congress is to be borrowed. M.I.S. Eng’g v. U.S. Express Enter.,
Lexington filed its original petition on January 6, 2005, within two years of the date on which Daybreak disallowed the damages claim. But Lexington sued only for breach of the alleged settlement agreement in its original petition; the Carmack Amendment claim was not asserted until 2007. To determine whether Lexington’s Carmack Amendment claim was timely, we must decide next whether it “relates back” to the claim for breach of an alleged settlement agreement filed before expiration of the limitations period.
III. Relation Back
We look to state law to determine how to apply a state limitations period to an action accruing under federal law unless the applicable limitations rule would be inconsistent with federal law. See Bd. of Regents of the Univ. of State of N.Y. v. Tomanio,
Because federal courts would apply Texas relation-back rules in deciding a Car-
Under Texas law, the test for determining whether a claim asserted in an amended pleading filed after limitations has run relates back to an earlier, timely filed claim focuses on “whether the cause of action alleged in the amended petition is wholly based upon and grows out of a new, distinct, or different transaction or occurrence.” Meisler v. Republic of Tex. Sav. Ass’n,
Here, the Carmack Amendment claim rests on a transaction that centered on the transport of electrical equipment by a common carrier from New Jersey to Texas; this transaction focuses on details of the transport by Supor, Daybreak, Daybreak’s sister company, and Orr across state lines that resulted in $85,800 in damages. In contrast, the breach of contract claim rests on a wholly separate transaction that centered on an alleged settlement agreement; this separate transaction focuses on negotiations between Burr and Cunningham Lindsey as Daybreak’s purported agent leading to the alleged $166,655 settlement. On this record, Lexington’s 2007 Carmack Amendment claim is “wholly based on a new, distinct or different transaction” that is independent of the settlement agreement upon which Lexington predicated its 2005 breach of contract claim. Therefore, Lexington’s Carmack Amendment claim does not relate back to the breach of contract claim asserted in its original petition. See Meisler,
The conclusion that the Carmack Amendment claim and the claim for breach of a purported settlement agreement involve wholly distinct transactions comports with Lexington’s characterization of its claims in its court filings. Lexington successfully argued in federal court that the Burr-Daybreak settlement transaction was wholly distinct from the underlying transaction to transport equipment — and, therefore, beyond the reach of complete preemption under the Carmack Amendment: “The sole cause of action asserted by Lexington is for breach of the settlement agreement.... Lexington has not pled the underlying cause of action for which the settlement was reached; in fact if the underlying cause of action is for negligence, it would be time-barred by the Texas two-year statute of limitations .... ” (original emphasis). The federal district court agreed with Lexington. “Because this is not a suit to recover for loss or damage to property against a carrier, but rather one to enforce a settlement agreement, the ease will be remanded to state court.” Lexington Ins. Co.,
The determination that interstate transportation of goods by a common carrier is a transaction distinct from a purported settlement agreement does not depend on an estoppel theory or on Lexington having asserted inconsistent positions. Instead, this determination flows from the conclusion that Lexington’s claim for breach of the purported settlement agreement was not subject to complete preemption under the Carmack Amendment — and, therefore, was not removable to federal court based on federal question jurisdiction under 28 U.S.C. § 1441(b). See Lexington Ins. Co.,
In reaching this holding, the federal district court cited Fifth Circuit case law discussing removability and the scope of complete preemption under the Carmack Amendment. Id. at 540 (citing Hoskins v. Bekins Van Lines,
Although a preemption defense provides no basis for removal under 28 U.S.C. § 1441(b), “the Supreme Court has construed certain federal statutes as ‘not only preempting state law but also authorizing removal of actions that sought relief only under state law.’ ” Id. at 773 (quoting Beneficial Nat’l Bank v. Anderson,
Given this backdrop, Lexington cannot convincingly argue on appeal that “Lexington’s originally filed claim for breaching an alleged agreement to pay for cargo damage was not ‘wholly based on a new, distinct, or different transaction or occurrence’ from the cargo claim itself’ (original emphasis). The expansive reach of complete preemption under the Carmack Amendment means that any cause of action arising from the interstate transportation of goods by a common carrier “ ‘is either wholly federal or nothing at all’” regardless of how it is labeled. Hoskins,
Because Lexington’s 2007 Carmack Amendment claim arises from a distinct transaction and does not relate back to the 2005 claim for breach of an alleged settlement agreement, the Carmack Amendment claim is barred by the applicable two-year limitations period. See Tex. Civ. Prac. & Rem.Code Ann. § 16.003; see also Carpenter,
CONCLUSION
Because the only claim supported by the trial court’s findings is barred by limitations, we must reverse the judgment of the trial court and render a take-nothing judgment in favor of Daybreak.
CHRISTOPHER, J., dissenting.
Notes
. These findings were recited in the final judgment. We consider findings of fact recited in the judgment unless they are supplanted by separately filed findings. See In re C.A.B.,
. Daybreak claims that its tariff establishes a limitation period because "it reiterated the Carmack Amendment's two-year statute of limitations by reference....” We need not address whether the tariff applies or incorporates a statute of limitations under the Car-mack Amendment because we conclude that the Carmack Amendment establishes no statute of limitations.
. Relying on Computer Assoc. Int’l, Inc. v. Altai, Inc.,
Dissenting Opinion
substitute dissenting opinion.
I would hold that the Carmack-Amendment claim is not barred by the Texas two-year statute of limitations, because under section 16.068 of the Civil Practices and Remedies Code, the amended pleading of May 4, 2007 relates back to the original timely-filed pleading of January 6, 2005. See Tex. Crv. Prac. & Rem.Code § 16.068 (West 2008). I therefore respectfully dissent.
Section 16.068 of the Civil Practices and Remedies Code is designed to protect litigants from loss of their claims by a plea of limitations, and as a remedial statute, it should be liberally construed. Milestone Props., Inc. v. Federated Metals Corp.,
If a filed pleading relates to a cause of action ... that is not subject to a plea of*807 limitation when the pleading is filed, a subsequent amendment or supplement to the pleading that changes the facts or grounds of liability or defense is not subject to a plea of limitation unless the amendment or supplement is wholly based on a new, distinct, or different transaction or occurrence.
(emphasis added).
The majority concludes that the breach-of-settlement claim originally pled rests on a “wholly different transaction” from the Carmack-Amendment claim. The original pleading described the fact of the original shipment; that the shipment was damaged in transit; and that Burr sustained property damages in the form of the lost value of the equipment. Lexington also pled that it was subrogated to the rights of Burr in both contract and equity and that it was subrogated to Burr’s causes of action in both contract and tort. While it is true that the only cause of action pled in the original petition was for breach of the settlement contract, section 16.068 specifically allows for changes in facts and grounds of liability. If, as Daybreak contended, there was no settlement agreement, then Lexington/Burr retained its original tort claim.
The majority, without saying so explicitly, seems to be applying an estoppel argument against Lexington because of Lexington’s response to removal of its case to federal court. But, Daybreak has taken the same inconsistent positions. Daybreak removed the case to federal court arguing that Lexington asserted a Carmack-Amendment claim rather than a breach-of-contract claim in the original petition, but Daybreak now argues that the Carmack-Amendment claim is a wholly-new transaction and does not relate back to the same original petition that it removed to federal court.
The majority focuses on the remand opinion and discusses federal preemption at length, concluding that Lexington’s argument is foreclosed. The remand opinion on lack of subject-matter jurisdiction is not subject to appellate review even if clearly erroneous. Dahiya v. Talmidge Int’l, Ltd., 371 F.Sd 207, 209 (5th Cir.2004). It has no precedential value on a defense of preemption. Smith v. Tex. Children’s Hosp.,
The district court’s opinion was based on the pleading before it, in which the claim was styled as one for breach of contract. That ruling did not foreclose amendments to Lexington’s pleading, and it does not address the state-law issue as to whether or not the Carmack-Amendment claim is a wholly-new, distinct, or different transaction or occurrence within the meaning of section 16.068. Moreover, under federal law, a party may remove a lawsuit based on an amended pleading. 28 U.S.C. § 1446(b). Daybreak could have removed the case to federal court again after Lexington amended its pleading to assert the Carmack-Amendment claim, but it chose not to do so.
In the original petition, Lexington described the damage to Burr’s equipment during transit as the occurrence that was the subject of the settlement agreement. After Daybreak denied that a settlement agreement existed, Lexington, as Burr’s subrogee, asserted Burr’s tort cause of action under the Carmack Amendment.
Because the Carmack-Amendment claim is not barred by limitations, I therefore would address the remaining issues not reached by the majority.
